Rajasthan Solar Projects Face Daytime Curtailment Risk
POWER & RENEWABLE ENERGY

Rajasthan Solar Projects Face Daytime Curtailment Risk

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources.

A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours.

Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability.

Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins.

In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan.

Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity.

An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines.

According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources. A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours. Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability. Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins. In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan. Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity. An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines. According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Next Story
Infrastructure Transport

East Vinod Nagar Metro Station Wins NECA 2025 Honour

East Vinod Nagar Metro Station on Delhi Metro’s Pink Line has been named the “Best Performing Unit” in the metro stations category at the National Energy Conservation Awards (NECA) 2025, recognising its excellence in energy efficiency and conservation practices. The award was presented by President Droupadi Murmu at a ?????? held at Vigyan Bhawan on the occasion of National Energy Conservation Day. The recognition highlights Delhi Metro’s continued focus on sustainable operations and efficient energy management across its network. Delhi Metro Rail Corporation (DMRC) Managing Director..

Next Story
Infrastructure Transport

DMRC Begins Work On Lajpat Nagar–Saket Phase IV Corridor

The Delhi Metro Rail Corporation (DMRC) has commenced construction on the Lajpat Nagar–Saket G Block corridor under Phase IV, marking the first section beyond the project’s priority corridors where physical work has begun. The elevated corridor forms part of the Golden Line (Line 11) and will feature eight stations: Lajpat Nagar, Andrews Ganj, Greater Kailash-1, Chirag Delhi, Pushpa Bhawan, Saket District Centre, Pushp Vihar and Saket G Block. Once operational, the line is expected to significantly enhance metro connectivity across key parts of South Delhi. According to DMRC, the corrido..

Next Story
Infrastructure Transport

MoPSW Reviews Inland Water Transport Projects In Varanasi

A high-level review meeting chaired by Vijay Kumar, Secretary, Ministry of Ports, Shipping and Waterways (MoPSW), was held in Varanasi to assess the progress of Inland Water Transport (IWT) projects and advance plans to develop the city as a major IWT hub. During the meeting, Kumar reviewed multiple ongoing IWT initiatives, with senior officials from central and state agencies participating to strengthen coordination and accelerate project implementation. In line with the Ministry’s vision for Varanasi, discussions covered the expansion of cargo handling capacity at the Multi-Modal Terminal..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App