+
SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects
POWER & RENEWABLE ENERGY

SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4.

The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW.

The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement.

The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above.

According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity.

To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used.

Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project.

Eligibility:

The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date.

The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date.

The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity.

The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26.

The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%.

In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme.

Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects.

According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned.

Image Source


Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4. The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW. The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement. The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above. According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity. To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used. Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project. Eligibility: The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date. The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date. The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity. The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26. The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%. In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme. Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects. According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned. Image Source Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

Next Story
Real Estate

DLF Returns to Mumbai with Premium Andheri Residential Project

Delhi-NCR based real estate major DLF announced its return to the Mumbai market on 17 July with the launch of its premium residential project, The WestPark, in Andheri. The first phase includes 416 apartments spread across four towers, with two towers launched on the announcement day. The company plans to invest over Rs 8 billion in the project and expects a topline exceeding Rs 20 billion from Phase 1.“We have launched two towers and, given the strong response, plan to unveil the remaining two towers ahead of schedule, within the next few days,” said Aakash Ohri, Joint Managing Director o..

Next Story
Infrastructure Urban

APCRDA Advances Net Zero Goal with IGBC Training for Officials

In a significant stride towards Andhra Pradesh’s Net Zero target by 2040 and the Swarna Andhra 2047 vision, the Andhra Pradesh Capital Region Development Authority (APCRDA), in partnership with the Indian Green Building Council (IGBC), conducted a high-level capacity-building programme for senior officials in Vijayawada on Friday.Held at a city hotel, the session saw the participation of over 50 senior APCRDA officials, including the Engineer-in-Chief, Chief Engineer (H&B), Director (Planning), Director (Environment), and heads of key departments. The training centred on IGBC’s Green B..

Next Story
Infrastructure Energy

Assam Solar Project Halted as Waaree EPC Contract Is Cancelled

Following the Assam government’s withdrawal from its proposed solar project, the Engineering, Procurement, and Construction (EPC) contract awarded to Waaree Renewable has been suspended. Waaree Group’s EPC division informed the stock exchange of this development through a regulatory filing.The Assam solar project was suspended due to funding challenges, which rendered the initiative unviable for the state government. Waaree Renewable Transmission Limited (RTL) explained that the Government of Assam has withdrawn the project’s funding via the Asian Development Bank (ADB) loan. Consequentl..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?