GERC Grants Extension For Seven Point Eight MW Captive Solar Project
POWER & RENEWABLE ENERGY

GERC Grants Extension For Seven Point Eight MW Captive Solar Project

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution.

The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure.

GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses.

Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution. The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure. GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses. Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Next Story
Infrastructure Transport

Afcons Secures Rs 53.01 Billion Vadhvan Breakwater Contract

Afcons Infrastructure has received the Letter of Award from Vadhvan Port Project for the construction of a 10.14-km-long breakwater at the upcoming Vadhvan Port in Maharashtra. Valued at Rs 53.01 billion, the project will create what is set to become the second longest breakwater in the world upon completion.The contract marks a significant milestone for the marine infrastructure specialist and is expected to play a crucial role in the development of Vadhvan Port, envisaged as India's largest public port and one of the world's biggest container ports.Krishnamurthy Subramanian, Executive Chairm..

Next Story
Infrastructure Energy

India Clean Industry Pipeline Grows 30%

India’s clean industry project pipeline has grown by 30 per cent over a six-month period, reflecting rising interest in low-carbon industrial growth amid geopolitical and supply-chain uncertainty.Mission Possible Partnership’s latest Global Project Tracker shows that India now has the world’s third-largest clean industrial project pipeline by project count, after China and the United States. The country has 65 projects across four sectors and 11 states, representing an estimated $433.07 billion investment opportunity in clean fuels, chemicals and low-carbon manufacturing.The pipeline inc..

Next Story
Infrastructure Urban

Kärcher Showcases Professional Cleaning Solutions

Kärcher India recently showcased its professional cleaning solutions portfolio for commercial, industrial, hospitality, healthcare, retail, automotive and institutional applications. The range includes cleaning agents and detergents designed to support efficiency, material safety, operational reliability and hygiene across multiple environments.Under floor cleaning, Kärcher offers solutions such as FloorPro Deep Cleaner RM 751, FloorPro Shine Cleaner RM 755, FloorPro Fine Stoneware Cleaner RM 753, FloorPro Crystallising Agent RM 749 and High Gloss Crystallising Powder RM 775. These products ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement