Railway Board Clears Signalling For Namma Metro Pink And Blue Lines
RAILWAYS & METRO RAIL

Railway Board Clears Signalling For Namma Metro Pink And Blue Lines

The Railway Board has accorded in-principle approval for the Communications Based Train Control (CBTC) signalling and train control system for Namma Metro's Pink Line, Reach-six, and for the entire Blue Line comprising Phase two A and Phase two B extending to Kempegowda International Airport (KIA), the Bangalore Metro Rail Corporation Limited (BMRCL) said. The approval covers the systems required to enable integrated signalling and train operation across the specified corridors. BMRCL stated that the clearance represents a key regulatory milestone ahead of passenger operations.

BMRCL said the in-principle nod is a step towards commissioning the Pink Line section between Kalena Agrahara and Tavarekere and that it has been pursuing final approvals with the Railway Board and the Research Designs and Standards Organisation (RDSO) over the past one month. For the Blue Line, which runs from Central Silk Board to KIA, the signalling clearance had been secured earlier, enabling the authority to proceed with testing and safety work without delay. The corporation indicated that securing CBTC approval was a pending requirement for the Pink Line and has now been addressed.

The corporation outlined the remaining statutory and technical steps before passenger services commence on the Pink Line. These include interim speed certification from RDSO, statutory inspection of the rolling stock by the Central Commissioner of Railway Safety (CCRS), and trial runs to validate operations under the CBTC regime. Once these stages are completed and the final statutory inspection is cleared, the line will be opened for public use.

BMRCL will continue coordination with the Railway Board and RDSO to expedite completion of the approval process and to schedule the required tests. The clearance is expected to support integrated metro connectivity to the airport and to facilitate timely safety certification across the expanded network. The corporation said it will announce further operational timelines after completing trial runs and regulatory clearances.

The Railway Board has accorded in-principle approval for the Communications Based Train Control (CBTC) signalling and train control system for Namma Metro's Pink Line, Reach-six, and for the entire Blue Line comprising Phase two A and Phase two B extending to Kempegowda International Airport (KIA), the Bangalore Metro Rail Corporation Limited (BMRCL) said. The approval covers the systems required to enable integrated signalling and train operation across the specified corridors. BMRCL stated that the clearance represents a key regulatory milestone ahead of passenger operations. BMRCL said the in-principle nod is a step towards commissioning the Pink Line section between Kalena Agrahara and Tavarekere and that it has been pursuing final approvals with the Railway Board and the Research Designs and Standards Organisation (RDSO) over the past one month. For the Blue Line, which runs from Central Silk Board to KIA, the signalling clearance had been secured earlier, enabling the authority to proceed with testing and safety work without delay. The corporation indicated that securing CBTC approval was a pending requirement for the Pink Line and has now been addressed. The corporation outlined the remaining statutory and technical steps before passenger services commence on the Pink Line. These include interim speed certification from RDSO, statutory inspection of the rolling stock by the Central Commissioner of Railway Safety (CCRS), and trial runs to validate operations under the CBTC regime. Once these stages are completed and the final statutory inspection is cleared, the line will be opened for public use. BMRCL will continue coordination with the Railway Board and RDSO to expedite completion of the approval process and to schedule the required tests. The clearance is expected to support integrated metro connectivity to the airport and to facilitate timely safety certification across the expanded network. The corporation said it will announce further operational timelines after completing trial runs and regulatory clearances.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code