Government Issues Bidding Guidelines for Pumped Storage Projects
POWER & RENEWABLE ENERGY

Government Issues Bidding Guidelines for Pumped Storage Projects

The Ministry of Power has released tariff-based competitive bidding guidelines for procuring stored energy from existing, under-construction, or new Pumped Storage Projects (PSP). 
According to the National Electricity Plan 2023, India will require 74 GW/411 GWh of energy storage systems (ESS) by 2031-32, including 27 GW/175 GWh from PSPs and 47 GW/236 GWh from Battery Energy Storage Systems (BESS). 

Procurement models 

Mode 1: PSPs developed on sites identified by the procurer 

• The procurer selects the site, and the project is developed on a Build-Own-Operate-Transfer (BOOT) basis for 25 to 40 years. 
• A Special Purpose Vehicle (SPV) will handle pre-feasibility activities, including environmental and statutory clearances. 
• The SPV, initially owned by the procurer, will be transferred to the successful bidder at a pre-specified cost. 

Mode 2: PSPs identified by the bidder or already commissioned 

• PSPs may be developed on self-identified sites or existing facilities on a Build-Own-Operate (BOO) basis for 15 to 40 years. 
• Developers must secure environmental, forest, and land clearances before construction. 
• The procurer is not responsible for clearance-related delays. 

Key bidding criteria Minimum bid capacity 

• ISTS-connected projects: 50 MW 
• InSTS-connected projects: 10 MW (lower capacities may be permitted in the Northeast and Special Category States). 

Eligibility requirements 
• Developers must have infrastructure project experience from the last five years. 
• Minimum capital expenditure thresholds will be defined in the bidding documents. 
• Net worth or assets under management must be at least 20% of the estimated capital cost of the project. 

Financial obligations 
• Earnest Money Deposit (EMD): 2% of the estimated project cost. 
• Performance Bank Guarantee (PBG): 5% of the estimated project cost. 

Contractual and regulatory framework 
• The Power Purchase Agreement (PPA) must be signed within six months of the Letter of Award (LoA), or the awarded capacity may be cancelled. 
• The tariff adoption process must be completed within 60 days of application to the relevant Commission. 

Additional provisions 
• Transmission connectivity: Developers must secure access to the ISTS network at their own cost. 
• Force majeure: Developers must notify the procurer within 15 days of any such event. 
• Financial closure: Must be completed within 12 months, with penalties for delays. 
• Minimum commissioning capacity: 50% of the project capacity or 50 MW, whichever is lower. 

The government has also modified its budgetary support for hydroelectric and PSP projects, allocating Rs 124.6 billion for development. These guidelines aim to accelerate energy storage expansion and support India’s growing renewable energy sector. 
(Mercom) 

The Ministry of Power has released tariff-based competitive bidding guidelines for procuring stored energy from existing, under-construction, or new Pumped Storage Projects (PSP). According to the National Electricity Plan 2023, India will require 74 GW/411 GWh of energy storage systems (ESS) by 2031-32, including 27 GW/175 GWh from PSPs and 47 GW/236 GWh from Battery Energy Storage Systems (BESS). Procurement models Mode 1: PSPs developed on sites identified by the procurer • The procurer selects the site, and the project is developed on a Build-Own-Operate-Transfer (BOOT) basis for 25 to 40 years. • A Special Purpose Vehicle (SPV) will handle pre-feasibility activities, including environmental and statutory clearances. • The SPV, initially owned by the procurer, will be transferred to the successful bidder at a pre-specified cost. Mode 2: PSPs identified by the bidder or already commissioned • PSPs may be developed on self-identified sites or existing facilities on a Build-Own-Operate (BOO) basis for 15 to 40 years. • Developers must secure environmental, forest, and land clearances before construction. • The procurer is not responsible for clearance-related delays. Key bidding criteria Minimum bid capacity • ISTS-connected projects: 50 MW • InSTS-connected projects: 10 MW (lower capacities may be permitted in the Northeast and Special Category States). Eligibility requirements • Developers must have infrastructure project experience from the last five years. • Minimum capital expenditure thresholds will be defined in the bidding documents. • Net worth or assets under management must be at least 20% of the estimated capital cost of the project. Financial obligations • Earnest Money Deposit (EMD): 2% of the estimated project cost. • Performance Bank Guarantee (PBG): 5% of the estimated project cost. Contractual and regulatory framework • The Power Purchase Agreement (PPA) must be signed within six months of the Letter of Award (LoA), or the awarded capacity may be cancelled. • The tariff adoption process must be completed within 60 days of application to the relevant Commission. Additional provisions • Transmission connectivity: Developers must secure access to the ISTS network at their own cost. • Force majeure: Developers must notify the procurer within 15 days of any such event. • Financial closure: Must be completed within 12 months, with penalties for delays. • Minimum commissioning capacity: 50% of the project capacity or 50 MW, whichever is lower. The government has also modified its budgetary support for hydroelectric and PSP projects, allocating Rs 124.6 billion for development. These guidelines aim to accelerate energy storage expansion and support India’s growing renewable energy sector. (Mercom) 

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Urban

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement