+
GERC Grants Extension For Seven Point Eight MW Captive Solar Project
POWER & RENEWABLE ENERGY

GERC Grants Extension For Seven Point Eight MW Captive Solar Project

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution.

The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure.

GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses.

Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution. The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure. GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses. Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Annette Gregg Named WTCA’s First Female CEO

World Trade Centers Association (WTCA) has appointed Annette Gregg as Chief Executive Officer, making her the first woman to lead the organisation in its 57-year history.Gregg assumed the role from October 5 and will lead WTCA from its recently established global headquarters at One World Trade Center in New York City. The association connects more than 300 World Trade Center locations across nearly 100 countries and territories.As CEO, Gregg will provide strategic leadership to WTCA and its global staff, working with the Board of Directors and members to advance business priorities, strengthe..

Next Story
Resources

Isprava Appoints Sanjay Sethi as Strategic Advisor

Isprava Group has appointed Dr Sanjay Sethi as Strategic Advisor to the business, with a focus on Lohono Stays and Isprava Hospitality.Sethi brings more than 37 years of experience across hospitality operations, development, ownership, strategic growth and capital markets. He will work closely with the Group on strategy, growth and the development of its hospitality business.The appointment comes as Isprava Group expands its integrated ecosystem spanning luxury homes, hospitality, private membership and end-to-end homeowner services.Nibhrant Shah, Managing Director & Co-CEO, Isprava Group, sai..

Next Story
Infrastructure Energy

SunBridge BioEnergy Starts Ethanol Production in Seoni

SunBridge BioEnergy, the bioenergy arm of SunBridge Group, has commenced commercial production at its grain-based fuel-grade ethanol manufacturing facility in Seoni, Madhya Pradesh. The Seoni plant has a production capacity of 300 kilolitres per day and a storage capacity of 11,000 kilolitres. Spread across approximately 117,560 sq m, the facility marks SunBridge BioEnergy’s entry into commercial ethanol production. The company is also expanding its ethanol portfolio with a 400 KLD facility in Raipur, Chhattisgarh, which is expected to become operational soon. Once commissioned, SunBridge ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code