NTPC invites bids for BoS Package for solar projects of 1,000 MW
POWER & RENEWABLE ENERGY

NTPC invites bids for BoS Package for solar projects of 1,000 MW

NTPC Renewable Energy Limited (NTPC REL) has issued a Request For Proposals (RFP) for a Balance of System (BoS) package with land for up to 1,000 MW of ISTS-connected solar projects to be built anywhere in India.

Bids must be received by February 3, 2022, to be considered. The next day, bids will be accepted. On the 24th of January, there will be a pre-bid meeting.

Bidders quoting for capacity between 50 MW and 110 MW should submit a bid security deposit of Rs 20 million. The bid security amount is Rs 5 million for capacity above 110 MW up to 220 MW, and Rs 100 million for capacity between 220 MW and 440 MW. The bid security deposit for capacity between 440 MW and 600 MW is Rs 200 million.

Identification, acquisition, and transfer of land ownership or lease in favour of NTPC Renewable Energy are all part of the project's scope. Engineering, design, manufacturing, supply, packaging, forwarding, transporting, unloading, storage, installation, testing, and commissioning of solar projects will also be the responsibility of the successful bidders, excluding solar module supply.

The successful bidders must provide comprehensive operation and maintenance services for three years after commissioning these projects, including switchyard and power evacuation systems until the interconnecting grid substation.

At least 40 MW of grid-connected solar projects should have been designed and commissioned by bidders. One project must have a capacity of 10 MW or more and have been operational for at least six months before the techno-commercial bid opening date.

Alternatively, bidders must have completed grid-connected solar projects with a total capacity of at least 40 MW. One solar project should have a capacity of at least 10 MW. The project must have been up and running for at least six months before the opening of the techno-commercial bid.

Bidders must have completed an industrial project in the power, steel, oil, gas, petrochemical, fertiliser, cement, or coal mining sectors in the previous ten years, either as developers or as Engineering, Procurement, and Construction (EPC) contractors. Before the date of the techno-commercial bid opening, the project should have been in operation for at least one year.

Bidders must have completed at least one electrical substation with a voltage level of 33 kV or higher, including equipment such as power transformers and circuit breakers.

In the previous three financial years, the bidders' minimum average annual turnover for quoted capacity between 50 MW and 300 MW should have been Rs 1.1 billion. If the capacity is between 300 MW and 600 MW, their average annual turnover must not be less than Rs 2.2 billion in the previous three financial years. In the previous financial year, their net worth had to be equal to or greater than their paid-up share capital.

NTPC Renewable Energy issued a request for proposals last month for a BoS package for 325 MW of projects in Madhya Pradesh's Shajapur Solar Park.

The 735 MW Nokh solar power project in Rajasthan was reissued in November by NTPC Limited as a balance of system package tender.

Image Source

Also read: UPNEDA floats tenders to empanel installers for 38 MW rooftop solar

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

NTPC Renewable Energy Limited (NTPC REL) has issued a Request For Proposals (RFP) for a Balance of System (BoS) package with land for up to 1,000 MW of ISTS-connected solar projects to be built anywhere in India. Bids must be received by February 3, 2022, to be considered. The next day, bids will be accepted. On the 24th of January, there will be a pre-bid meeting. Bidders quoting for capacity between 50 MW and 110 MW should submit a bid security deposit of Rs 20 million. The bid security amount is Rs 5 million for capacity above 110 MW up to 220 MW, and Rs 100 million for capacity between 220 MW and 440 MW. The bid security deposit for capacity between 440 MW and 600 MW is Rs 200 million. Identification, acquisition, and transfer of land ownership or lease in favour of NTPC Renewable Energy are all part of the project's scope. Engineering, design, manufacturing, supply, packaging, forwarding, transporting, unloading, storage, installation, testing, and commissioning of solar projects will also be the responsibility of the successful bidders, excluding solar module supply. The successful bidders must provide comprehensive operation and maintenance services for three years after commissioning these projects, including switchyard and power evacuation systems until the interconnecting grid substation. At least 40 MW of grid-connected solar projects should have been designed and commissioned by bidders. One project must have a capacity of 10 MW or more and have been operational for at least six months before the techno-commercial bid opening date. Alternatively, bidders must have completed grid-connected solar projects with a total capacity of at least 40 MW. One solar project should have a capacity of at least 10 MW. The project must have been up and running for at least six months before the opening of the techno-commercial bid. Bidders must have completed an industrial project in the power, steel, oil, gas, petrochemical, fertiliser, cement, or coal mining sectors in the previous ten years, either as developers or as Engineering, Procurement, and Construction (EPC) contractors. Before the date of the techno-commercial bid opening, the project should have been in operation for at least one year. Bidders must have completed at least one electrical substation with a voltage level of 33 kV or higher, including equipment such as power transformers and circuit breakers. In the previous three financial years, the bidders' minimum average annual turnover for quoted capacity between 50 MW and 300 MW should have been Rs 1.1 billion. If the capacity is between 300 MW and 600 MW, their average annual turnover must not be less than Rs 2.2 billion in the previous three financial years. In the previous financial year, their net worth had to be equal to or greater than their paid-up share capital. NTPC Renewable Energy issued a request for proposals last month for a BoS package for 325 MW of projects in Madhya Pradesh's Shajapur Solar Park. The 735 MW Nokh solar power project in Rajasthan was reissued in November by NTPC Limited as a balance of system package tender. Image Source Also read: UPNEDA floats tenders to empanel installers for 38 MW rooftop solar

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement