+
The company has avoided borrowing funds from lenders and bankers
Steel

The company has avoided borrowing funds from lenders and bankers

             CW Top Challengers 2018-19

Gallantt Group made a humble beginning in 1984, with an investment of Rs 5 lakh in an oil extraction plant. At present, the group runs two primary steel plants with a captive power plant in Uttar Pradesh and Gujarat in the name of Gallantt Ispat and Gallantt Metal, respectively. Gallantt Ispat operates a steel plant, which comprises a sponge iron unit, steel melt shop with a continuous casting machine that produces MS billets, a rolling and block mill that produces TMT bars and wire rods, and a 53-mw captive power plant that ensures uninterrupted power supply to the entire facility. Mayank Agrawal, CEO, Gallantt Ispat, shares more….
 
Name one major challenge faced in FY2018-19. How did the company approach the same?
There was a shortage of raw material, especially iron ore. To overcome this crisis, we entered into a long-term understanding with Essel Mining & Industries, a Birla Group mining company in Odisha, with a commitment that 80 per cent of the required iron ore will be procured from them. This understanding helped us get discounts and finalise weekly sourcing as per requirement, reducing the shortage of iron ore and enabling us to run the plant smoothly. 

Our entire raw material is transported through railway rakes in bulk quantity. In 2018-19, there was a major crisis in the availability of railway rakes, owing to which we faced great difficulty in the beginning of the year. After vigorous persuasion with the railway authorities, we were upgraded as ‘Priority C’ category where the Railways alots the total quantity of rakes from various railway zones as per the requirement. This approval enabled us to overcome this transportation crisis. 

What is one decision you consider the biggest contributor to the company’s growth in FY2018-19?
Naturally, nobody takes the risk of expanding capacity during a recession period. But we did by expanding our steelmaking capacity twofold, making it 330,000 mtpa, and the power plant to 53 mw with an investment of Rs 2.5 billion. The ‘goddess of luck’ favoured us and proved our decision right as we could successfully complete the expansion programme at a lower capital cost, which resulted in negligible borrowing and reduced the interest burden. Simultaneously, when we commenced commercial production, the steel markets improved drastically, thereby helping the company reap the benefits of the expanded capacity.

Name one single factor you avoided that could have otherwise impacted the company’s topline and bottomline.
The company has avoided borrowing funds from lenders and bankers, which has kept us away from the clutches of the debt trap and burden of loan repayment and interest thereon. All our expansion programmes are going on with internal accruals. We are not solely dependent on indigenous procurements of raw materials and are importing raw materials at competitive prices

Going forward, what are your plans for the company’s growth in FY2019-20?
The company is undergoing further capacity enhancement of all manufacturing facilities and backward integration by adding a pelletisation plant to produce 800,000 mtpa of iron pellets with a capital expenditure of Rs.8 billion; of this, approximately Rs 0.70 billion has already been spent. Post this expansion, the finished steel making capacity increased from 3.30 lakh mtpa to 6.60 lakh mtpa. The expansion is expected to commence commercial production from March 2021 and will be completed in March 2022 in a phased manner.

Gallantt has forayed into the field of real estate with our flagship project: the development of a 12 lakh sq ft built-up area in a JV with a reputed developer in Lucknow, The Shalimar Group. Further, the company has a land bank of about 12 lakh sq ft in Gorakhpur, which will also be developed into world-class commercial and residential complexes. The group is coming up with a five-star and three-star hotel in Gorakhpur in collaboration with Taj Vivanta. The group has already signed an agreement with Indian Hotels Company for construction of the proposed five-star hotel. Last, we are planning to construct a multiplex cum three-star hotel-cum-banquet hall too.

Read on the CW Top Challengers selection criteria and methodology at https://www.constructionworld.in/articles/beststories/CW-identifies-the-Top-Challengers-of-FY2019/21687


Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

             CW Top Challengers 2018-19Gallantt Group made a humble beginning in 1984, with an investment of Rs 5 lakh in an oil extraction plant. At present, the group runs two primary steel plants with a captive power plant in Uttar Pradesh and Gujarat in the name of Gallantt Ispat and Gallantt Metal, respectively. Gallantt Ispat operates a steel plant, which comprises a sponge iron unit, steel melt shop with a continuous casting machine that produces MS billets, a rolling and block mill that produces TMT bars and wire rods, and a 53-mw captive power plant that ensures uninterrupted power supply to the entire facility. Mayank Agrawal, CEO, Gallantt Ispat, shares more…. Name one major challenge faced in FY2018-19. How did the company approach the same?There was a shortage of raw material, especially iron ore. To overcome this crisis, we entered into a long-term understanding with Essel Mining & Industries, a Birla Group mining company in Odisha, with a commitment that 80 per cent of the required iron ore will be procured from them. This understanding helped us get discounts and finalise weekly sourcing as per requirement, reducing the shortage of iron ore and enabling us to run the plant smoothly. Our entire raw material is transported through railway rakes in bulk quantity. In 2018-19, there was a major crisis in the availability of railway rakes, owing to which we faced great difficulty in the beginning of the year. After vigorous persuasion with the railway authorities, we were upgraded as ‘Priority C’ category where the Railways alots the total quantity of rakes from various railway zones as per the requirement. This approval enabled us to overcome this transportation crisis. What is one decision you consider the biggest contributor to the company’s growth in FY2018-19?Naturally, nobody takes the risk of expanding capacity during a recession period. But we did by expanding our steelmaking capacity twofold, making it 330,000 mtpa, and the power plant to 53 mw with an investment of Rs 2.5 billion. The ‘goddess of luck’ favoured us and proved our decision right as we could successfully complete the expansion programme at a lower capital cost, which resulted in negligible borrowing and reduced the interest burden. Simultaneously, when we commenced commercial production, the steel markets improved drastically, thereby helping the company reap the benefits of the expanded capacity.Name one single factor you avoided that could have otherwise impacted the company’s topline and bottomline.The company has avoided borrowing funds from lenders and bankers, which has kept us away from the clutches of the debt trap and burden of loan repayment and interest thereon. All our expansion programmes are going on with internal accruals. We are not solely dependent on indigenous procurements of raw materials and are importing raw materials at competitive pricesGoing forward, what are your plans for the company’s growth in FY2019-20?The company is undergoing further capacity enhancement of all manufacturing facilities and backward integration by adding a pelletisation plant to produce 800,000 mtpa of iron pellets with a capital expenditure of Rs.8 billion; of this, approximately Rs 0.70 billion has already been spent. Post this expansion, the finished steel making capacity increased from 3.30 lakh mtpa to 6.60 lakh mtpa. The expansion is expected to commence commercial production from March 2021 and will be completed in March 2022 in a phased manner.Gallantt has forayed into the field of real estate with our flagship project: the development of a 12 lakh sq ft built-up area in a JV with a reputed developer in Lucknow, The Shalimar Group. Further, the company has a land bank of about 12 lakh sq ft in Gorakhpur, which will also be developed into world-class commercial and residential complexes. The group is coming up with a five-star and three-star hotel in Gorakhpur in collaboration with Taj Vivanta. The group has already signed an agreement with Indian Hotels Company for construction of the proposed five-star hotel. Last, we are planning to construct a multiplex cum three-star hotel-cum-banquet hall too.Read on the CW Top Challengers selection criteria and methodology at https://www.constructionworld.in/articles/beststories/CW-identifies-the-Top-Challengers-of-FY2019/21687

Next Story
Infrastructure Urban

Delivering metals in 24 hours with AI

India’s metal supply chain has long struggled with delays, fragmentation and lack of transparency, forcing purchase teams to chase vendors and juggle uncertain stock. Enlight Metals is tackling these inefficiencies with an AI-powered aggregation platform, multilingual voice-enabled procurement and strategically located dark stores that enable 24-hour delivery – transforming how OEMs, EPCs and infrastructure players source their metals. In a conversation with CW, Dhananjay Goel, Director, and Vedant Goel, Director, shares how the company is reshaping procurement. What problem..

Next Story
Infrastructure Urban

Silvin's CPVC Additive Gets NSF® Certification for Safety

Silvin Additives, a prominent manufacturer of PVC and CPVC additives, has secured the NSF® Guideline 533 certification for its CPVC Super1Pack formulation. This certification affirms the additive’s compliance with stringent international health and safety standards for products intended for drinking water applications.Awarded by NSF, a globally respected public health and safety authority based in Michigan, United States, the certification is granted only after rigorous product testing and inspection. NSF® Guideline 533 specifically assesses the safety of chemical ingredients used in produ..

Next Story
Infrastructure Urban

Mitsubishi Halts Offshore Wind Projects in Japan

Mitsubishi Corporation (MC) has announced its decision to withdraw from three major offshore wind projects off the coast of Japan due to a significant shift in global business conditions. The projects were being developed through a consortium led by its subsidiary, Mitsubishi Corporation Offshore Wind Ltd., and were located off the shores of Noshiro City, Mitane Town, and Oga City in Akita Prefecture; Yurihonjo City in Akita Prefecture; and Choshi City in Chiba Prefecture.The company stated that following a review initiated in February 2025, it concluded the projects were no longer viable. The..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?