Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower
Equipment

Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.
Liebherr Tower Crane Center and Tower Crane Solutions provide implementation support
A high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.
“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.
In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.
The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.
Fast construction progress with a four-shift system to achieve spectacular heights
Two luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.Liebherr Tower Crane Center and Tower Crane Solutions provide implementation supportA high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.Fast construction progress with a four-shift system to achieve spectacular heightsTwo luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

Next Story
Infrastructure Urban

IHC and Adani to Invest US$11.5 bn in Odisha Aluminium Project

Abu Dhabi's International Holding Company (IHC) will invest US$11.5 bn in an integrated aluminium project in the eastern Indian state of Odisha in a joint venture with the Adani Group, a state official said. The official said the announcement represented the country's largest foreign investment in mining and metallurgy. Officials said the venture would span both mining and metallurgical activities across several facilities in the state. The project has been described as integrated, encompassing upstream bauxite extraction and downstream smelting and metallurgy, and is intended to develop a com..

Next Story
Infrastructure Transport

Air India and SIAEC to Explore MRO Joint Venture in India

Air India and SIA Engineering Company (SIAEC) have signed a memorandum of understanding (MoU) to explore the formation of a maintenance, repair and overhaul joint venture in India. The MoU, signed on Friday, will examine collaboration to develop India as a global aviation MRO hub and to serve growing needs across the Indian and regional markets. SIA Engineering Company, part of the Singapore Airlines Group which holds a 25.1 per cent stake in Air India, will bring technical expertise alongside Air India's established airline operations network. The partnership builds on existing cooperation be..

Next Story
Infrastructure Transport

Assam and Centre Review Aviation Projects Push Silchar Airport Approval

Assam and the Centre on Thursday, July two reviewed a series of aviation infrastructure projects aimed at strengthening air connectivity across the state, with the proposed greenfield airport at Silchar emerging as a key priority. The review formed part of broader efforts to position Assam as a major aviation and logistics hub for the north east. Officials outlined timelines and preparatory work that they said would guide the next stages of project approvals. The Chief Minister met the Union Civil Aviation Minister at Rajiv Gandhi Bhavan in New Delhi and described the meeting as very productiv..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement