SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects
POWER & RENEWABLE ENERGY

SECI invites bids for 1.2 GW ISTS wind-solar hybrid projects

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4.

The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW.

The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement.

The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above.

According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity.

To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used.

Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project.

Eligibility:

The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date.

The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date.

The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity.

The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26.

The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%.

In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme.

Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects.

According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned.

Image Source


Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

The Solar Energy Corporation of India (SECI) has opened a tender inviting bids to set up 1,200 MW interstate transmission system (ISTS) connected wind-solar hybrid power projects on a build, own, operate basis across India in Tranche-4. The minimum bid capacity should be 50 MW, with at least 50 MW of project capacity being proposed at each project site. The maximum capacity has been set at 1,200 MW. The successful bidder will have to submit a performance bank guarantee for a value of Rs 1 million per MW per project latest by seven days before signing the power purchase agreement. The hybrid power projects must be designed for interconnection with the transmission network of the central transmission utility at the voltage level of 220 kV or above. According to the tender, a hybrid power project should comprise two components—one solar and one wind power project. The rated installed project capacity of either of the two components should be at least 33% of the contracted capacity. To ensure only quality systems are installed, the wind turbine models listed in the Revised List of Models and Manufacturers issued by the Ministry of New and Renewable Energy (MoNRE) will have to be used. Bidders have been adviced to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while preparing their bids. The bidder should provide information about the solar panels and wind turbines to be installed in the project. Eligibility: The bidder’s net worth should be equal to or greater than Rs 1 crore per MW of the quoted capacity, as on the day at least seven days before the bid submission date. The bidder’s annual turnover should be Rs 75 lakh per MW of the quoted capacity during the last financial year. The internal resource generation capacity should be Rs 15 lakh per MW of the quoted capacity as of the previous financial year’s last date. The bidder should also have a sanction letter from the lending institution committing a line of credit for a minimum of Rs 18.75 lakh per MW of the quoted capacity. The last date to submit the bids is 28 May 2021. The pre-bid meeting will be held on April 26. The project should be designed for interconnection with the ISTS per the prevailing Central Electricity Regulatory Commission (CERC) regulations. The declared annual capacity utilisation factor should not be less than 30%. In December 2020, three companies won 1.2 GW of solar-wind hybrid projects quoting a tariff of Rs 2.41 per kWh, the lowest-ever for solar-wind hybrid projects. The tariff was discovered in the SECI’s auction for setting up 1.2 GW of interstate transmission-connected wind-solar hybrid power projects under Tranche-3 of the ISTS programme. Earlier, Adani Green Energy had emerged as the lowest bidder in SECI’s auction for 1,200 MW of ISTS-connected solar-wind hybrid power projects under Tranche-2. Adani Green Energy had quoted a tariff of Rs 2.69 kWh to set up 600 MW of solar-wind hybrid projects. According to Mercom India, SECI has issued a total of 3.6 GW of wind-solar hybrid tenders under Tranche 1, 2 and 3, out of which 2.76 GW of capacity has been auctioned. Image Source Also read: Winners of SECI’s 1.2 GW wind auction in Karnataka

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->