+
SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects
POWER & RENEWABLE ENERGY

SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4.

The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW.

The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement.

The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above.

According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity.

To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used.

Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project.

Eligibility:

The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date.

The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date.

The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity.

The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26.

The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%.

In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme.

Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects.

According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned.

Image Source


Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4. The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW. The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement. The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above. According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity. To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used. Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project. Eligibility: The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date. The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date. The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity. The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26. The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%. In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme. Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects. According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned. Image Source Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement