Mumbai-Ahmedabad bullet train gets environmental clearance
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train gets environmental clearance

All the necessary environmental clearances in Gujarat and Maharashtra for the 508 km Ahmedabad-Mumbai High-Speed Rail Corridor has been received by the Indian Railways as reported by officials on Tuesday. Railway Board CEO and Chairman VK Yadav stated that 1,070 out of 1,651 utilities had been shifted for the corridor. He further added that railways had acquired 67% of the land required for the Bullet Train project.

In Maharashtra, 97 out of 432 hectares have been acquired, which is only 22% of the land required. Seven out of eight hectares of land have been acquired in Dadra & Nagar Haveli. Prime Minister Narendra Modi and Japan's then Prime Minister, Shinzo Abe had inaugurated the ambitious Rs 1.08 lakh crore project in September 2017.

The earlier deadline to complete the ambitious project was December 2023. The expected speed of the bullet train is 350 km per hour, covering the 508 km stretch in about two hours. Trains that are currently operating on the route take more than seven hours to cover the distance and flights take about an hour.

Source: Economic Times

All the necessary environmental clearances in Gujarat and Maharashtra for the 508 km Ahmedabad-Mumbai High-Speed Rail Corridor has been received by the Indian Railways as reported by officials on Tuesday. Railway Board CEO and Chairman VK Yadav stated that 1,070 out of 1,651 utilities had been shifted for the corridor. He further added that railways had acquired 67% of the land required for the Bullet Train project. In Maharashtra, 97 out of 432 hectares have been acquired, which is only 22% of the land required. Seven out of eight hectares of land have been acquired in Dadra & Nagar Haveli. Prime Minister Narendra Modi and Japan's then Prime Minister, Shinzo Abe had inaugurated the ambitious Rs 1.08 lakh crore project in September 2017. The earlier deadline to complete the ambitious project was December 2023. The expected speed of the bullet train is 350 km per hour, covering the 508 km stretch in about two hours. Trains that are currently operating on the route take more than seven hours to cover the distance and flights take about an hour. Source: Economic Times

Next Story
Infrastructure Urban

India to Invest Rs 600 Billion to Upgrade 1,000 ITIs

As part of its drive to modernise vocational training, the Ministry of Skill Development and Entrepreneurship (MSDE), in collaboration with Gujarat’s Labour and Employment Department, held a State-Level Workshop at the NAMTECH Campus within IIT-Gandhinagar to discuss the National Scheme for ITI Upgradation.The consultation brought together key stakeholders from industry and the training ecosystem to align expectations and support implementation of the scheme, which aims to transform 1,000 Industrial Training Institutes (ITIs) across India using a hub-and-spoke model. The total outlay stands ..

Next Story
Infrastructure Urban

India Unveils Rs 600 Billion Maritime Finance Push

The Ministry of Ports, Shipping & Waterways (MoPSW) hosted the Maritime Financing Summit 2025 in New Delhi, bringing together over 250 stakeholders including policymakers, industry leaders, global investors, and financial institutions. The summit, held under the ambit of Maritime Amrit Kaal Vision (MAKV) 2047, focused on transforming India into a leading maritime power with strengthened financial, infrastructural, and technological capabilities.Union Minister Sarbananda Sonowal emphasised India's strategic progress, noting that average port turnaround times have dropped from four days to u..

Next Story
Infrastructure Urban

Govt Allocates Rs 500 Million To Boost Community Radio

The Central Government, through its ‘Supporting Community Radio Movement in India’ scheme, has allocated Rs 500 million to strengthen the community radio ecosystem across the country. The initiative aims to assist both newly established and long-operational Community Radio Stations (CRSs), ensuring their relevance to local educational, social, cultural, and developmental needs.According to the policy published by the Ministry of Information and Broadcasting, CRSs may be set up by not-for-profit organisations with at least three years of demonstrated community service. These stations are ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?