Rajasthan Solar Projects Face Daytime Curtailment Risk
POWER & RENEWABLE ENERGY

Rajasthan Solar Projects Face Daytime Curtailment Risk

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources.

A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours.

Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability.

Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins.

In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan.

Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity.

An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines.

According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Nearly 4.3 GW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth around Rs 200 billion at risk, according to industry sources. A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently operating under the Temporary General Network Access framework as their associated transmission systems are yet to be commissioned. With available transmission margins fully exhausted, power generation from these plants has been entirely curtailed during daytime hours. Data from the Northern Regional Load Despatch Centre shows that Rajasthan has about 23 GW of commissioned renewable energy capacity, while its transmission capacity stands at roughly 18.9 GW. This entire transmission capacity has been allocated to projects with long-term General Network Access, leaving more than 4 GW of capacity operating under T-GNA without adequate evacuation capability. Industry officials said that despite the commissioning of the 765 kV Khetri–Narela transmission line, only around 600 MW of additional transmission capacity became available. At the same time, more than 4.3 GW of capacity was operationalised under long-term GNA, effectively absorbing all surplus margins. In an email dated 11 December, the NRLDC withdrew the No Objection Certificates for the 26 projects following the commissioning of the Khetri–Narela line and the operationalisation of long-term GNA. Developers warned that prolonged curtailment could severely impact project viability and debt servicing, flagging the issue as a growing systemic risk as renewable generation continues to outpace transmission additions in resource-rich states such as Rajasthan. Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, dynamic reallocation of unused GNA margins during low utilisation periods, and the use of Dynamic Line Rating to maximise real-time transmission capacity. An industry official said most of the 4.3 GW capacity is well within its notified connectivity start date but is being forced to operate under T-GNA due to delays in commissioning associated transmission systems. He added that there is currently no formal mechanism for generators to assess in advance the transmission capacity that may become available with the commissioning of new lines. According to industry estimates, if Rajasthan’s 18.9 GW transmission capacity were equitably distributed across its 23 GW of operational renewable capacity, peak-hour curtailment would be limited to around 15 per cent, which would be manageable on an annualised basis. Without immediate intervention, however, developers warned that large-scale renewable assets risk becoming stranded.

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement