+
Mumbai Coastal Road Project to Be Completed by End of 2023
ROADS & HIGHWAYS

Mumbai Coastal Road Project to Be Completed by End of 2023

The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections.

Part 1 cost escalation

M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023.

Part 2 cost escalation

M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023.

Part 3 cost escalation

Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023.

According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained.

See also:
Mumbai to build Bowstring Bridge to connect coastal road
BMC completes Mumbai's final undersea tunnel for Coastal Road Project


The enormous Mumbai Coastal Road project will now be completed by the end of 2023, having missed its original timetable. The BMC has told RTI activist Anil Galgali that a punishment of Rs 31 crore has been imposed on the project contractors, who have suffered a cost overrun of Rs 226 crores. Despite this, the contractors have already received 65 percent of their dues. Galgali had requested project details from the BMC. The BMC informed him that the project's work is separated into three sections. Part 1 cost escalation M/s Larsen & Toubro has been awarded the work from Priyadarshini Park to Baroda Palace under Part 1, and the original cost has increased by Rs 99.79 crores. The initial investment was estimated to be Rs 3,505 crores. The contractor had received roughly Rs 2,286 crore as of June 20, 2023. So far, a fine of Rs 8.57 crores has been issued for this job. The work was scheduled to be completed on October 12, 2022, however the deadline has been pushed back to September 10, 2023. Part 2 cost escalation M/s HCC HDC has been awarded the work from Baroda Palace to the southern end of the Bandra Worli Sea Link under Part 2, with an increase in the initial cost of Rs 62.25 crores. The initial investment was estimated to be Rs 2,126 crores. The contractor had received roughly Rs 1193 crore as of June 20, 2023. This work has resulted in a fine of Rs 15.37 crores. This section was supposed to be finished on October 15, 2022. The deadline, however, has been extended, and the project will now be completed by October 7, 2023. Part 3 cost escalation Part 3 work has been given to M/s Larsen & Toubro, and the initial cost has increased by Rs 63.83 crores. The initial cost was projected to be Rs 2,798 crores. The contractor had been paid around Rs 2,160 crore as of June 20, 2023. For this work, a punishment of Rs 7.25 crores was imposed. The planned completion date was October 12, 2022, but the deadline has been pushed out to November 26, 2023. According to Galgali, the penalty imposed is relatively minor given the cost rise. Contractors work hard to secure such ambitious projects, but once they do, they fail to finish them on time. As a result, the cost rises, and the higher spending is covered by monies raised by taxpayers, he explained. See also: Mumbai to build Bowstring Bridge to connect coastal road BMC completes Mumbai's final undersea tunnel for Coastal Road Project

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code