Mumbai Coastal Road Project to Be Completed by End of 2023
ROADS & HIGHWAYS

Mumbai Coastal Road Project to Be Completed by End of 2023

The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections.

Part 1 cost escalation

M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023.

Part 2 cost escalation

M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023.

Part 3 cost escalation

Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023.

According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained.

See also:
Mumbai to build Bowstring Bridge to connect coastal road
BMC completes Mumbai's final undersea tunnel for Coastal Road Project


The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections. Part 1 cost escalation M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023. Part 2 cost escalation M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023. Part 3 cost escalation Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023. According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained. See also: Mumbai to build Bowstring Bridge to connect coastal road BMC completes Mumbai's final undersea tunnel for Coastal Road Project

Next Story
Infrastructure Transport

Maharashtra Approves Rs 9.31 Bn for Bhandara–Gadchiroli Expressway

The Maharashtra cabinet, chaired by Chief Minister Devendra Fadnavis, has approved the revised design and funding of Rs 9.31 billion for the Bhandara–Gadchiroli controlled access expressway, a project expected to enhance connectivity across Vidarbha.The 94.2 km expressway, to be implemented by the Maharashtra State Road Development Corporation (MSRDC), will cut the Bhandara–Gadchiroli distance by 23 km and reduce travel time to 1.5 hours. Of the sanctioned funds, Rs 5.34 billion has been earmarked for project work and Rs 3.96 billion for interest, with land acquisition to begin shortly.The..

Next Story
Infrastructure Energy

Waaree Energies to Offload 14.66% Stake in Indosolar via OFS

Waaree Energies, promoter of Indosolar, will sell up to 61 lakh equity shares, representing 14.66 per cent of Indosolar’s paid-up capital, through an Offer for Sale (OFS) on stock exchanges. The move is aimed at meeting SEBI’s minimum public shareholding (MPS) norms.The OFS will open for non-retail investors on September 18 (T-day), followed by retail investors on September 19 (T+1 day), through a dedicated trading window. Each share carries a face value of Rs 10.Antique Stock Broking has been appointed as the seller’s broker to manage the transaction, ensuring compliance and transparenc..

Next Story
Infrastructure Energy

Gujarat Adds 6,632 MW Renewable Capacity in 2025

Gujarat has added 6,632 MW of renewable energy capacity between April and August 2025, taking its total installed capacity to 39,275.7 MW.The surge is driven by large-scale solar parks, hybrid solar-wind projects, and enhanced transmission infrastructure, further cementing Gujarat’s position as a renewable energy leader.Officials said the expansion supports the state’s sustainable energy goals while strengthening grid reliability and ensuring long-term energy security.News source: Bharat Aawaz ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?