+
APTEL Grants 289-Day Extension for POWERGRID Transmission Project
POWER & RENEWABLE ENERGY

APTEL Grants 289-Day Extension for POWERGRID Transmission Project

The Appellate Tribunal for Electricity (APTEL) determined that the POWERGRID Southern Interconnector Transmission System is entitled to a 289-day extension for completing its transmission project, acknowledging that the delay resulted from ?force majeure? events. Consequently, the Central Electricity Regulatory Commission has been directed to issue a new order, taking into account the appellate authority?s observations, and has been given two months to finalize this process.

In a separate decision, the Uttar Pradesh Electricity Regulatory Commission (UPERC) approved a petition from the Uttar Pradesh Power Corporation (UPPCL) for the procurement of 2,000 MW of solar power. This move aligns with the government?s objective to reach 500 GW of non-fossil-based installed power capacity by 2030. UPPCL's proposal for acquiring 2,000 MW of solar power is intended to support this target. The tender documents were developed according to the Ministry of Power?s guidelines for tariff-based competitive bidding for solar projects. These projects are expected to be executed on a build, own, operate, and maintain (BOOM) basis, with a 25-year Power Purchase Agreement (PPA) duration. The Uttar Pradesh Solar Policy 2022 will be applicable, offering various advantages to developers.

The Appellate Tribunal for Electricity (APTEL) determined that the POWERGRID Southern Interconnector Transmission System is entitled to a 289-day extension for completing its transmission project, acknowledging that the delay resulted from ?force majeure? events. Consequently, the Central Electricity Regulatory Commission has been directed to issue a new order, taking into account the appellate authority?s observations, and has been given two months to finalize this process. In a separate decision, the Uttar Pradesh Electricity Regulatory Commission (UPERC) approved a petition from the Uttar Pradesh Power Corporation (UPPCL) for the procurement of 2,000 MW of solar power. This move aligns with the government?s objective to reach 500 GW of non-fossil-based installed power capacity by 2030. UPPCL's proposal for acquiring 2,000 MW of solar power is intended to support this target. The tender documents were developed according to the Ministry of Power?s guidelines for tariff-based competitive bidding for solar projects. These projects are expected to be executed on a build, own, operate, and maintain (BOOM) basis, with a 25-year Power Purchase Agreement (PPA) duration. The Uttar Pradesh Solar Policy 2022 will be applicable, offering various advantages to developers.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code