CAG Finds 20,304 Railway Safety Works Unfinished In FY25
RAILWAYS & METRO RAIL

CAG Finds 20,304 Railway Safety Works Unfinished In FY25

The Comptroller and Auditor General of India reported that railway safety enhancement efforts suffered delays as 20,304 safety-related works remained unfinished in the financial year 2024-25. The audit, which was tabled in Parliament, presented an analytical review of the finances and accounts of Indian Railways based on audited accounts for the year ended March 2025. The report identified shortfalls in planned spending and instances where funds were deployed without achieving intended safety outcomes.

The audit highlighted deficiencies in the Rashtriya Rail Sanraksha Kosh, the dedicated safety fund, noting that Indian Railways contributed only Rs 53.25 billion (bn) from internal resources in the first five years of the scheme against an envisaged Rs 250.00 bn, achieving roughly 21.30 per cent of the targeted contribution. It recorded that Rs 8.23 bn under the fund had been allocated to works outside the prescribed prioritisation framework, and that Rs 33.98 bn of RRSK funds was utilised for non-priority projects during 2022-23 to 2024-25.

The report set total Ministry of Railways expenditure in 2024-25 at Rs 5,323.78 bn, an increase of 3.36 per cent over the previous year, comprising Rs 2,693.61 bn in capital spending and Rs 2,630.18 bn in revenue spending. It observed that about 76.83 per cent of working expenses were absorbed by staff costs, pension payments and lease-hire charges for rolling stock, and warned that under-provisioning for depreciation had created throw forward renewal works estimated at Rs 64.48 bn up to 2024-25.

Financial anomalies included unsanctioned expenditure amounting to Rs 194.58 bn across 1,321 cases, equal to 2.55 per cent of total expenditure for the year. Total gross traffic receipts were reported at Rs 2,651.14 bn, rising 3.86 per cent mainly on account of higher passenger, coaching and freight earnings, with coal transport comprising 51.68 per cent of freight receipts. The audit noted a decline in net surplus to Rs 26.60 bn and an operating ratio of 98.22 per cent, signalling constrained fiscal headroom for accelerated safety delivery.

The Comptroller and Auditor General of India reported that railway safety enhancement efforts suffered delays as 20,304 safety-related works remained unfinished in the financial year 2024-25. The audit, which was tabled in Parliament, presented an analytical review of the finances and accounts of Indian Railways based on audited accounts for the year ended March 2025. The report identified shortfalls in planned spending and instances where funds were deployed without achieving intended safety outcomes. The audit highlighted deficiencies in the Rashtriya Rail Sanraksha Kosh, the dedicated safety fund, noting that Indian Railways contributed only Rs 53.25 billion (bn) from internal resources in the first five years of the scheme against an envisaged Rs 250.00 bn, achieving roughly 21.30 per cent of the targeted contribution. It recorded that Rs 8.23 bn under the fund had been allocated to works outside the prescribed prioritisation framework, and that Rs 33.98 bn of RRSK funds was utilised for non-priority projects during 2022-23 to 2024-25. The report set total Ministry of Railways expenditure in 2024-25 at Rs 5,323.78 bn, an increase of 3.36 per cent over the previous year, comprising Rs 2,693.61 bn in capital spending and Rs 2,630.18 bn in revenue spending. It observed that about 76.83 per cent of working expenses were absorbed by staff costs, pension payments and lease-hire charges for rolling stock, and warned that under-provisioning for depreciation had created throw forward renewal works estimated at Rs 64.48 bn up to 2024-25. Financial anomalies included unsanctioned expenditure amounting to Rs 194.58 bn across 1,321 cases, equal to 2.55 per cent of total expenditure for the year. Total gross traffic receipts were reported at Rs 2,651.14 bn, rising 3.86 per cent mainly on account of higher passenger, coaching and freight earnings, with coal transport comprising 51.68 per cent of freight receipts. The audit noted a decline in net surplus to Rs 26.60 bn and an operating ratio of 98.22 per cent, signalling constrained fiscal headroom for accelerated safety delivery.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

MMRDA Targets Completion of Projects by December 2028

The Mumbai Metropolitan Region Development Authority (MMRDA) is targeting the completion of all its ongoing infrastructure projects by December 2028, a year ahead of its December 2029 deadline, Metropolitan Commissioner Dr Sanjay Mukherjee has said.Speaking at the sixth edition of the Real Estate & Infrastructure Investors' Summit (REIIS) 2026 in Mumbai, Mukherjee said the authority was developing an integrated network of roads, tunnels, sea links and Metro corridors under its broader vision of “Mumbai in 59 Minutes”.The objective is to improve east-west and north-south connectivity an..

Next Story
Building Material

High-Performance Façades Gain Ground in Indian Buildings

High-performance façades are gaining greater importance in Indian architecture as developers and architects increasingly focus on energy efficiency, thermal comfort and building performance, according to Shankar Fenestrations & Glasses.The company said modern façade systems are increasingly being considered as part of a building's overall performance strategy rather than being used primarily as aesthetic elements.High-performance glass, curtain wall systems and structural glazing can contribute to thermal regulation, solar control, daylight management and indoor comfort. Their growing ad..

Next Story
Technology

SPML Infra's 104.4 kWh BESS Battery Pack Clears Global Tests

SPML Infra has announced that its proprietary 104.4 kWh Battery Energy Storage System (BESS) battery pack has completed key international safety, performance and transportation testing and certification requirements, marking a step towards its commercial deployment.Developed under the company's own intellectual property, the battery pack has completed requirements under UL9540A, IEC 62619, IEC 63056, IEC 60730, IEC 61000-6-2, IEC 61000-6-4 and UN38.3 standards.The testing covers areas including thermal runaway safety, battery performance, system functional safety, electromagnetic compatibility..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code