Land issues pose challenges for MCL's coal corridor project
POWER & RENEWABLE ENERGY

Land issues pose challenges for MCL's coal corridor project

The Bankibahal-Bhedabahal dedicated coal corridor project by Mahanadi Coalfields Ltd (MCL) in Sundargarh district has finally commenced after years of delay. However, the project continues to face roadblocks due to land issues, raising uncertainties about meeting the 2023-end deadline set by the Works department, which is responsible for project execution. To expedite the project, the Works department divided the construction into separate packages, focusing on bridges along the alignment. While progress has been visible in bridge construction, the road construction phase, which requires private land, has been progressing slowly. MCL has provided the necessary funds for the project and has been urging the district administration and Works department to expedite the handover of the coal corridor.

The project, which should have been completed decades ago, received approval and funds in 2017. The four-lane road spanning 8.5 km from Bankibahal, with the remaining stretch being two lanes, covers a total length of approximately 30.8 km. Despite the completion of road laying work on most of the stretch and four out of five bridges, the project encountered a setback when the contract firm abruptly stopped work two months ago. Land disputes at Khamarbahal, Duduka, Budelkani, Jhapanga, and other areas are causing the project to remain stuck.

Authorities, including Sundargarh ADM (Revenue) Abhimanyu Behera, have assured that the land issues are minor and will be resolved soon. Superintending engineer of the Works department, Sundargarh division Narayan Patel, stated that four bridges have been completed, with the remaining bridge nearing completion. He also mentioned that road laying work is nearly finished, and the project is expected to be completed by the end of 2023. Despite the challenges posed by land disputes, efforts are underway to overcome the roadblocks and ensure the timely completion of MCL's coal corridor project, which holds significance for the region's coal transportation infrastructure.

The Bankibahal-Bhedabahal dedicated coal corridor project by Mahanadi Coalfields Ltd (MCL) in Sundargarh district has finally commenced after years of delay. However, the project continues to face roadblocks due to land issues, raising uncertainties about meeting the 2023-end deadline set by the Works department, which is responsible for project execution. To expedite the project, the Works department divided the construction into separate packages, focusing on bridges along the alignment. While progress has been visible in bridge construction, the road construction phase, which requires private land, has been progressing slowly. MCL has provided the necessary funds for the project and has been urging the district administration and Works department to expedite the handover of the coal corridor. The project, which should have been completed decades ago, received approval and funds in 2017. The four-lane road spanning 8.5 km from Bankibahal, with the remaining stretch being two lanes, covers a total length of approximately 30.8 km. Despite the completion of road laying work on most of the stretch and four out of five bridges, the project encountered a setback when the contract firm abruptly stopped work two months ago. Land disputes at Khamarbahal, Duduka, Budelkani, Jhapanga, and other areas are causing the project to remain stuck. Authorities, including Sundargarh ADM (Revenue) Abhimanyu Behera, have assured that the land issues are minor and will be resolved soon. Superintending engineer of the Works department, Sundargarh division Narayan Patel, stated that four bridges have been completed, with the remaining bridge nearing completion. He also mentioned that road laying work is nearly finished, and the project is expected to be completed by the end of 2023. Despite the challenges posed by land disputes, efforts are underway to overcome the roadblocks and ensure the timely completion of MCL's coal corridor project, which holds significance for the region's coal transportation infrastructure.

Next Story
Infrastructure Urban

Western Railway Seeks Rs 3.95 Billion Fee for BMC Water Pipelines

Western Railway has invoiced the Brihanmumbai Municipal Corporation for Rs 3.95 billion in Right of Way (RoW) licence fees covering a ten year period for underground water pipelines laid beneath railway land across Mumbai. The demand, disclosed through an RTI query by railway activist Samir Zaveri, requires payment in advance.These pipelines deliver filtered drinking water to millions of residents. Railway officials have based the charge on current market values of the land above the pipes, a valuation that has astonished civic authorities and policy experts.Zaveri points out that BMC su..

Next Story
Infrastructure Transport

Third Rail Tests Begin on Bengaluru Metro’s Pink Line

The long awaited Pink Line of Namma Metro has reached a key milestone as Bangalore Metro Rail Corporation Ltd (BMRCL) starts third rail electrification tests on the elevated section between Jayadeva and Tavarekere stations. This power supply check is the first in a series of technical validations required before the 21.3 km corridor can open.According to officials, the current trials cover the elevated stretch of the Kalena Agrahara–Nagawara route. Once the third rail passes safety checks, teams will move on to signal validation, telecommunications testing and loading trials to ver..

Next Story
Infrastructure Energy

MCL Plots Rs 400 Billion Thermal Plant, Green Projects

Mahanadi Coalfields Ltd (MCL) will invest about Rs 400 billion to build a 4,000 MW coal fired power station in partnership with Coal India and Odisha’s Energy Department.The miner also plans a high ash coal to ammonium nitrate plant (600,000 tpa) costing roughly Rs 117.82 billion with BCGCL and the state Industries Department.In renewables, MCL expects to spend Rs 120 billion on a 2,000 MW solar complex (ground mounted and floating), Rs 50 billion on a 500 MW pumped storage project, and Rs 9 billion on a 100 MW wind farm.These schemes align with MCL’s Vi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?