Rajasthan Solar Projects Face Daytime Curtailment Risk
POWER & RENEWABLE ENERGY

Rajasthan Solar Projects Face Daytime Curtailment Risk

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources.

A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours.

Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability.

Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins.

In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan.

Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity.

An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines.

According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources. A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours. Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability. Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins. In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan. Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity. An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines. According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Next Story
Infrastructure Urban

Powerplay Rolls Out Procurement-Linked Credit for Contractors

Powerplay has announced the launch of Powerplay Credit, a project-linked working capital solution aimed at easing cash flow pressures faced by contractors during active construction execution. The solution has gone live across key markets in South India, with a wider national rollout planned for 2026.The launch comes amid rising activity in India’s construction sector across infrastructure, housing, industrial corridors, renewable energy and urban redevelopment. Contractors executing large corporate and government projects often face extended payment cycles, stage-based billing and delayed r..

Next Story
Infrastructure Urban

Jyoti Structures Commissions Galvanisation at Second Nashik Unit

Jyoti Structures has commissioned galvanisation operations at its second tower manufacturing unit in Nashik, strengthening its in-house capabilities across critical stages of power transmission infrastructure production. The listed Engineering, Procurement and Construction (EPC) company operates globally and has delivered projects for customers across more than 50 countries.The second Nashik unit, with an annual manufacturing capacity of 36,000 metric tonnes, has become operational following the completion of installation, testing and readiness of the new galvanising facilities. With this deve..

Next Story
Infrastructure Energy

Rosatom Connects First Kursk NPP-2 Unit to National Grid

Rosatom has launched the first power unit of the Kursk Nuclear Power Plant-2 (Kursk NPP-2) into Russia’s Unified Energy System, marking a key milestone in the country’s nuclear energy programme. The initial grid connection took place at the end of the year, bringing a new source of low-carbon electricity online for the Kursk region and the broader Central Energy System.The newly commissioned unit is the first implementation of the VVER-TOI reactor design, which incorporates advanced safety and performance features. With an installed capacity of 1,250 MW, it is the most powerful nuclear pow..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App