Timely completion of Jammu-Akhnoor 4-lane road project is uncertain
ROADS & HIGHWAYS

Timely completion of Jammu-Akhnoor 4-lane road project is uncertain

The much-hyped Jammu-Akhnoor 4-laning road project, which the Union Government approved in 2015, has missed numerous deadlines and won't be finished until 2023. In flagrant violation of the "contract agreement," the contractor, M/s Tarmat Limited, which has sublet work to local contractors, has failed to provide adequate and concrete service lanes along this road that is still being built.

When transporting patients from the Akhnoor, Khour, Jourian, Sunderbani, Nowshera, Kalakote, Rajouri, and Poonch areas to Jammu and back, commuters and especially the patients have been experiencing a great deal of difficulty due to the very bumpy and rough drive on the broken road patches at many locations along this under construction road. Even the District Magistrate of Jammu, the Regional Officer of the National Highway Authority of India (NHAI) in Jammu, and senior NHIDCL officials in the area have done nothing to stop the open breach of the contract agreement or the suffering of the road users.

Although the project was sanctioned in 2015 as part of the Prime Minister's Development Package Projects, according to official sources, actual ground work on the 26.35 km road project from Bhagwati Nagar/Canal Head Jammu up to Khati Chowk, a crossing near new Chenab bridge near Akhnoor town along bypass road, began in 2018.

Even though NHIDCL gave the contractor a completion deadline of July 31, 2023, the Rs 9.17 billion project known as NH-144-A is far from finished. Construction was done in stages, and because of bureaucracy and the slow speed of the contractors' work, many locations have not yet seen a resumption of the project. While work on five other bridges is progressing slowly, work on the bridge spanning Ranbir Canal at Suyya No. 1 (Bypass) has been abandoned for the past eight months.

The much-hyped Jammu-Akhnoor 4-laning road project, which the Union Government approved in 2015, has missed numerous deadlines and won't be finished until 2023. In flagrant violation of the contract agreement, the contractor, M/s Tarmat Limited, which has sublet work to local contractors, has failed to provide adequate and concrete service lanes along this road that is still being built. When transporting patients from the Akhnoor, Khour, Jourian, Sunderbani, Nowshera, Kalakote, Rajouri, and Poonch areas to Jammu and back, commuters and especially the patients have been experiencing a great deal of difficulty due to the very bumpy and rough drive on the broken road patches at many locations along this under construction road. Even the District Magistrate of Jammu, the Regional Officer of the National Highway Authority of India (NHAI) in Jammu, and senior NHIDCL officials in the area have done nothing to stop the open breach of the contract agreement or the suffering of the road users. Although the project was sanctioned in 2015 as part of the Prime Minister's Development Package Projects, according to official sources, actual ground work on the 26.35 km road project from Bhagwati Nagar/Canal Head Jammu up to Khati Chowk, a crossing near new Chenab bridge near Akhnoor town along bypass road, began in 2018. Even though NHIDCL gave the contractor a completion deadline of July 31, 2023, the Rs 9.17 billion project known as NH-144-A is far from finished. Construction was done in stages, and because of bureaucracy and the slow speed of the contractors' work, many locations have not yet seen a resumption of the project. While work on five other bridges is progressing slowly, work on the bridge spanning Ranbir Canal at Suyya No. 1 (Bypass) has been abandoned for the past eight months.

Next Story
Real Estate

Heena Lalwani Buys Rs 1.13 Billion Juhu Apartment

Heena Lalwani, promoter of Aatman Innovations Private Limited, has purchased a luxury apartment worth Rs 1.13 billion in Mumbai’s upscale Juhu locality, according to property registration documents accessed by Zapkey.com.The 9,862 sq ft apartment, located on the 10th floor of Lodha Developers’ Avalon Tower, was acquired at Rs 115,000 per sq ft and comes with five car parking spaces. The deal, registered on 18 August 2025, also included the payment of Rs 68 million in stamp duty and a Rs 30,000 registration fee.Lodha Developers did not respond to queries regarding the transaction, while the..

Next Story
Real Estate

Godrej Buys KPHB Land for Rs 7 Billion in E-Auction

An acre of prime land in Kukatpally Housing Board (KPHB), Hyderabad, was auctioned for Rs 7 billion, with the Telangana Housing Board generating Rs 5.47 billion from the sale of 7.8 acres through e-auction on 20 August 2025.The auction notification was issued last month, attracting bids from Godrej Properties, Aurobindo Realty, Prestige Estates, and Ashoka Builders, according to Board vice-chairman V.P. Gautham. With an offset price of Rs 4 billion per acre, the three-hour auction saw 46 bid increases, before Godrej Properties acquired the land.Revenue generated from the auction will be utilis..

Next Story
Real Estate

HMDA to Auction 93 Prime Plots in September

The Hyderabad Metropolitan Development Authority (HMDA) is preparing to conduct a three-day auction of prime open plots across Hyderabad, Rangareddy, and Medchal-Malkajgiri districts this September.According to official reports, the e-auction will take place on 17, 18, and 19 September, offering 93 plots. Of these, 70 are located in the Bachupally HMDA layout, with the remainder spread across Turkayamjal, Kokapet, Poppalguda, Chandanagar, Bairagiguda, Gandi Maisamma, Suraram, Medipally, and Bachupally village.The highest upset price has been fixed at Rs 175,000 per square yard for a land parce..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?