Six Ahmedabad Trains Rerouted For 70-Day Station Upgrade
RAILWAYS & METRO RAIL

Six Ahmedabad Trains Rerouted For 70-Day Station Upgrade

Western Railway will divert six long-distance services from Ahmedabad’s Kalupur station for 70 days while the hub undergoes major redevelopment. From 5 July until 12 September 2025, the following changes will apply:
The 12932 Ahmedabad–Mumbai Central AC Double Decker will start from Maninagar at 05.50, the 12655 Ahmedabad–Chennai Navjivan Express will leave Asarva at 21.05, and the 19034 Ahmedabad–Valsad Gujarat Queen will depart Maninagar at 18.20.
Arriving trains will also finish elsewhere: the Mumbai Central–Ahmedabad AC Double Decker will terminate at Vatva at 21.20, the Chennai–Ahmedabad Navjivan Express at Asarva at 18.20, and the Mumbai Central–Ahmedabad Gujarat Superfast at Vatva at 14.30.
Western Railway said the switches will ease congestion and allow piling work for a new footbridge and concourse at Platform 8. Some other services will call at Sabarmati with revised timings. Passengers must therefore board or alight at Vatva, Maninagar or Asarva until the works conclude.

Western Railway will divert six long-distance services from Ahmedabad’s Kalupur station for 70 days while the hub undergoes major redevelopment. From 5 July until 12 September 2025, the following changes will apply:The 12932 Ahmedabad–Mumbai Central AC Double Decker will start from Maninagar at 05.50, the 12655 Ahmedabad–Chennai Navjivan Express will leave Asarva at 21.05, and the 19034 Ahmedabad–Valsad Gujarat Queen will depart Maninagar at 18.20.Arriving trains will also finish elsewhere: the Mumbai Central–Ahmedabad AC Double Decker will terminate at Vatva at 21.20, the Chennai–Ahmedabad Navjivan Express at Asarva at 18.20, and the Mumbai Central–Ahmedabad Gujarat Superfast at Vatva at 14.30.Western Railway said the switches will ease congestion and allow piling work for a new footbridge and concourse at Platform 8. Some other services will call at Sabarmati with revised timings. Passengers must therefore board or alight at Vatva, Maninagar or Asarva until the works conclude.

Next Story
Infrastructure Energy

Reliable Energy Storage Vital for 24/7 Renewable Power: TKIL

Reliable, scalable, and efficient energy storage systems are essential to ensuring uninterrupted renewable energy supply, said engineering firm TKIL Industries at the India Energy Storage Week (IESW) 2025.India aims to achieve 500 GW of renewable energy capacity within the next five years.Speaking at IESW, organised by the India Energy Storage Alliance (IESA), Vivek Bhatia, Managing Director and CEO of TKIL Industries, emphasised that the country’s energy sector is experiencing a major transformation. This shift is being driven by innovations in storage technology, aimed at improving grid re..

Next Story
Infrastructure Energy

IIT Madras, Hyundai Launch £17m Hydrogen Research Centre

The Indian Institute of Technology Madras (IIT Madras) and Hyundai Motor India Ltd (HMIL) have announced the establishment of the Hyundai HTWO Innovation Centre, a cutting-edge hydrogen research facility set to begin operations by 2026.The Rs 180 crore (approx. £17 million or USD 21.5 million) project will be located at IIT Madras' Discovery Campus in Thaiyur, near Chennai. Of the total, Rs 100 crore (approx. £9.4 million) has been committed by HMIL and its philanthropic arm, Hyundai Motor India Foundation (HMIF), with support from the Government of Tamil Nadu and its investment promotion ag..

Next Story
Infrastructure Energy

India’s Hydrogen Demand to Hit 8.8 MTPA by 2032: IESA Report

India’s hydrogen demand is projected to grow at a compound annual growth rate (CAGR) of 3 per cent, reaching 8.8 million tonnes per annum (MTPA) by 2032, according to a report released by the India Energy Storage Alliance (IESA).Unveiled on the first day of the India Energy Storage Week (IESW) 2025, the report points out a gap between ambitious project announcements and actual progress. While green hydrogen (GH₂) projects totalling 9.2 MTPA have been announced, only a limited number have reached Final Investment Decision (FID) or secured long-term domestic or international offtake agreemen..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?