GERC Grants Extension For Seven Point Eight MW Captive Solar Project
POWER & RENEWABLE ENERGY

GERC Grants Extension For Seven Point Eight MW Captive Solar Project

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution.

The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure.

GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses.

Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution. The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure. GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses. Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement