NHAI Clears Land Hurdle for Eight-Lane Corridor Near Pune
ROADS & HIGHWAYS

NHAI Clears Land Hurdle for Eight-Lane Corridor Near Pune

The National Highways Authority of India (NHAI) has completed land acquisition, including paper possession, for the long-pending Nashik Phata-Khed (Rajgurunagar) elevated corridor near Pune. The eight-lane project is intended to ease congestion on the Pune-Nashik highway, with construction likely to begin within six to eight weeks.

The letter of award for the project was issued to the selected bidder on 28 October. NHAI officials said the contractor must first secure financing from banks or other financial institutions, execute the required agreement and complete the formal work order process before construction can start. This sequence is expected to take about one-and-a-half to two months.

The project faced delays because of repeated changes to its alignment and planning. The original 2019-20 tender was cancelled because of the Chakan metro project. The route was initially planned as a six-lane road with service lanes, underpasses and flyovers, but was later redesigned as an elevated corridor following directions from the Union minister, creating additional land acquisition requirements.

The Maharashtra government approved a resolution on 17 July 2025 providing support for GST reimbursement, land acquisition expenses and royalty concessions. A meeting held on 14 July 2026 considered funding the land acquisition through the Maharashtra State Road Development Corporation and the state Public Works Department’s national highways wing.

Until the new corridor is built, NHAI will continue addressing potholes, waterlogging, maintenance and traffic management issues on the existing NH-60. It will also oversee signage and lighting along the route. The authority expects the project to move ahead after the remaining contractual steps and has indicated that construction could be completed within three years if there are no further delays.

The National Highways Authority of India (NHAI) has completed land acquisition, including paper possession, for the long-pending Nashik Phata-Khed (Rajgurunagar) elevated corridor near Pune. The eight-lane project is intended to ease congestion on the Pune-Nashik highway, with construction likely to begin within six to eight weeks. The letter of award for the project was issued to the selected bidder on 28 October. NHAI officials said the contractor must first secure financing from banks or other financial institutions, execute the required agreement and complete the formal work order process before construction can start. This sequence is expected to take about one-and-a-half to two months. The project faced delays because of repeated changes to its alignment and planning. The original 2019-20 tender was cancelled because of the Chakan metro project. The route was initially planned as a six-lane road with service lanes, underpasses and flyovers, but was later redesigned as an elevated corridor following directions from the Union minister, creating additional land acquisition requirements. The Maharashtra government approved a resolution on 17 July 2025 providing support for GST reimbursement, land acquisition expenses and royalty concessions. A meeting held on 14 July 2026 considered funding the land acquisition through the Maharashtra State Road Development Corporation and the state Public Works Department’s national highways wing. Until the new corridor is built, NHAI will continue addressing potholes, waterlogging, maintenance and traffic management issues on the existing NH-60. It will also oversee signage and lighting along the route. The authority expects the project to move ahead after the remaining contractual steps and has indicated that construction could be completed within three years if there are no further delays.

Related Stories

Gold Stories

Next Story
Real Estate

Emaar India Launches Grade-A Office Tower in Gurugram

Emaar India, the Indian arm of Dubai-based Emaar Properties, recently launched Emaar Business Square, a Grade-A commercial tower in Sector 65, Gurugram. Pre-certified IGBC Platinum, the development offers flexible office spaces, sustainable building features and ground-floor retail facilities.The launch comes amid growing demand for premium office spaces in Gurugram. According to Cushman & Wakefield, Gurugram accounted for 63 per cent of Delhi NCR’s office leasing during the July–September quarter of 2026. The region recorded office leasing of 3.8 million sq ft during the quarter, taki..

Next Story
Infrastructure Urban

SFC Environmental Technologies Posts 80.5% Revenue Growth in H1 FY27

SFC Environmental Technologies recently announced its first financial results as a listed company, reporting an 80.5 per cent year-on-year (YoY) increase in consolidated revenue from operations to Rs 2.97 billion for the half year ended 30 September 2026 (H1 FY27).The company’s EBITDA increased by 86.9 per cent YoY to Rs 200.5 million, with an EBITDA margin of 6.8 per cent. Profit after tax (PAT) rose to Rs 35.8 million from Rs 0.4 million in H1 FY26. The company's order book stood at Rs 16.56 billion as of 30 September 2026, representing approximately 2.1 times its FY26 revenue.For Q2 FY27,..

Next Story
Infrastructure Urban

IGBC, University of Mumbai Partner to Advance Green Education

The Indian Green Building Council (IGBC), part of the Confederation of Indian Industry (CII), and the University of Mumbai recently signed a Memorandum of Understanding (MoU) to strengthen green education and develop skilled professionals for India’s sustainable built environment sector. The agreement was signed during the Green Education Conclave 2026 at the university’s Kalina campus.Under the partnership, both institutions will jointly develop a specialised course on ‘Green Built Environment’ for students pursuing civil, electrical, environmental and mechanical engineering, as well ..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code