Rajasthan Solar Projects Face Daytime Curtailment Risk
POWER & RENEWABLE ENERGY

Rajasthan Solar Projects Face Daytime Curtailment Risk

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources.

A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours.

Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability.

Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins.

In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan.

Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity.

An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines.

According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources. A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours. Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability. Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins. In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan. Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity. An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines. According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->