+
 NTPC invites bids for BoS Package for solar projects of 1,000 MW
POWER & RENEWABLE ENERGY

NTPC invites bids for BoS Package for solar projects of 1,000 MW

NTPC Renewable Energy Limited (NTPC REL) has issued a Request For Proposals (RFP) for a Balance of System (BoS) package with land for up to 1,000 MW of ISTS-connected solar projects to be built anywhere in India.

Bids must be received by February 3, 2022, to be considered. The next day, bids will be accepted. On the 24th of January, there will be a pre-bid meeting.

Bidders quoting for capacity between 50 MW and 110 MW should submit a bid security deposit of Rs 20 million. The bid security amount is Rs 5 million for capacity above 110 MW up to 220 MW, and Rs 100 million for capacity between 220 MW and 440 MW. The bid security deposit for capacity between 440 MW and 600 MW is Rs 200 million.

Identification, acquisition, and transfer of land ownership or lease in favour of NTPC Renewable Energy are all part of the project's scope. Engineering, design, manufacturing, supply, packaging, forwarding, transporting, unloading, storage, installation, testing, and commissioning of solar projects will also be the responsibility of the successful bidders, excluding solar module supply.

The successful bidders must provide comprehensive operation and maintenance services for three years after commissioning these projects, including switchyard and power evacuation systems until the interconnecting grid substation.

At least 40 MW of grid-connected solar projects should have been designed and commissioned by bidders. One project must have a capacity of 10 MW or more and have been operational for at least six months before the techno-commercial bid opening date.

Alternatively, bidders must have completed grid-connected solar projects with a total capacity of at least 40 MW. One solar project should have a capacity of at least 10 MW. The project must have been up and running for at least six months before the opening of the techno-commercial bid.

Bidders must have completed an industrial project in the power, steel, oil, gas, petrochemical, fertiliser, cement, or coal mining sectors in the previous ten years, either as developers or as Engineering, Procurement, and Construction (EPC) contractors. Before the date of the techno-commercial bid opening, the project should have been in operation for at least one year.

Bidders must have completed at least one electrical substation with a voltage level of 33 kV or higher, including equipment such as power transformers and circuit breakers.

In the previous three financial years, the bidders' minimum average annual turnover for quoted capacity between 50 MW and 300 MW should have been Rs 1.1 billion. If the capacity is between 300 MW and 600 MW, their average annual turnover must not be less than Rs 2.2 billion in the previous three financial years. In the previous financial year, their net worth had to be equal to or greater than their paid-up share capital.

NTPC Renewable Energy issued a request for proposals last month for a BoS package for 325 MW of projects in Madhya Pradesh's Shajapur Solar Park.

The 735 MW Nokh solar power project in Rajasthan was reissued in November by NTPC Limited as a balance of system package tender.

Image Source

Also read: UPNEDA floats tenders to empanel installers for 38 MW rooftop solar

NTPC Renewable Energy Limited (NTPC REL) has issued a Request For Proposals (RFP) for a Balance of System (BoS) package with land for up to 1,000 MW of ISTS-connected solar projects to be built anywhere in India. Bids must be received by February 3, 2022, to be considered. The next day, bids will be accepted. On the 24th of January, there will be a pre-bid meeting. Bidders quoting for capacity between 50 MW and 110 MW should submit a bid security deposit of Rs 20 million. The bid security amount is Rs 5 million for capacity above 110 MW up to 220 MW, and Rs 100 million for capacity between 220 MW and 440 MW. The bid security deposit for capacity between 440 MW and 600 MW is Rs 200 million. Identification, acquisition, and transfer of land ownership or lease in favour of NTPC Renewable Energy are all part of the project's scope. Engineering, design, manufacturing, supply, packaging, forwarding, transporting, unloading, storage, installation, testing, and commissioning of solar projects will also be the responsibility of the successful bidders, excluding solar module supply. The successful bidders must provide comprehensive operation and maintenance services for three years after commissioning these projects, including switchyard and power evacuation systems until the interconnecting grid substation. At least 40 MW of grid-connected solar projects should have been designed and commissioned by bidders. One project must have a capacity of 10 MW or more and have been operational for at least six months before the techno-commercial bid opening date. Alternatively, bidders must have completed grid-connected solar projects with a total capacity of at least 40 MW. One solar project should have a capacity of at least 10 MW. The project must have been up and running for at least six months before the opening of the techno-commercial bid. Bidders must have completed an industrial project in the power, steel, oil, gas, petrochemical, fertiliser, cement, or coal mining sectors in the previous ten years, either as developers or as Engineering, Procurement, and Construction (EPC) contractors. Before the date of the techno-commercial bid opening, the project should have been in operation for at least one year. Bidders must have completed at least one electrical substation with a voltage level of 33 kV or higher, including equipment such as power transformers and circuit breakers. In the previous three financial years, the bidders' minimum average annual turnover for quoted capacity between 50 MW and 300 MW should have been Rs 1.1 billion. If the capacity is between 300 MW and 600 MW, their average annual turnover must not be less than Rs 2.2 billion in the previous three financial years. In the previous financial year, their net worth had to be equal to or greater than their paid-up share capital. NTPC Renewable Energy issued a request for proposals last month for a BoS package for 325 MW of projects in Madhya Pradesh's Shajapur Solar Park. The 735 MW Nokh solar power project in Rajasthan was reissued in November by NTPC Limited as a balance of system package tender. Image Source Also read: UPNEDA floats tenders to empanel installers for 38 MW rooftop solar

Next Story
Technology

Minda, Qualcomm Join Forces for Smart Auto Cockpit Tech

Minda Corporation Limited, the flagship of the Spark Minda Group, has announced a strategic partnership with Qualcomm Technologies, Inc. to develop intelligent and connected cockpit solutions for the Indian automotive market. The upcoming smart interface will be powered by Qualcomm’s Snapdragon Cockpit Platform.Commenting on the collaboration, Suresh D, Group CTO of Minda Corporation, said, “This partnership with Qualcomm Technologies marks a major milestone in advancing Minda’s digital cockpit capabilities. By utilising Qualcomm’s cutting-edge automotive platforms, we can now offer se..

Next Story
Infrastructure Transport

Railways Spent Rs 604.7 Billion on Passenger Subsidy in FY24

New Delhi – The Indian Railways provisionally spent Rs 604.7 billion in subsidies during the financial year 2023–24, covering 45 per cent of passenger travel costs, Railway Minister Ashwini Vaishnaw informed the Lok Sabha on Wednesday.In a written response to questions from multiple Members of Parliament regarding the recent rail fare hike, Vaishnaw stated that the Indian Railways continues to offer one of the most affordable transport services globally, ferrying over 7.2 billion passengers annually."The total amount of subsidy provided in FY 2023–24 on passenger travel is provisionally ..

Next Story
Infrastructure Urban

Auto Sector Can Cut Emissions by 87% by 2050: CEEW

India’s automobile industry could reduce its manufacturing emissions by 87 per cent by 2050 through a shift to green electricity and low-carbon steel, according to a study released by the Council on Energy, Environment and Water (CEEW).The report estimates that if original equipment manufacturers (OEMs) and their suppliers target net-zero emissions by 2050, annual emissions could fall from a projected 64 million tonnes of CO₂ (under the business-as-usual scenario) to just 9 million tonnes. This would require OEMs to adopt 100 per cent green electricity and steel suppliers to source 56 per ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?