Forest Clearance Delay Hits Karnataka’s Yettinahole Project
WATER & WASTE

Forest Clearance Delay Hits Karnataka’s Yettinahole Project

Karnataka’s Yettinahole integrated drinking water project, intended to supply water to drought-prone regions across seven districts, has hit a major roadblock due to delays in securing forest clearance from the Union Ministry of Environment, Forest and Climate Change.

The project aims to lift 24.01 TMC of water from west-flowing streams in the Western Ghats to serve around 7.5 million people across 28 taluks. While Stage 1 water lifting works have been completed and construction of the gravity canal is nearing completion, the second phase has stalled as it involves diversion of water through forest land that is yet to receive central approval.

Sources said parts of the project allegedly encroached on forest land without prior clearance. Work on the main canal near Salagame village in Hassan constituency has been halted due to pending land acquisition for a three-kilometre forest stretch. Although the district administration has identified about 410 acres for compensatory afforestation, the ministry has reportedly returned the proposal twice, listing 11 conditions that must be met before clearance can be granted.

The project was originally approved in 2014 under then Chief Minister B S Yediyurappa at an estimated cost of Rs 120 billion. The cost has since been revised multiple times and now stands at over Rs 232.51 billion, with around Rs 171.47 billion already spent. While the project was initially scheduled for completion by July 2026, the timeline has now been pushed to 2027.

The Yettinahole project has also drawn criticism from opposition leaders, including former Union Minister H D Kumaraswamy, who has questioned its scientific feasibility. With forest clearance for the second phase still pending, the state government faces a significant challenge in meeting its objective of providing drinking water to drought-affected regions.

Karnataka’s Yettinahole integrated drinking water project, intended to supply water to drought-prone regions across seven districts, has hit a major roadblock due to delays in securing forest clearance from the Union Ministry of Environment, Forest and Climate Change. The project aims to lift 24.01 TMC of water from west-flowing streams in the Western Ghats to serve around 7.5 million people across 28 taluks. While Stage 1 water lifting works have been completed and construction of the gravity canal is nearing completion, the second phase has stalled as it involves diversion of water through forest land that is yet to receive central approval. Sources said parts of the project allegedly encroached on forest land without prior clearance. Work on the main canal near Salagame village in Hassan constituency has been halted due to pending land acquisition for a three-kilometre forest stretch. Although the district administration has identified about 410 acres for compensatory afforestation, the ministry has reportedly returned the proposal twice, listing 11 conditions that must be met before clearance can be granted. The project was originally approved in 2014 under then Chief Minister B S Yediyurappa at an estimated cost of Rs 120 billion. The cost has since been revised multiple times and now stands at over Rs 232.51 billion, with around Rs 171.47 billion already spent. While the project was initially scheduled for completion by July 2026, the timeline has now been pushed to 2027. The Yettinahole project has also drawn criticism from opposition leaders, including former Union Minister H D Kumaraswamy, who has questioned its scientific feasibility. With forest clearance for the second phase still pending, the state government faces a significant challenge in meeting its objective of providing drinking water to drought-affected regions.

Next Story
Infrastructure Transport

Castrol Expands Sarathi Mitra with Mobile Learning for Truckers

Castrol India Limited has expanded its flagship social responsibility initiative, Sarathi Mitra, with the launch of ‘Highways as Classroom’ for truck drivers across Uttar Pradesh. As part of the first phase, a specially designed mobile learning truck will travel to 46 locations in the state, delivering structured knowledge and training directly to the trucking community through on-ground engagement.Truck drivers play a critical role in India’s supply chain, yet they continue to face challenges such as road accidents, health risks, demanding working conditions, and limited access to forma..

Next Story
Infrastructure Transport

East Vinod Nagar Metro Station Wins NECA 2025 Honour

East Vinod Nagar Metro Station on Delhi Metro’s Pink Line has been named the “Best Performing Unit” in the metro stations category at the National Energy Conservation Awards (NECA) 2025, recognising its excellence in energy efficiency and conservation practices. The award was presented by President Droupadi Murmu at a ?????? held at Vigyan Bhawan on the occasion of National Energy Conservation Day. The recognition highlights Delhi Metro’s continued focus on sustainable operations and efficient energy management across its network. Delhi Metro Rail Corporation (DMRC) Managing Director..

Next Story
Infrastructure Transport

DMRC Begins Work On Lajpat Nagar–Saket Phase IV Corridor

The Delhi Metro Rail Corporation (DMRC) has commenced construction on the Lajpat Nagar–Saket G Block corridor under Phase IV, marking the first section beyond the project’s priority corridors where physical work has begun. The elevated corridor forms part of the Golden Line (Line 11) and will feature eight stations: Lajpat Nagar, Andrews Ganj, Greater Kailash-1, Chirag Delhi, Pushpa Bhawan, Saket District Centre, Pushp Vihar and Saket G Block. Once operational, the line is expected to significantly enhance metro connectivity across key parts of South Delhi. According to DMRC, the corrido..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App