Odisha constructs 272.75 km rural roads under PMGSY in FY22
ROADS & HIGHWAYS

Odisha constructs 272.75 km rural roads under PMGSY in FY22

The Odisha government is lagging in the schedule of completing the development of 2,700 km for 2021-22.

It has managed to build just 272.75 km of rural roads under the flagship Pradhan Mantri Gram Sadak Yojana (PMGSY).

Recognised as a best-performing state in the development of rural roads, Odisha has attained development of 62,465 km by rendering all-weather connectivity to 16,301 out of 16,382 feasible habitations.

Road construction under PMGSY for the current financial year has remained a non-starter in Bhadrak, Balasore, Nabarangpur, Jagatsinghpur and Sonepur districts, while the progress is critically low in many others. There has been notable progress in tribal-dominated districts of Malkangiri (44.26 km), Kandhamal (20 km), Koraput (60.71 km) and Bargarh (40 km).

The state government has rendered connectivity to 146 habitations out of the 326 targeted for the current financial year. With an unused balance of Rs 1,116 crore as of April 1, 2021, the centre has made a budgetary provision of Rs 666.67 crore in FY22 out of which the state’s share is Rs 266.67 crore.

The Ministry of Rural Development has suggested to the state government about the falling of seven roads, five in Cuttack district and two in Kalahandi, from the list of approved projects.

Work contracts of these projects, approved in 2017-18, have not been granted by the State Rural Road Development Agency (SRRDA) despite repeated time extensions by the Ministry of Rural Development (MoRD).

Image Source

Also read: J&K to develop 4,500 km of roads under PMGSY this year

The Odisha government is lagging in the schedule of completing the development of 2,700 km for 2021-22. It has managed to build just 272.75 km of rural roads under the flagship Pradhan Mantri Gram Sadak Yojana (PMGSY). Recognised as a best-performing state in the development of rural roads, Odisha has attained development of 62,465 km by rendering all-weather connectivity to 16,301 out of 16,382 feasible habitations. Road construction under PMGSY for the current financial year has remained a non-starter in Bhadrak, Balasore, Nabarangpur, Jagatsinghpur and Sonepur districts, while the progress is critically low in many others. There has been notable progress in tribal-dominated districts of Malkangiri (44.26 km), Kandhamal (20 km), Koraput (60.71 km) and Bargarh (40 km). The state government has rendered connectivity to 146 habitations out of the 326 targeted for the current financial year. With an unused balance of Rs 1,116 crore as of April 1, 2021, the centre has made a budgetary provision of Rs 666.67 crore in FY22 out of which the state’s share is Rs 266.67 crore. The Ministry of Rural Development has suggested to the state government about the falling of seven roads, five in Cuttack district and two in Kalahandi, from the list of approved projects. Work contracts of these projects, approved in 2017-18, have not been granted by the State Rural Road Development Agency (SRRDA) despite repeated time extensions by the Ministry of Rural Development (MoRD). Image Source Also read: J&K to develop 4,500 km of roads under PMGSY this year

Next Story
Infrastructure Transport

Cabinet Approves Key Highway and Rail Projects in Bihar Region

The Union Cabinet on Wednesday approved the four-laning of the 84.2-km Mokama-Munger section of the Buxar-Bhagalpur high-speed corridor, a key industrial region in poll-bound Bihar. The Cabinet also sanctioned the doubling of the 177-km Bhagalpur-Dumka-Rampurhat railway line, which passes through Bihar, Jharkhand, and West Bengal, at a cost of Rs 31.7 billion.The Rs 44.5 billion highway project will be constructed under the hybrid annuity model, a variant of public-private partnership. The Mokama-Munger stretch was the only remaining two-lane section of the 363-km Buxar-Bhagalpur corridor. Fou..

Next Story
Infrastructure Transport

NGT Issues Notice on Bengaluru Twin Tunnel Project

The National Green Tribunal (NGT) on Wednesday issued notices in response to a petition filed by Bengaluru Praja Vedike and others, challenging the Bengaluru twin tunnel road project. Petitioners claim the project was “hastily announced” and bypassed mandatory environmental impact assessment procedures.Notices have been served to the Karnataka Government, Greater Bengaluru Authority, State Environment Impact Assessment Authority (SEIAA), Bengaluru Smart Infrastructure Ltd (B-SMILE), the Union Ministry of Environment, Forest and Climate Change, and project consultants.The 16.74-km twin-tube..

Next Story
Real Estate

India’s Residential Sales to Dip Slightly in FY26

Residential sales in India’s seven major cities are projected to decline by up to 3 per cent year-on-year in FY26 to 620–640 million square feet (msf), amid a moderation in sales velocity, according to ratings agency Icra.In FY25, sales stood at 643 msf, down 8 per cent YoY, following a sharp contraction in new launches and moderated demand in the affordable and mid-income segments. This slowdown came after the sector posted a robust compound annual growth rate of 26 per cent in area sales between FY22 and FY24.Icra noted: “Having seen a strong upcycle, the sector entered an equilibrium ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?