Bagalur Cross Metro station gets maiden pile cap in Bengaluru
RAILWAYS & METRO RAIL

Bagalur Cross Metro station gets maiden pile cap in Bengaluru

A notable milestone in KR Puram to Kempegowda International Airport (KIA) Line of Bengaluru was accomplished when the maiden pile cap was completed for the Bagalur Cross Metro station.

Six piles, which are concrete foundation elements that extend 25 m below the surface, are covered by the cap. In the 17 stations along this 37-km Phase-2B route, about 200 pile caps would be installed.

The contract for 15 stations on this line, broken up into three packages, has been given to NCC Ltd. Except for a 900 m section underground in the final stop at KIA, the station is mostly elevated.

A senior official told the media that this station is included in Package 2 of the Airport Line, which runs from Hebbal to Bagalur.

All three of the line's packages have the viaduct's pile cap, where the rails are laid. But this is the first time a station's cap has been prepared. Piling is a vital component of station building because underground work presents a huge obstacle.

The official informed that piling is essential for a sturdy foundation since it transfers the weight of the structures above to the soil depth. Each pile below the cap is spaced three metres apart from the others. There should be between 7 and 14 pile caps in a station.

If everything goes according to plan, it takes between 20 and 25 days to prepare a pile cap.

At Hebbal, Kodigehalli, Jakkur Cross, Yelahanka, and Bagalur Cross, this line features five elevated stations. Only at Bagalur Cross on March 27 was the first viaduct pile cover for the Airport Line put in place.

The official added the difficulties encountered at Bagalur Cross during piling by stating that the ground profile proved difficult. Extreme changes in the land below caused it to be quite high in some places and very low in others. It was difficult to bring them up to par, he continued.

While Package 3 from Bagalur Cross to KIA already has 30 pile caps ready for its bridge, Package One from KR Puram to Hebbal and Package 2 have a few pier caps prepared for the viaduct.

Image Source

Also read: BMRCL launches first U-girder on Outer Ring Road

A notable milestone in KR Puram to Kempegowda International Airport (KIA) Line of Bengaluru was accomplished when the maiden pile cap was completed for the Bagalur Cross Metro station. Six piles, which are concrete foundation elements that extend 25 m below the surface, are covered by the cap. In the 17 stations along this 37-km Phase-2B route, about 200 pile caps would be installed. The contract for 15 stations on this line, broken up into three packages, has been given to NCC Ltd. Except for a 900 m section underground in the final stop at KIA, the station is mostly elevated. A senior official told the media that this station is included in Package 2 of the Airport Line, which runs from Hebbal to Bagalur. All three of the line's packages have the viaduct's pile cap, where the rails are laid. But this is the first time a station's cap has been prepared. Piling is a vital component of station building because underground work presents a huge obstacle. The official informed that piling is essential for a sturdy foundation since it transfers the weight of the structures above to the soil depth. Each pile below the cap is spaced three metres apart from the others. There should be between 7 and 14 pile caps in a station. If everything goes according to plan, it takes between 20 and 25 days to prepare a pile cap. At Hebbal, Kodigehalli, Jakkur Cross, Yelahanka, and Bagalur Cross, this line features five elevated stations. Only at Bagalur Cross on March 27 was the first viaduct pile cover for the Airport Line put in place. The official added the difficulties encountered at Bagalur Cross during piling by stating that the ground profile proved difficult. Extreme changes in the land below caused it to be quite high in some places and very low in others. It was difficult to bring them up to par, he continued. While Package 3 from Bagalur Cross to KIA already has 30 pile caps ready for its bridge, Package One from KR Puram to Hebbal and Package 2 have a few pier caps prepared for the viaduct. Image Source Also read: BMRCL launches first U-girder on Outer Ring Road

Next Story
Infrastructure Transport

Gurgaon-Pataudi-Rewari Highway Set for Completion by December 2025

The National Highways Authority of India (NHAI) has set a new target to complete the four-lane Gurgaon-Pataudi-Rewari highway by December 2025, following a two-year delay.Originally planned in 2018 to upgrade the two-lane state highway into a national highway, the project is estimated to cost Rs 9 billion. Construction, which began in 2021, was initially scheduled for completion in November 2023. According to NHAI, around 70 per cent of the work is already complete, with two major structures still pending: a railway overbridge at Pahari village and a two-lane unidirectional flyover on Dwarka E..

Next Story
Infrastructure Transport

UP Plans Rs 900 Million Extensions to Hindon Elevated Road

The Uttar Pradesh state bridge corporation has prepared the detailed project report and cost estimates for two proposed extensions of the 10.3-km Hindon elevated road, officials said on Thursday. The road connects Raj Nagar Extension to UP-Gate near the east Delhi border, and the project is expected to cost around Rs 900 million.The two extensions, each 400 metres long, will be added to the existing elevated road to ensure smoother traffic flow. “One of the extensions will be from near the Kanawani culvert (near Indirapuram) to the elevated road for commuters heading towards Delhi. The other..

Next Story
Infrastructure Urban

Goa Likely to Miss October Deadline for Maritime Master Plan

Goa is expected to miss the October 31 deadline for submitting its maritime and waterways master plan, which covers the state’s 105 km coastline and river network. The delay is due to the project management consultant not yet being appointed. The plan is now anticipated to be completed by December, Captain of Ports Octavio Rodrigues stated at the India Maritime Week 2025 roadshow.“We have already selected the consultant and will bring them on board within a week. Only then can we begin drafting the master plan, which is essential to secure central government funding,” Rodrigues added.A c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?