Kochi Metro Phase II Targets August 2027 Completion
RAILWAYS & METRO RAIL

Kochi Metro Phase II Targets August 2027 Completion

Kochi Metro Rail (KMRL) has stepped up work on its Phase II project and is pursuing a revised completion deadline of August 2027. Managing director G Priyanka chaired a review meeting on 1 October to assess construction and other pending work across the corridor. The line is planned to connect Jawaharlal Nehru Stadium in Kaloor with SmartCity in Kakkanad. The review covered both construction progress and activities still awaiting completion.

KMRL said civil construction on the remaining sections would begin immediately after land acquisition is completed along the right side of the Palarivattom and Padamugal stretches. The agency has dropped its earlier plan to open the line in partial stages and is instead working towards commissioning the entire corridor by August 2027. The project is valued at Rs. 19.57 bn and has been delayed by utility shifting, land acquisition and funding clearances.

Progress reported by the operator includes the arrival of all specialised steel rails required for track installation. A total of 2,444 pieces have been manufactured to international standards. Foundation work at every station, including piling and pile-cap construction, has been completed, while about 85 per cent of viaduct piling is finished.

KMRL is also examining ways to strengthen its finances after Phase II becomes operational. Passenger revenue will be supplemented by non-fare income, with the operator planning measures such as semi-naming rights for stations and other commercial initiatives. These measures are intended to broaden the project's revenue base once services begin, although the agency did not provide financial estimates or a timetable for the commercial plans.

Kochi Metro Rail (KMRL) has stepped up work on its Phase II project and is pursuing a revised completion deadline of August 2027. Managing director G Priyanka chaired a review meeting on 1 October to assess construction and other pending work across the corridor. The line is planned to connect Jawaharlal Nehru Stadium in Kaloor with SmartCity in Kakkanad. The review covered both construction progress and activities still awaiting completion. KMRL said civil construction on the remaining sections would begin immediately after land acquisition is completed along the right side of the Palarivattom and Padamugal stretches. The agency has dropped its earlier plan to open the line in partial stages and is instead working towards commissioning the entire corridor by August 2027. The project is valued at Rs. 19.57 bn and has been delayed by utility shifting, land acquisition and funding clearances. Progress reported by the operator includes the arrival of all specialised steel rails required for track installation. A total of 2,444 pieces have been manufactured to international standards. Foundation work at every station, including piling and pile-cap construction, has been completed, while about 85 per cent of viaduct piling is finished. KMRL is also examining ways to strengthen its finances after Phase II becomes operational. Passenger revenue will be supplemented by non-fare income, with the operator planning measures such as semi-naming rights for stations and other commercial initiatives. These measures are intended to broaden the project's revenue base once services begin, although the agency did not provide financial estimates or a timetable for the commercial plans.

Related Stories

Gold Stories

Next Story
Resources

K Raheja Corp Homes hosts Joyfest 2.0 at Navi Mumbai project

K Raheja Corp Homes hosted the second edition of Joyfest at Raheja Jade City in Juinagar, Navi Mumbai, bringing together more than 500 residents and visitors for an evening of games, music and family activities.The event, themed ‘Streets of India’, drew inspiration from traditional Indian fairs and included food stalls, interactive games and entertainment for different age groups. Activities included virtual reality cricket, balloon shooting, motion dance, Ring the Pot and Hit the Tins. A jumping castle, bubble artist and mascots added to the attractions.Participants also took part in diya..

Next Story
Real Estate

Ashiana Housing launches third phase of Chennai senior living project

Ashiana Housing has launched Phase 3 of Ashiana Vatsalya, its active senior living project in Chennai. The new phase will add 168 residential units, with an estimated investment of Rs 1.004 billion. Construction is scheduled for completion by March 2029.Spread across 17.9 acre, the new phase will offer one-, two-, and three-bedroom homes priced between Rs 8.5 million and Rs 16.9 million. The International Finance Corporation (IFC) will fund the investment.The larger development includes a 42,000 sq ft clubhouse, 6.3 acres of landscaped and park areas, and more than 40 lifestyle and sports amen..

Next Story
Infrastructure Transport

Seco Marks 30 Years in India, Strengthens Pune Operations Wins Rs 8.39 Billion Vande Bharat Sleeper Orders

"Wabtec Corporation (NYSE: WAB) has secured orders worth approximately US$94 million (Rs 8.39 billion, or Rs 8,390 million) from Indian Railways for systems for the Vande Bharat Sleeper programme. The equipment is intended to increase service availability, simplify maintenance and improve passenger safety.Wabtec will supply onboard brake systems, doors and gangway solutions. Its scope also includes system delivery, integration support, testing, commissioning and long-term operational reliability support.Pascal Schweitzer, President, Wabtec Transit, said the orders reflect the company’s commi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code