Udangudi Thermal Plant’s First Unit Synced to Grid
POWER & RENEWABLE ENERGY

Udangudi Thermal Plant’s First Unit Synced to Grid

The first 660 MW unit of the Udangudi Supercritical Thermal Power Project in Tamil Nadu has finally been synchronised with the grid, marking a long-awaited milestone for the state’s power sector. The project, being developed at a cost of Rs 13,076 crore by Tamil Nadu Power Generation and Distribution Corporation Ltd (TNGPCL), was originally scheduled for commissioning in 2021 but faced repeated delays due to court disputes and the COVID-19 pandemic.
The synchronisation took place at 7.56 pm on Thursday, when the unit produced 42 MW during its initial trial run. Officials noted that the plant will undergo inspections and troubleshooting during trial operations before moving toward commercial generation in the coming months.
A senior TNGPCL official said the unit is expected to be commissioned in time to meet next summer’s projected peak demand of 22,000 MW. “Generation from our own thermal units will reduce reliance on high-cost power purchases from outside sources,” the official added.
The project’s engineering, procurement, and construction contract was awarded to Bharat Heavy Electricals Limited (BHEL) in December 2017. Alongside Udangudi, TNGPCL chairman J Radhakrishnan has directed BHEL to accelerate work on the 2×660 MW Ennore SEZ supercritical project, with at least one unit targeted for commissioning by March 2026.
During a site visit at Vayalur in Tiruvallur district, Radhakrishnan said that about 70 per cent of construction at Ennore had been completed and urged faster resolution of legal disputes delaying the work. He also reviewed operations at the North Chennai thermal stations, stressing timely maintenance and replacement of ageing components.

The first 660 MW unit of the Udangudi Supercritical Thermal Power Project in Tamil Nadu has finally been synchronised with the grid, marking a long-awaited milestone for the state’s power sector. The project, being developed at a cost of Rs 13,076 crore by Tamil Nadu Power Generation and Distribution Corporation Ltd (TNGPCL), was originally scheduled for commissioning in 2021 but faced repeated delays due to court disputes and the COVID-19 pandemic.The synchronisation took place at 7.56 pm on Thursday, when the unit produced 42 MW during its initial trial run. Officials noted that the plant will undergo inspections and troubleshooting during trial operations before moving toward commercial generation in the coming months.A senior TNGPCL official said the unit is expected to be commissioned in time to meet next summer’s projected peak demand of 22,000 MW. “Generation from our own thermal units will reduce reliance on high-cost power purchases from outside sources,” the official added.The project’s engineering, procurement, and construction contract was awarded to Bharat Heavy Electricals Limited (BHEL) in December 2017. Alongside Udangudi, TNGPCL chairman J Radhakrishnan has directed BHEL to accelerate work on the 2×660 MW Ennore SEZ supercritical project, with at least one unit targeted for commissioning by March 2026.During a site visit at Vayalur in Tiruvallur district, Radhakrishnan said that about 70 per cent of construction at Ennore had been completed and urged faster resolution of legal disputes delaying the work. He also reviewed operations at the North Chennai thermal stations, stressing timely maintenance and replacement of ageing components.

Next Story
Infrastructure Urban

CFI Appoints New National Council for FY27 and FY28

The Construction Federation of India (CFI) has announced its newly elected National Council and office bearers for a two-year term covering FY27 and FY28. M. V. Satish, Advisor to CMD and Lead Ambassador for Middle East, L&T, has been elected President; Priti Patel, Chief Strategy & Growth Officer, Tata Projects, has been appointed Vice President; and Ajit Bhate, Managing Director, Precast India Infrastructures, has taken charge as Treasurer.The newly formed National Council brings together senior leaders from major EPC and infrastructure companies, reflecting CFI’s continued focus o..

Next Story
Infrastructure Urban

India REIT Market Gains Momentum with Strong Returns

India’s Real Estate Investment Trust (REIT) market is witnessing strong growth, emerging as a competitive investment avenue both domestically and across Asia. According to a recent ANAROCK report released at EXCELERATE 2026 by NAREDCO Maharashtra NextGen, the sector is evolving into a mature asset class driven by solid fundamentals, regulatory backing and rising investor confidence.The introduction of Small and Medium REITs (SM REITs) in 2025 has further widened access through fractional ownership, unlocking a potential monetisation opportunity of Rs 670–710 billion. Indian REITs have deli..

Next Story
Infrastructure Energy

G R Infraprojects Secures Rs 4,130 Million BESS Contract From NTPC

G R Infraprojects said it has secured a contract from NTPC to supply and implement a battery energy storage system (BESS) valued at Rs 4,130 million (mn). The company reported the order was awarded as part of NTPC's ongoing efforts to enhance grid flexibility and energy storage capacity. The contract represents a notable addition to the firm's project pipeline and underscores demand for utility scale storage solutions. The award is expected to strengthen G R Infraprojects' presence in the energy infrastructure sector and to contribute to the firm's order book and future revenues, subject to st..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement