Mumbai Coastal Road Project to Be Completed by End of 2023
ROADS & HIGHWAYS

Mumbai Coastal Road Project to Be Completed by End of 2023

The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections.

Part 1 cost escalation

M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023.

Part 2 cost escalation

M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023.

Part 3 cost escalation

Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023.

According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained.

See also:
Mumbai to build Bowstring Bridge to connect coastal road
BMC completes Mumbai's final undersea tunnel for Coastal Road Project


The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections. Part 1 cost escalation M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023. Part 2 cost escalation M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023. Part 3 cost escalation Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023. According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained. See also: Mumbai to build Bowstring Bridge to connect coastal road BMC completes Mumbai's final undersea tunnel for Coastal Road Project

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->