Chennai Metro Phase-II Records Ninth TBM Breakthrough
RAILWAYS & METRO RAIL

Chennai Metro Phase-II Records Ninth TBM Breakthrough

Chennai Metro Rail (CMRL) has recorded the ninth tunnel boring machine (TBM) breakthrough under Phase-II after TBM Kaveri reached Kilpauk Medical College Station. The machine completed a 685-metre underground drive from Chetpet as part of the downline tunnelling works for Corridor 3.

Larsen & Toubro executed the downline drive, which was completed in 252 days. During the operation, the TBM negotiated several technically challenging sections, including five live Southern Railway tracks, the Chetpet Eco Park lake and buildings located within the Kilpauk Medical College campus.

The machine passed beneath the railway tracks with an approximate overburden of 18 metres. The sections below the lake and college buildings had overburden ranging from 21 to 26 metres, requiring the tunnelling operation to maintain controlled progress through varying underground conditions.

The work was also carried out near existing Phase-I Metro tunnels. A minimum clearance of 6.1 metres was maintained between the Phase-I and Phase-II tunnel networks during the drive. CMRL said the operation was completed without any major ground settlement or adverse impact on existing infrastructure.

The tunnelling operation involved ten cutterhead interventions. The Chetpet-Kilpauk Medical College section used two TBMs, with Tamarabharani assigned to the upline and Kaveri working on the downline. Tamarabharani achieved its breakthrough on 26 November 2025, completing the corresponding tunnel drive for the section.

Kaveri’s latest breakthrough marks the ninth TBM breakthrough under the TU02 contract for Corridor 3 of Chennai Metro Phase-II. The milestone advances tunnelling works on a section that passes beneath active railway infrastructure, a lake and institutional buildings before reaching the Kilpauk Medical College Station area.

Chennai Metro Rail (CMRL) has recorded the ninth tunnel boring machine (TBM) breakthrough under Phase-II after TBM Kaveri reached Kilpauk Medical College Station. The machine completed a 685-metre underground drive from Chetpet as part of the downline tunnelling works for Corridor 3. Larsen & Toubro executed the downline drive, which was completed in 252 days. During the operation, the TBM negotiated several technically challenging sections, including five live Southern Railway tracks, the Chetpet Eco Park lake and buildings located within the Kilpauk Medical College campus. The machine passed beneath the railway tracks with an approximate overburden of 18 metres. The sections below the lake and college buildings had overburden ranging from 21 to 26 metres, requiring the tunnelling operation to maintain controlled progress through varying underground conditions. The work was also carried out near existing Phase-I Metro tunnels. A minimum clearance of 6.1 metres was maintained between the Phase-I and Phase-II tunnel networks during the drive. CMRL said the operation was completed without any major ground settlement or adverse impact on existing infrastructure. The tunnelling operation involved ten cutterhead interventions. The Chetpet-Kilpauk Medical College section used two TBMs, with Tamarabharani assigned to the upline and Kaveri working on the downline. Tamarabharani achieved its breakthrough on 26 November 2025, completing the corresponding tunnel drive for the section. Kaveri’s latest breakthrough marks the ninth TBM breakthrough under the TU02 contract for Corridor 3 of Chennai Metro Phase-II. The milestone advances tunnelling works on a section that passes beneath active railway infrastructure, a lake and institutional buildings before reaching the Kilpauk Medical College Station area.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Vedanta Secures Two Offshore Blocks in KG Basin Under DSF IV

Vedanta Oil and Gas has secured two offshore blocks in the Krishna Godavari (KG) Basin under the Government of India's Discovered Small Field (DSF) IV bidding round, strengthening its exploration and production portfolio along India's east coast.The newly awarded assets include the shallow water block KG/OSDSF/G1/2025 and the deepwater block KG/DWDSF/GD10/2025. The acquisition forms part of Vedanta's strategy to expand its offshore operations and explore India's untapped hydrocarbon resources through advanced technologies and efficient project execution.The blocks were awarded at a contract si..

Next Story
Resources

Hindustan Zinc's Sakhi Enterprise Income Grows 43%

Hindustan Zinc's Sakhi Microenterprise initiative has recorded a 43 per cent year-on-year increase in collective income, rising from Rs 2.3 million in FY26 to Rs 3.28 million, according to the company. The initiative, operated through Sakhi Utpadan Samiti, currently engages 426 women in income-generating activities across multiple production units.The programme aims to promote financial independence by helping rural women develop entrepreneurial skills and establish sustainable livelihoods. One of its beneficiaries, Manju Devi, who previously depended on seasonal agricultural work, now operate..

Next Story
Technology

KP Group Launches Waterless Solar Cleaning Robot at REI Expo

KP Group's KPI Green OMS has launched the SR 2000 V3.0, a waterless robotic solar panel cleaning system designed for single-axis tracker and fixed-tilt solar power plants, at the Renewable Energy India (REI) Expo 2026 in Greater Noida. The robot aims to improve solar plant efficiency while reducing water consumption and maintenance requirements.Designed to address dust accumulation on solar modules, particularly in dry and remote locations, the SR 2000 V3.0 uses a UV-resistant polybutylene terephthalate (PBT) brush operating at 130 rpm. According to the company, the system achieves a cleaning ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code