Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower
Equipment

Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.
Liebherr Tower Crane Center and Tower Crane Solutions provide implementation support
A high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.
“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.
In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.
The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.
Fast construction progress with a four-shift system to achieve spectacular heights
Two luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.Liebherr Tower Crane Center and Tower Crane Solutions provide implementation supportA high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.Fast construction progress with a four-shift system to achieve spectacular heightsTwo luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

Next Story
Infrastructure Energy

Hero Future Energies Secures Rs 19.08 Bn for 120 MW Hybrid Project

Hero Future Energies (HFE), through its SPV Clean Renewable Energy Hybrid Three, has secured Rs 19,080 million in funding from State Bank of India (lead) and Canara Bank for the development of its 120 MW renewable energy (RE) hybrid project in Kurnool, Andhra Pradesh.The project, contracted with SJVN, integrates wind, solar, and storage technologies to provide reliable peak power. The funding, structured with a 21-year repayment tenure, will support timely project execution and the commencement of commercial operations.This financial closure underscores the banking community’s confidence in ..

Next Story
Equipment

SANY India Opens New 3S Branches in Visakhapatnam and Palwancha

SANY India, a leading manufacturer of construction, mining, road, logistics, and energy equipment, has expanded its presence in southern India by inaugurating two new 3S (Sales, Service, Spares) branch offices in Visakhapatnam (Andhra Pradesh) and Palwancha (Telangana). The expansion, in partnership with its authorised dealer Madhura Engineering Services, reinforces SANY’s commitment to providing world-class equipment and faster service access in key industrial and mining hubs.These new facilities complement Madhura Engineering’s existing branches in Guntur and Vijayawada, marking a strate..

Next Story
Real Estate

Compact Homes Lead Demand as Indian Housing Market Stabilises: Magicbricks

Magicbricks, India’s leading real estate platform, has released its PropIndex Report for July–September 2025, revealing signs of stabilisation in the housing market. Despite affordability pressures, housing demand grew 3.1 per cent QoQ, driven largely by compact homes. The share of 1–2 BHK units rose to 54 per cent of total demand, reversing a two-year decline and signalling renewed focus on affordability.While overall supply increased marginally by 1 per cent QoQ (–4.5 per cent YoY), property prices continued to rise. Pune (+41.4 per cent YoY), Mumbai (+29.6 per cent YoY), and Greater..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?