Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower
Equipment

Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.
Liebherr Tower Crane Center and Tower Crane Solutions provide implementation support
A high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.
“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.
In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.
The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.
Fast construction progress with a four-shift system to achieve spectacular heights
Two luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.Liebherr Tower Crane Center and Tower Crane Solutions provide implementation supportA high-performance crane solution was needed to meet the exceptionally tight construction deadline of just 90 days. The Liebherr Tower Crane Center (TCC) provided the Liebherr 542 HC-L and 258 HC-L cranes from its rental fleet to facilitate rapid construction progress.“To secure 24/7 operation, we moved key spare parts such as a new fibre rope and various modules directly onto site in advance so that time isn’t lost if these are needed,” says Stefan Gröber, Head of TCC Used & Rental.In addition, Tower Crane Solutions (TCS), Liebherr’s project department for large and special projects, provided detailed calculations for optimal tie-in geometry and made the required tie bars available through the Tower Crane Center. The climbing steps were also carefully planned beforehand to ensure an efficient construction process. An optimal crane configuration, including hoist rope lengths, power supply and tower bracing, was put together specifically for the project. TCS also provided the structural data for foundation loading and tensioning forces and worked closely with the Tower Crane Center to coordinate tie-in geometries. This custom solution successfully met the project’s challenging requirements.The project was successfully completed within the timeline because of the excellent collaboration between TCC, TCS and the corresponding side in Sweden, Head Of Tower Cranes Skanska South District, Fredrik Funke and Project Specialist Anders Ekström from company Ekström Lyftkonsult AB.Fast construction progress with a four-shift system to achieve spectacular heightsTwo luffing jib cranes, a 258 HC-L 10/18 Fibre and a 542 HC-L 12/24 Litronic, were used on site and reached a final tower height of 213 and 210 metres respectively. The tower was constructed at an extraordinary speed. In just three months, the structure grew by an average of 2.6 metres per day thanks to a four-shift system and round-the-clock operation. The entire structure covers an area of 23 m2 and will boast a total volume of 112,445 m³, roughly the equivalent of 45 Olympic-sized swimming pools.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement