Juniper Green Energy Limited has begun commissioning India’s first firm and dispatchable renewable energy (FDRE) project under a tender awarded by SJVN. The FDRE project integrates 259 MWp (megawatt peak) of solar, 280 MW (megawatt) of wind generation and a 200 MWh (megawatt-hour) battery energy storage system (BESS) across Rajasthan and Gujarat to deliver scheduled renewable power aligned with grid demand. Ankush Malik, chief executive of Juniper Green Energy, described the milestone as the start of India’s first FDRE implementation and confirmed commissioning activities had commenced.

As renewable capacity has expanded, grid stability has become a concern because of the variable nature of solar and wind output. To address that, the Ministry of Power issued FDRE guidelines in June 2023 requiring integration of solar, wind and battery storage into a single project capable of supplying scheduled power in line with distribution company demand. The FDRE model is intended to provide firm, dispatchable output to match demand profiles.

The 259 MWp solar component entered commercial operations in March 2026 while the 200 MWh BESS began commercial operations in April 2026. Juniper Green secured the project through a tender floated by SJVN Limited and signed a 200 MW power purchase agreement (PPA) with SJVN, which in turn has a back-to-back power sale agreement with the Haryana Power Purchase Centre for supply to the state. The combined asset mix is designed to enable scheduled dispatch and improve supply predictability.

Since the FDRE guidelines were introduced in 2023, more than 10 tenders totalling over 14 GW have been issued by central and state agencies including SJVN, NHPC, SECI and NTPC, with around 10 GW under construction. Juniper Green is an independent renewable power producer headquartered in Delhi NCR and reported an operational capacity of approximately 1.66 GWp (gigawatt peak) as of January 2026. The company is part of the AT Capital Group, a Singapore-based investment group.

Juniper Green Energy Limited has begun commissioning India’s first firm and dispatchable renewable energy (FDRE) project under a tender awarded by SJVN. The FDRE project integrates 259 MWp (megawatt peak) of solar, 280 MW (megawatt) of wind generation and a 200 MWh (megawatt-hour) battery energy storage system (BESS) across Rajasthan and Gujarat to deliver scheduled renewable power aligned with grid demand. Ankush Malik, chief executive of Juniper Green Energy, described the milestone as the start of India’s first FDRE implementation and confirmed commissioning activities had commenced. As renewable capacity has expanded, grid stability has become a concern because of the variable nature of solar and wind output. To address that, the Ministry of Power issued FDRE guidelines in June 2023 requiring integration of solar, wind and battery storage into a single project capable of supplying scheduled power in line with distribution company demand. The FDRE model is intended to provide firm, dispatchable output to match demand profiles. The 259 MWp solar component entered commercial operations in March 2026 while the 200 MWh BESS began commercial operations in April 2026. Juniper Green secured the project through a tender floated by SJVN Limited and signed a 200 MW power purchase agreement (PPA) with SJVN, which in turn has a back-to-back power sale agreement with the Haryana Power Purchase Centre for supply to the state. The combined asset mix is designed to enable scheduled dispatch and improve supply predictability. Since the FDRE guidelines were introduced in 2023, more than 10 tenders totalling over 14 GW have been issued by central and state agencies including SJVN, NHPC, SECI and NTPC, with around 10 GW under construction. Juniper Green is an independent renewable power producer headquartered in Delhi NCR and reported an operational capacity of approximately 1.66 GWp (gigawatt peak) as of January 2026. The company is part of the AT Capital Group, a Singapore-based investment group.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement