+
SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects
POWER & RENEWABLE ENERGY

SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4.

The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW.

The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement.

The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above.

According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity.

To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used.

Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project.

Eligibility:

The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date.

The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date.

The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity.

The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26.

The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%.

In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme.

Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects.

According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned.

Image Source


Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4. The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW. The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement. The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above. According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity. To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used. Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project. Eligibility: The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date. The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date. The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity. The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26. The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%. In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme. Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects. According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned. Image Source Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

Next Story
Infrastructure Urban

GRM Overseas Reports Q1 FY26 Results; Strengthens Global & Domestic Presence

GRM Overseas has announced its unaudited financial results for the quarter ended 30 June 2025. The company reported a positive performance in terms of margins and profitability, despite topline pressures from global geopolitical challenges.Atul Garg, Managing Director, said:"We have maintained healthy margins and profitability while navigating short-term headwinds. Our focus remains on expanding our product portfolio, enhancing brand visibility, and deepening our distribution network. Internationally, we continue to hold a strong position in the Basmati rice export market, particularly in the ..

Next Story
Infrastructure Urban

Zuari Industries Posts Q1 FY26 Revenue Growth; PAT Turns Positive

Zuari Industries has announced its audited financial results for the quarter ended 30 June 2025.On a standalone basis, the company reported Revenue from Operations of Rs 2.10 billion and Operating EBITDA of Rs 220.4 million. Standalone Profit Before Tax (PBT), before exceptional items, stood at Rs 90 million.On a consolidated basis, Revenue rose 10.5 per cent year-on-year to Rs 2.67 billion, while Profit After Tax (PAT) stood at Rs 50 million compared to a loss of Rs 330.6 million in Q1 FY25.Segment HighlightsSugar, Power & Ethanol: Operations were impacted by an early mill closure due to ..

Next Story
Infrastructure Urban

Karnataka Bank Reports Q1 FY26 Net Profit of Rs 2.92 Bn

Karnataka Bank has announced a net profit of Rs 2.92 billion for the first quarter of FY26, compared to Rs 4 billion in Q1 FY25. The results were approved at the Board of Directors meeting held on 13 August 2025 at the Bank’s headquarters in Mangaluru.Asset Quality & Capital AdequacyGross NPA: 3.46 per cent, improved from 3.54 per cent in Q1 FY25.Net NPA: 1.44 per cent, down from 1.66 per cent in Q1 FY25.Capital Adequacy Ratio (CAR): 20.46 per cent, up from 17.64 per cent in Q1 FY25.Announcing the results, Raghavendra S Bhat, Managing Director & CEO, said:"The Bank has registered a m..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?