Forest Clearance Delay Hits Karnataka’s Yettinahole Project
WATER & WASTE

Forest Clearance Delay Hits Karnataka’s Yettinahole Project

Karnataka’s Yettinahole integrated drinking water project, intended to supply water to drought-prone regions across seven districts, has hit a major roadblock due to delays in securing forest clearance from the Union Ministry of Environment, Forest and Climate Change.

The project aims to lift 24.01 TMC of water from west-flowing streams in the Western Ghats to serve around 7.5 million people across 28 taluks. While Stage 1 water lifting works have been completed and construction of the gravity canal is nearing completion, the second phase has stalled as it involves diversion of water through forest land that is yet to receive central approval.

Sources said parts of the project allegedly encroached on forest land without prior clearance. Work on the main canal near Salagame village in Hassan constituency has been halted due to pending land acquisition for a three-kilometre forest stretch. Although the district administration has identified about 410 acres for compensatory afforestation, the ministry has reportedly returned the proposal twice, listing 11 conditions that must be met before clearance can be granted.

The project was originally approved in 2014 under then Chief Minister B S Yediyurappa at an estimated cost of Rs 120 billion. The cost has since been revised multiple times and now stands at over Rs 232.51 billion, with around Rs 171.47 billion already spent. While the project was initially scheduled for completion by July 2026, the timeline has now been pushed to 2027.

The Yettinahole project has also drawn criticism from opposition leaders, including former Union Minister H D Kumaraswamy, who has questioned its scientific feasibility. With forest clearance for the second phase still pending, the state government faces a significant challenge in meeting its objective of providing drinking water to drought-affected regions.

Karnataka’s Yettinahole integrated drinking water project, intended to supply water to drought-prone regions across seven districts, has hit a major roadblock due to delays in securing forest clearance from the Union Ministry of Environment, Forest and Climate Change. The project aims to lift 24.01 TMC of water from west-flowing streams in the Western Ghats to serve around 7.5 million people across 28 taluks. While Stage 1 water lifting works have been completed and construction of the gravity canal is nearing completion, the second phase has stalled as it involves diversion of water through forest land that is yet to receive central approval. Sources said parts of the project allegedly encroached on forest land without prior clearance. Work on the main canal near Salagame village in Hassan constituency has been halted due to pending land acquisition for a three-kilometre forest stretch. Although the district administration has identified about 410 acres for compensatory afforestation, the ministry has reportedly returned the proposal twice, listing 11 conditions that must be met before clearance can be granted. The project was originally approved in 2014 under then Chief Minister B S Yediyurappa at an estimated cost of Rs 120 billion. The cost has since been revised multiple times and now stands at over Rs 232.51 billion, with around Rs 171.47 billion already spent. While the project was initially scheduled for completion by July 2026, the timeline has now been pushed to 2027. The Yettinahole project has also drawn criticism from opposition leaders, including former Union Minister H D Kumaraswamy, who has questioned its scientific feasibility. With forest clearance for the second phase still pending, the state government faces a significant challenge in meeting its objective of providing drinking water to drought-affected regions.

Next Story
Infrastructure Urban

Powerplay Rolls Out Procurement-Linked Credit for Contractors

Powerplay has announced the launch of Powerplay Credit, a project-linked working capital solution aimed at easing cash flow pressures faced by contractors during active construction execution. The solution has gone live across key markets in South India, with a wider national rollout planned for 2026.The launch comes amid rising activity in India’s construction sector across infrastructure, housing, industrial corridors, renewable energy and urban redevelopment. Contractors executing large corporate and government projects often face extended payment cycles, stage-based billing and delayed r..

Next Story
Infrastructure Urban

Jyoti Structures Commissions Galvanisation at Second Nashik Unit

Jyoti Structures has commissioned galvanisation operations at its second tower manufacturing unit in Nashik, strengthening its in-house capabilities across critical stages of power transmission infrastructure production. The listed Engineering, Procurement and Construction (EPC) company operates globally and has delivered projects for customers across more than 50 countries.The second Nashik unit, with an annual manufacturing capacity of 36,000 metric tonnes, has become operational following the completion of installation, testing and readiness of the new galvanising facilities. With this deve..

Next Story
Infrastructure Energy

Rosatom Connects First Kursk NPP-2 Unit to National Grid

Rosatom has launched the first power unit of the Kursk Nuclear Power Plant-2 (Kursk NPP-2) into Russia’s Unified Energy System, marking a key milestone in the country’s nuclear energy programme. The initial grid connection took place at the end of the year, bringing a new source of low-carbon electricity online for the Kursk region and the broader Central Energy System.The newly commissioned unit is the first implementation of the VVER-TOI reactor design, which incorporates advanced safety and performance features. With an installed capacity of 1,250 MW, it is the most powerful nuclear pow..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App