Forest Clearance Delay Hits Karnataka’s Yettinahole Project
WATER & WASTE

Forest Clearance Delay Hits Karnataka’s Yettinahole Project

Karnataka’s Yettinahole integrated drinking water project, intended to supply water to drought-prone regions across seven districts, has hit a major roadblock due to delays in securing forest clearance from the Union Ministry of Environment, Forest and Climate Change.

The project aims to lift 24.01 TMC of water from west-flowing streams in the Western Ghats to serve around 7.5 million people across 28 taluks. While Stage 1 water lifting works have been completed and construction of the gravity canal is nearing completion, the second phase has stalled as it involves diversion of water through forest land that is yet to receive central approval.

Sources said parts of the project allegedly encroached on forest land without prior clearance. Work on the main canal near Salagame village in Hassan constituency has been halted due to pending land acquisition for a three-kilometre forest stretch. Although the district administration has identified about 410 acres for compensatory afforestation, the ministry has reportedly returned the proposal twice, listing 11 conditions that must be met before clearance can be granted.

The project was originally approved in 2014 under then Chief Minister B S Yediyurappa at an estimated cost of Rs 120 billion. The cost has since been revised multiple times and now stands at over Rs 232.51 billion, with around Rs 171.47 billion already spent. While the project was initially scheduled for completion by July 2026, the timeline has now been pushed to 2027.

The Yettinahole project has also drawn criticism from opposition leaders, including former Union Minister H D Kumaraswamy, who has questioned its scientific feasibility. With forest clearance for the second phase still pending, the state government faces a significant challenge in meeting its objective of providing drinking water to drought-affected regions.

Karnataka’s Yettinahole integrated drinking water project, intended to supply water to drought-prone regions across seven districts, has hit a major roadblock due to delays in securing forest clearance from the Union Ministry of Environment, Forest and Climate Change. The project aims to lift 24.01 TMC of water from west-flowing streams in the Western Ghats to serve around 7.5 million people across 28 taluks. While Stage 1 water lifting works have been completed and construction of the gravity canal is nearing completion, the second phase has stalled as it involves diversion of water through forest land that is yet to receive central approval. Sources said parts of the project allegedly encroached on forest land without prior clearance. Work on the main canal near Salagame village in Hassan constituency has been halted due to pending land acquisition for a three-kilometre forest stretch. Although the district administration has identified about 410 acres for compensatory afforestation, the ministry has reportedly returned the proposal twice, listing 11 conditions that must be met before clearance can be granted. The project was originally approved in 2014 under then Chief Minister B S Yediyurappa at an estimated cost of Rs 120 billion. The cost has since been revised multiple times and now stands at over Rs 232.51 billion, with around Rs 171.47 billion already spent. While the project was initially scheduled for completion by July 2026, the timeline has now been pushed to 2027. The Yettinahole project has also drawn criticism from opposition leaders, including former Union Minister H D Kumaraswamy, who has questioned its scientific feasibility. With forest clearance for the second phase still pending, the state government faces a significant challenge in meeting its objective of providing drinking water to drought-affected regions.

Next Story
Infrastructure Energy

BMW Industries partners with IOCL for PNG supply at Bokaro plant

BMW Industries has entered into a strategic partnership with Indian Oil Corporation (IOCL) for the supply of Piped Natural Gas (PNG), reinforcing its commitment to adopting cleaner and more efficient energy sources for its operations.The agreement was signed at the Eastern Region Pipelines (ERPL) headquarters in Kolkata. The partnership is expected to support the company’s upcoming manufacturing facility in Bokaro by facilitating the use of natural gas as a primary energy source.According to the company, the adoption of PNG will help enhance operational efficiency while also contributing to ..

Next Story
Real Estate

Bombay Realty Secures RERA for Three ICC Tower in South Mumbai

Bombay Realty, the real estate arm of Bombay Dyeing and part of the Wadia Group, has received Real Estate Regulatory Authority (RERA) certification for Three ICC – Wing A, the latest luxury residential tower at Island City Center in Mumbai’s Dadar.The RERA registration marks a key milestone in the development timeline and reinforces the company’s focus on regulatory transparency, timely project delivery, and high construction standards.Following the success of One ICC and Two ICC, the upcoming Three ICC tower represents the next phase of the Island City Center development. The project ai..

Next Story
Infrastructure Energy

Flender launches India’s largest wind gearbox test rig in Walajabad

Flender has inaugurated a 13.5 MW wind turbine gearbox test rig at its Walajabad facility near Chennai, marking the largest installation of its kind in India. The new facility is expected to strengthen the company’s manufacturing and testing capabilities while supporting the growing demands of the wind power sector in both domestic and global markets.The test rig was inaugurated on March 5 in the presence of Andreas Evertz, Group CEO, Flender; Lars Wiegemann, Vice President Wind Gears, Flender; and Vinod Shetty, CEO, Flender India, along with key industry customers and stakeholders.The insta..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement