Two Jammu and Kashmir NABARD Road Projects Abandoned After Rs. 16.6 mn Spent
ROADS & HIGHWAYS

Two Jammu and Kashmir NABARD Road Projects Abandoned After Rs. 16.6 mn Spent

Two road projects taken up under the National Bank for Agriculture and Rural Development’s (NABARD) Rural Infrastructure Development Fund (RIDF) in Jammu and Kashmir were abandoned after Rs. 16.6 mn was spent on them, according to the Composite Audit Report. The audit found that the expenditure had remained partially unproductive because the projects were not completed.

The two projects were among 309 NABARD-funded projects examined during the audit. Together, they had a sanctioned cost of Rs. 50 mn. Their abandonment meant that the planned road connectivity was not fully provided to the rural population in the areas covered by the schemes.

The Main Road Choolan to Daragutliyan to Bosian Phase-I project in Uri, Baramulla, was sanctioned under RIDF-XXV. The project had an approved cost of Rs. 24.9 mn, against which Rs. 9.8 mn had been spent before the work was abandoned.

The audit attributed the abandonment of the Uri project to the contractor stopping work. The incomplete project therefore did not deliver the full connectivity intended under the rural infrastructure programme, despite the release and use of part of its sanctioned funds.

The second project was the construction and upgradation of the Hanga Dilmarg Road in Handwara, Kupwara. It was sanctioned under RIDF-XXII. The report identified both projects as examples where implementation did not result in the planned public asset, leaving the intended rural road benefits only partly realised.

The findings highlight the need for closer monitoring of projects funded through RIDF, particularly after work begins and payments are made. Ensuring that contractors continue work until completion would help protect public spending and improve the delivery of road connectivity in rural areas. The report’s observations cover the projects examined as part of the wider audit of NABARD-funded works in the Union territory.

Two road projects taken up under the National Bank for Agriculture and Rural Development’s (NABARD) Rural Infrastructure Development Fund (RIDF) in Jammu and Kashmir were abandoned after Rs. 16.6 mn was spent on them, according to the Composite Audit Report. The audit found that the expenditure had remained partially unproductive because the projects were not completed. The two projects were among 309 NABARD-funded projects examined during the audit. Together, they had a sanctioned cost of Rs. 50 mn. Their abandonment meant that the planned road connectivity was not fully provided to the rural population in the areas covered by the schemes. The Main Road Choolan to Daragutliyan to Bosian Phase-I project in Uri, Baramulla, was sanctioned under RIDF-XXV. The project had an approved cost of Rs. 24.9 mn, against which Rs. 9.8 mn had been spent before the work was abandoned. The audit attributed the abandonment of the Uri project to the contractor stopping work. The incomplete project therefore did not deliver the full connectivity intended under the rural infrastructure programme, despite the release and use of part of its sanctioned funds. The second project was the construction and upgradation of the Hanga Dilmarg Road in Handwara, Kupwara. It was sanctioned under RIDF-XXII. The report identified both projects as examples where implementation did not result in the planned public asset, leaving the intended rural road benefits only partly realised. The findings highlight the need for closer monitoring of projects funded through RIDF, particularly after work begins and payments are made. Ensuring that contractors continue work until completion would help protect public spending and improve the delivery of road connectivity in rural areas. The report’s observations cover the projects examined as part of the wider audit of NABARD-funded works in the Union territory.

Related Stories

Gold Stories

Next Story
Real Estate

Adani begins construction of Dharavi rehabilitation homes

Construction of rehabilitation homes for eligible Dharavi residents has commenced at the 22-acre Matunga railway site, following a Bhoomi Poojan ceremony performed by Pranav Adani, Director, Adani Enterprises (AEL). The project, being implemented by Adani Navbharat Developers (ANDPL), envisages 10 towers comprising 10,432 rehabilitation apartments and 1,379 commercial and industrial units.Under the in-situ rehabilitation scheme, eligible residents will receive homes measuring 350 sq ft. Residents from Sectors 6 and 1 will be accommodated at Matunga first, followed by nearly 4,500 apartments fo..

Next Story
Equipment

Seven Propel 470 HEV electric tippers go to work on coal haulage in Chhattisgarh

Propel EV, the electric mobility division of Propel Industries and India's No. 1 electric tipper brand, has deployed seven 470 HEV electric trucks with a leading coal-haulage contractor at one of India's largest opencast coal mines in Chhattisgarh. The trucks are in daily operation, moving coal on continuous haul cycles in one of the most demanding applications in Indian mining.Why Electric - and Why CoalCoal haulage runs round the clock: heavy loads, long haul cycles, steep ramps and abrasive dust. It is also where diesel hurts most. Engines run continuously, fuel is the largest single operat..

Next Story
Infrastructure Transport

UP Cabinet Approves Renaming Jewar Airport After PM Modi

The Uttar Pradesh Cabinet has approved a proposal to rename Noida International Airport at Jewar as Narendra Modi International Airport, Noida-Jewar. Chief Minister Yogi Adityanath announced the decision after a Cabinet meeting, saying the airport represented a major contribution to the state and would become Uttar Pradesh’s largest airport and a significant aviation hub. The greenfield airport’s foundation stone was laid by Prime Minister Narendra Modi on November 25, 2021. He inaugurated Phase 1 on March 28, 2026, and commercial flights began on June 15. The facility is being developed a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code