Railways working 24x7 on new line for Mizoram
RAILWAYS & METRO RAIL

Railways working 24x7 on new line for Mizoram

The Bairabi-Sairang New Line railway project to connect Mizoram in the northeast to the rest of the country is likely to be completed soon. The project aims to create an additional 51.38 km of railway track in northeast India.

The Bairabi-Sairang project includes 55 major bridges which require about 42,000 tonnes of steel to be fabricated, transported and erected. A record 35,000 tonnes of steel has been fabricated in last 14 months and about 30,000 tonnes has been transported to various work sites.

Transportation of fabricated girders to bridge sites is a challenging task that is being done with round the clock deployment of trailers and heavy machines for assisting in sharp curves of narrow hilly roads and pulling/pushing of these trailers at steep gradients.

The railways stated that erection of the steel girders is a critical activity of the project. In spite of cold nights and remote areas, the work is being executed 24x7. Though there are many challenges in execution of this project like a very short working season due to heavy and prolonged monsoons, tough hilly terrain through deep forests, poor accessibility, non-availability of construction materials and skilled labour in Mizoram, etc, Northeast Frontier Railway is making all efforts for early commissioning of the project.

See also:
HAML gears up to expedite Hyderabad Airport Metro works
Metro work in Pune likely to be stopped during G20 to avoid traffic


The Bairabi-Sairang New Line railway project to connect Mizoram in the northeast to the rest of the country is likely to be completed soon. The project aims to create an additional 51.38 km of railway track in northeast India. The Bairabi-Sairang project includes 55 major bridges which require about 42,000 tonnes of steel to be fabricated, transported and erected. A record 35,000 tonnes of steel has been fabricated in last 14 months and about 30,000 tonnes has been transported to various work sites. Transportation of fabricated girders to bridge sites is a challenging task that is being done with round the clock deployment of trailers and heavy machines for assisting in sharp curves of narrow hilly roads and pulling/pushing of these trailers at steep gradients. The railways stated that erection of the steel girders is a critical activity of the project. In spite of cold nights and remote areas, the work is being executed 24x7. Though there are many challenges in execution of this project like a very short working season due to heavy and prolonged monsoons, tough hilly terrain through deep forests, poor accessibility, non-availability of construction materials and skilled labour in Mizoram, etc, Northeast Frontier Railway is making all efforts for early commissioning of the project. See also: HAML gears up to expedite Hyderabad Airport Metro worksMetro work in Pune likely to be stopped during G20 to avoid traffic

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->