+
Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower
Equipment

Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.
Liebherr Tower Crane Center and Tower Crane Solutions provide implementation support
A high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.
“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.
In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.
The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.
Fast construction progress with a four-shift system to achieve spectacular heights
Two luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.Liebherr Tower Crane Center and Tower Crane Solutions provide implementation supportA high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.Fast construction progress with a four-shift system to achieve spectacular heightsTwo luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App