Bridges require solutions to execution delays
ROADS & HIGHWAYS

Bridges require solutions to execution delays

The success of a bridge project depends on the management of various complex and interlinked issues such as timely decisions, robust risk assessment and its mitigation, timely approvals of design and drawings, effective mobilisation of men and machinery, material planning, implementation of right construction methods, project and financial management, prompt and timely troubleshooting, and optimal and effective usage of resources. While all these factors carry inherent complexities, there could be more issues that are technical and administrative in nature. SV Desai, Executive Vice President & Head-Heavy Civil Infrastructure IC, L&T Construction, elaborates....

  • Availability of RoW and environmental clearances can eventually determine whether a contractor is able to deliver a project. Some L&T projects like Delhi’s Barapullah Bridge, Mandovi Bridge in Panaji, Goa, Khulna Mongla Bridge in Bangladesh and even Hyderabad’s Durgam Cheruvu Bridge have suffered initial delays owing to non-availability of RoW. A more recent example is the Mumbai Coastal Road project, stalled because of public agitations and environmental issues. A mechanism should be put in place by the respective state and central ministries to eliminate delays on account of these two factors.

  • Non-availability of skilled labour and execution staff is another pressing issue. The Government has set up a Skills Development Council to encourage industries to develop skills and create a pool of trained indigenous workforce. L&T has established eight Construction Skills Training Institutes across India to impart training in various aspects of construction and improve productivity. Development of frontline supervisors is another initiative by the company to train fresh engineers in supervisory roles by exposing them to various aspects of construction. Despite all these efforts, owing to the boom in the construction industry, contractors are feeling the acute shortfall of skilled workforce, resulting in delays in project execution.

  • Construction challenges could be several, starting with the construction of the foundation of a bridge that depends on the type (open, pile, well, or any other), soil strata, machineries deployed and other logistic issues. In the case of the third Mandovi Bridge, special engineering techniques were adopted to counter the rock boulders left over from the construction of the two earlier bridges. Similar surprises in the foundation media can delay construction if not addressed adequately at the design stage. The next critical step is the construction of the superstructure that involves transport of heavy precast elements through busy roads/waterways, and positioning and erecting them at site. This issue must be addressed with correct design and construction technology right at the planning stage to avoid mishaps, delays and consequent cost escalation.

  • Changes: Complexities could arise from changes in the alignment of the bridge. Unchartered utilities like underground pipe lines, gas lines, cables and high-tension electrical lines are most commonly encountered while constructing bridges. Shifting or relocating these utilities requires approvals from government bodies resulting in undue delay. In several instances, bridges have to be redesigned as some the utilities cannot be re-routed or disconnected.

  • Adverse and challenging terrain can impact delivery. L&T’s project to construct the Kachchi Dargah Bridge in Patna across the Ganga has often been disrupted owing to frequent and sudden floods. The construction of the Panvel Nadi viaduct in Maharashtra for Konkan Railways, one of Asia’s tallest viaducts, involved the use of the innovative incremental push method across a deep gorge. Numerous such instances have been faced by L&T at various bridge projects across the country.


      SHRIYAL SETHUMADHAVAN

The success of a bridge project depends on the management of various complex and interlinked issues such as timely decisions, robust risk assessment and its mitigation, timely approvals of design and drawings, effective mobilisation of men and machinery, material planning, implementation of right construction methods, project and financial management, prompt and timely troubleshooting, and optimal and effective usage of resources. While all these factors carry inherent complexities, there could be more issues that are technical and administrative in nature. SV Desai, Executive Vice President & Head-Heavy Civil Infrastructure IC, L&T Construction, elaborates....Availability of RoW and environmental clearances can eventually determine whether a contractor is able to deliver a project. Some L&T projects like Delhi’s Barapullah Bridge, Mandovi Bridge in Panaji, Goa, Khulna Mongla Bridge in Bangladesh and even Hyderabad’s Durgam Cheruvu Bridge have suffered initial delays owing to non-availability of RoW. A more recent example is the Mumbai Coastal Road project, stalled because of public agitations and environmental issues. A mechanism should be put in place by the respective state and central ministries to eliminate delays on account of these two factors.Non-availability of skilled labour and execution staff is another pressing issue. The Government has set up a Skills Development Council to encourage industries to develop skills and create a pool of trained indigenous workforce. L&T has established eight Construction Skills Training Institutes across India to impart training in various aspects of construction and improve productivity. Development of frontline supervisors is another initiative by the company to train fresh engineers in supervisory roles by exposing them to various aspects of construction. Despite all these efforts, owing to the boom in the construction industry, contractors are feeling the acute shortfall of skilled workforce, resulting in delays in project execution. Construction challenges could be several, starting with the construction of the foundation of a bridge that depends on the type (open, pile, well, or any other), soil strata, machineries deployed and other logistic issues. In the case of the third Mandovi Bridge, special engineering techniques were adopted to counter the rock boulders left over from the construction of the two earlier bridges. Similar surprises in the foundation media can delay construction if not addressed adequately at the design stage. The next critical step is the construction of the superstructure that involves transport of heavy precast elements through busy roads/waterways, and positioning and erecting them at site. This issue must be addressed with correct design and construction technology right at the planning stage to avoid mishaps, delays and consequent cost escalation. Changes: Complexities could arise from changes in the alignment of the bridge. Unchartered utilities like underground pipe lines, gas lines, cables and high-tension electrical lines are most commonly encountered while constructing bridges. Shifting or relocating these utilities requires approvals from government bodies resulting in undue delay. In several instances, bridges have to be redesigned as some the utilities cannot be re-routed or disconnected. Adverse and challenging terrain can impact delivery. L&T’s project to construct the Kachchi Dargah Bridge in Patna across the Ganga has often been disrupted owing to frequent and sudden floods. The construction of the Panvel Nadi viaduct in Maharashtra for Konkan Railways, one of Asia’s tallest viaducts, involved the use of the innovative incremental push method across a deep gorge. Numerous such instances have been faced by L&T at various bridge projects across the country.  SHRIYAL SETHUMADHAVAN

Next Story
Real Estate

Capacit’e Infraprojects Wins Rs 6.21 billion order from Saifee Burhani Upliftment Trust

Capacit’e Infraprojects has secured a Letter of Intent (LOI) worth Rs 6.21 billion (excluding GST) from Saifee Burhani Upliftment Trust (SBUT) for the execution of core and shell works, finishing, MEPF services, and other associated components of the redevelopment project—Sector 07 of the Saifee Burhani Upliftment Project—located at Ward ‘C’, Bhendi Bazaar, Mumbai. This is the third repeat order from SBUT to Capacit’e Infraprojects, underscoring the trust and satisfaction of a long-standing client in the company’s project delivery capabilities. Commenting on the develop..

Next Story
Resources

K Raheja Corp's Volunteering Drive Brings Back-to-School Cheer for Underprivileged Kids

Real estate major K Raheja Corp concluded its latest community initiative under the ‘Time Off for Volunteering’ programme, titled Paint a Pair, Show You Care. Held in association with NGO ConnectFor, the campaign was part of a larger 'Back to School' drive aimed at supporting underprivileged students from the Jhanvi Charitable Trust. More than 45 employees from across group companies—Mindspace Business Parks, Chalet Hotels Ltd., K Raheja Corp Homes, and Inorbit Malls—came together to hand-paint over 60 pairs of canvas shoes for children preparing to return to school. Volunteers al..

Next Story
Infrastructure Urban

CCI Worldwide Logistics Launches ‘Trans Africa’ Freight Service

CCI Worldwide Logistics, the international freight forwarding arm of the CCI Group, has launched ‘Trans Africa’—a technology-led logistics platform aimed at streamlining cross-border trade across Africa. The company is investing Rs 1.06 billion in the initiative, targeting an annual freight volume of 5,000 TEUs by air and sea, with an estimated 15 per cent return on investment. The service is being rolled out in key markets such as Nigeria, Kenya, South Africa, Ghana, and Egypt, with planned expansion into Francophone West Africa, Central Africa, and landlocked nations including Uga..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?