GERC Grants Extension For Seven Point Eight MW Captive Solar Project
POWER & RENEWABLE ENERGY

GERC Grants Extension For Seven Point Eight MW Captive Solar Project

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution.

The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure.

GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses.

Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Panara Craft LLP sought a 90 day extension to commission its seven point eight megawatt (MW) captive solar power project in Gujarat, citing delays in financing and completion of evacuation infrastructure. The project is divided into two three point nine MW installations in Bharuch district and has faced setbacks in securing grid connectivity. The company said the loan process with the State Bank of India began in March 2024, was sanctioned in November 2024 and disbursement started in February 2025, which slowed execution. The request was considered under GERC Order No. 06 of 2024 and the Gujarat Renewable Energy Policy 2023, which require solar projects ranging from one MW to 100 MW to be commissioned within 12 months of the Technical Feasibility Report. For Panara Craft the deadline was 22 April 2025 but the company argued the delays were beyond its control and should be treated as unavoidable circumstances. Dakshin Gujarat Vij Company Limited and Gujarat Energy Transmission Corporation Limited opposed the extension, asserting developer responsibility and noting that delayed disbursement did not amount to force majeure. GERC examined project progress and observed that key technical activities such as pile drilling, casting and structure mounting had largely been completed. The Commission also referenced its earlier order in Petition No. 2564 of 2025 that extended the timeline for evacuation infrastructure from 12 months to 18 months. The company warned that strict action including cancellation of connectivity or encashment of bank guarantees worth Rs 3.9 million (mn) would inflict serious financial losses. Balancing the circumstances, the Commission granted additional time and directed Panara Craft to complete remaining technical and regulatory work within six months from the date of its order, offering the developer an opportunity to secure grid connectivity without immediate penalties. The decision reflects an attempt to reconcile regulatory timelines with practical financing and infrastructure challenges and signals that prompt coordination remains essential to avoid future enforcement actions.

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement