BMRCL launches first U-girder on Outer Ring Road
RAILWAYS & METRO RAIL

BMRCL launches first U-girder on Outer Ring Road

The Namma Metro's first U-girder was installed at Doddanekundi on Outer Ring Road (ORR) early on Sunday morning.

Bangalore Metro Rail Corporation Limited (BMRCL), along with contractor Shankaranarayana Constructions (SNC), began work on erecting the U-girder near Bagmane World Technology Centre in Doddanekundi on ORR. The first U-girder was established on top of pillars between 473 and 474 at about 4 am.

The U-girder was transported on a 43 m long trailer to the pier area from Lowry Junction close to KR Puram at 2.25 am. Traffic police had barricaded the road area to enable the work.

Each U-girder is 4.6 m wide, 28 m long, and weighs 165 metric tonnes (mt). It is lifted and installed with two hydraulic cranes, one with a capacity of 700 mt and another with 400 mt.

This is the first time U-girders are being utilised in Bengaluru to speed up the metro construction work.

BMRCL decided to employ U-girders for building the viaduct on Silk Board-KR Puram (19.5 km) on Outer Ring Road and KR Puram-Kempegowda International Airport (36 km) areas.

The U-girders will be used for nearly 80% of the corridor's length in the ORR-KIA route. The U-girders will involve casting the whole span of a viaduct between two piers in a single piece, whereas box-girders will have many parts between two piers. One U-girder between two pillars can be erected overnight, against 5-6 days needed in case of box girders.

Experts said U-girders would also save time as well as lower construction expenses. The much longer U-girders drastically decrease construction time. However, due to their length, they need absolute precision during construction. Also, their length makes ferrying them from the casting yard to the location a difficult task.

Image Source

Also read: RITES submits DPR for Namma Metro's phase 3 corridors to BMRCL

The Namma Metro's first U-girder was installed at Doddanekundi on Outer Ring Road (ORR) early on Sunday morning. Bangalore Metro Rail Corporation Limited (BMRCL), along with contractor Shankaranarayana Constructions (SNC), began work on erecting the U-girder near Bagmane World Technology Centre in Doddanekundi on ORR. The first U-girder was established on top of pillars between 473 and 474 at about 4 am. The U-girder was transported on a 43 m long trailer to the pier area from Lowry Junction close to KR Puram at 2.25 am. Traffic police had barricaded the road area to enable the work. Each U-girder is 4.6 m wide, 28 m long, and weighs 165 metric tonnes (mt). It is lifted and installed with two hydraulic cranes, one with a capacity of 700 mt and another with 400 mt. This is the first time U-girders are being utilised in Bengaluru to speed up the metro construction work. BMRCL decided to employ U-girders for building the viaduct on Silk Board-KR Puram (19.5 km) on Outer Ring Road and KR Puram-Kempegowda International Airport (36 km) areas. The U-girders will be used for nearly 80% of the corridor's length in the ORR-KIA route. The U-girders will involve casting the whole span of a viaduct between two piers in a single piece, whereas box-girders will have many parts between two piers. One U-girder between two pillars can be erected overnight, against 5-6 days needed in case of box girders. Experts said U-girders would also save time as well as lower construction expenses. The much longer U-girders drastically decrease construction time. However, due to their length, they need absolute precision during construction. Also, their length makes ferrying them from the casting yard to the location a difficult task. Image Source Also read: RITES submits DPR for Namma Metro's phase 3 corridors to BMRCL

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->