Bridge execution delays impact on cost-overun
ROADS & HIGHWAYS

Bridge execution delays impact on cost-overun

When the construction of a bridge faces delays, the cost overrun is much higher compared to any other road or rail projects.

Hardik Agrawal, Director, Dineshchandra R Agrawal Infracon, says “Bridge construction is heavily dependent on construction materials such as cement and steel, which are price-sensitive. If the material cost is quantified compared to the overall project cost, it is much higher than any other segment.”

The most complex bridge projects are the ones across deep valleys, wide rivers and sea crossings. “Geological surprises at the foundation are among the complexities involved,” says NN Sinha, Chairman, National Highways Authority of India (NHAI), and Managing Director, National Highways & Infrastructure Development Corporation (NHIDCL). “Technical expertise, in terms of design and supervision, is shallow, leading many clients to look to foreign shores. Also, lack of local manufacturing and testing of advanced materials such as cables, weathered steel and fibre-reinforcement are other weaknesses.”


RVR Kishore, Project Director, Hindustan Construction Company, agrees that the challenges in bridge construction basically revolve around the geology of the river. “Detailed investigation and preliminary planning are crucial and should be done by the client or contractor,” he suggests. “It is important to first determine the construction methodology, followed by the design of the structure.”


For his part, Vivek Gautam, COO - Strategic Business Group – Core Infra, Tata Projects, points to complexities such as terrain type, RoW, vehicular traffic congestion, dense urban localities and green and regulatory clearances. He mentions the company’s recent project involving DMRC’s 9.63-km Dilshad Garden-Ghaziabad New Bus Adda elevated metro extension. “It included a 170-m bridge across Hindon River. The bridge section was challenging as it was on the upstream side of the river barrage and almost full of water. To reduce time and overcome challenges, we opted for the precast method and the bridge was executed in two parts, thereby safely completing it within 180 days.”


Nitesh Kumar Asati, Joint General Manager, IRCON, says, “Various challenges in bridge construction include selection of girders and bearings, methodology of stressing, finalisation of borrow pits, launching schemes, CRS inspection, etc, with all quality and safety standards as per the statutory requirement. However, use of specialised equipment and technology will definitely help in ensuring timely project completion. During construction, we need to ensure the achievement of various milestones as per the programme submitted by the agency by conducting regular progress review meetings with our agencies and the client. It is imperative for a dedicated team to focus on the various sequential and parallel activities of a bridge, which is a great managerial challenge.”


Referring to Bogibeel Bridge as a feather in the cap of Indian Railway engineers, HCC and Gammon, Shashikant Limaye, Member Expert Committee, Pune Metro Project, says, “Several new technologies were used in this bridge comprising 124-m span steel through girders with a composite RCC deck carrying a two-lane road.” He further mentions the Chenab Bridge along the Udhampur-Srinagar Rail Link, which comprises a 467-m steel truss arch span rising 350 m above the riverbed, as a unique example of a bridge in an earthquake-prone region. Afcons is steadfastly making progress on this unique project. A 145-m-tall viaduct on the Jiribaum-Tupul Railway Line between Silchar and Manipur is another unique project in progress.


That said, if we were to compare India’s approach to bridge construction to other parts of the world, we are still at a nascent stage. However, with the 20-km MTHL and several other bridges coming up across the Ganga and Brahmaputra, the future is bright – and connected!


SHRIYAL SETHUMADHAVAN

When the construction of a bridge faces delays, the cost overrun is much higher compared to any other road or rail projects.Hardik Agrawal, Director, Dineshchandra R Agrawal Infracon, says “Bridge construction is heavily dependent on construction materials such as cement and steel, which are price-sensitive. If the material cost is quantified compared to the overall project cost, it is much higher than any other segment.”The most complex bridge projects are the ones across deep valleys, wide rivers and sea crossings. “Geological surprises at the foundation are among the complexities involved,” says NN Sinha, Chairman, National Highways Authority of India (NHAI), and Managing Director, National Highways & Infrastructure Development Corporation (NHIDCL). “Technical expertise, in terms of design and supervision, is shallow, leading many clients to look to foreign shores. Also, lack of local manufacturing and testing of advanced materials such as cables, weathered steel and fibre-reinforcement are other weaknesses.”RVR Kishore, Project Director, Hindustan Construction Company, agrees that the challenges in bridge construction basically revolve around the geology of the river. “Detailed investigation and preliminary planning are crucial and should be done by the client or contractor,” he suggests. “It is important to first determine the construction methodology, followed by the design of the structure.” For his part, Vivek Gautam, COO - Strategic Business Group – Core Infra, Tata Projects, points to complexities such as terrain type, RoW, vehicular traffic congestion, dense urban localities and green and regulatory clearances. He mentions the company’s recent project involving DMRC’s 9.63-km Dilshad Garden-Ghaziabad New Bus Adda elevated metro extension. “It included a 170-m bridge across Hindon River. The bridge section was challenging as it was on the upstream side of the river barrage and almost full of water. To reduce time and overcome challenges, we opted for the precast method and the bridge was executed in two parts, thereby safely completing it within 180 days.”Nitesh Kumar Asati, Joint General Manager, IRCON, says, “Various challenges in bridge construction include selection of girders and bearings, methodology of stressing, finalisation of borrow pits, launching schemes, CRS inspection, etc, with all quality and safety standards as per the statutory requirement. However, use of specialised equipment and technology will definitely help in ensuring timely project completion. During construction, we need to ensure the achievement of various milestones as per the programme submitted by the agency by conducting regular progress review meetings with our agencies and the client. It is imperative for a dedicated team to focus on the various sequential and parallel activities of a bridge, which is a great managerial challenge.”Referring to Bogibeel Bridge as a feather in the cap of Indian Railway engineers, HCC and Gammon, Shashikant Limaye, Member Expert Committee, Pune Metro Project, says, “Several new technologies were used in this bridge comprising 124-m span steel through girders with a composite RCC deck carrying a two-lane road.” He further mentions the Chenab Bridge along the Udhampur-Srinagar Rail Link, which comprises a 467-m steel truss arch span rising 350 m above the riverbed, as a unique example of a bridge in an earthquake-prone region. Afcons is steadfastly making progress on this unique project. A 145-m-tall viaduct on the Jiribaum-Tupul Railway Line between Silchar and Manipur is another unique project in progress.That said, if we were to compare India’s approach to bridge construction to other parts of the world, we are still at a nascent stage. However, with the 20-km MTHL and several other bridges coming up across the Ganga and Brahmaputra, the future is bright – and connected!SHRIYAL SETHUMADHAVAN

Next Story
Real Estate

Capacit’e Infraprojects Wins Rs 6.21 billion order from Saifee Burhani Upliftment Trust

Capacit’e Infraprojects has secured a Letter of Intent (LOI) worth Rs 6.21 billion (excluding GST) from Saifee Burhani Upliftment Trust (SBUT) for the execution of core and shell works, finishing, MEPF services, and other associated components of the redevelopment project—Sector 07 of the Saifee Burhani Upliftment Project—located at Ward ‘C’, Bhendi Bazaar, Mumbai. This is the third repeat order from SBUT to Capacit’e Infraprojects, underscoring the trust and satisfaction of a long-standing client in the company’s project delivery capabilities. Commenting on the develop..

Next Story
Resources

K Raheja Corp's Volunteering Drive Brings Back-to-School Cheer for Underprivileged Kids

Real estate major K Raheja Corp concluded its latest community initiative under the ‘Time Off for Volunteering’ programme, titled Paint a Pair, Show You Care. Held in association with NGO ConnectFor, the campaign was part of a larger 'Back to School' drive aimed at supporting underprivileged students from the Jhanvi Charitable Trust. More than 45 employees from across group companies—Mindspace Business Parks, Chalet Hotels Ltd., K Raheja Corp Homes, and Inorbit Malls—came together to hand-paint over 60 pairs of canvas shoes for children preparing to return to school. Volunteers al..

Next Story
Infrastructure Urban

CCI Worldwide Logistics Launches ‘Trans Africa’ Freight Service

CCI Worldwide Logistics, the international freight forwarding arm of the CCI Group, has launched ‘Trans Africa’—a technology-led logistics platform aimed at streamlining cross-border trade across Africa. The company is investing Rs 1.06 billion in the initiative, targeting an annual freight volume of 5,000 TEUs by air and sea, with an estimated 15 per cent return on investment. The service is being rolled out in key markets such as Nigeria, Kenya, South Africa, Ghana, and Egypt, with planned expansion into Francophone West Africa, Central Africa, and landlocked nations including Uga..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?