Three WOLFF Cranes Enable Spectacular Aurach Valley Bridge Project
Equipment

Three WOLFF Cranes Enable Spectacular Aurach Valley Bridge Project

After over three years of construction, the new Aurach Bridge near the Regau junction opened to traffic in early September. Three WOLFF 7534.16 Clear cranes were deployed on behalf of the Habau/Porr joint venture to support the demolition and reconstruction of the A1 West Motorway bridge. Long-standing Wolffkran customer Habau supplied the flat-top cranes, each with a maximum load capacity of 16.5 tons. The cranes, installed in 2022, were mounted on two 77.6-meter towers and one 64.1-meter tower.

The cranes handled demolition of the old bridge and the transport of reinforcing steel, formwork elements, precast concrete components, construction vehicles, and concrete for the new superstructures and piers. Freestanding loads of up to 13 tons were lifted safely. After approximately three years on site, the cranes were dismantled in March 2025.

Precise logistics were essential due to restricted space between highway traffic, railway tracks, and a stream. Numerous safety and water protection regulations were observed. The Wolffkran team supported site planning and equipped the cranes with slew limiters and cameras to enhance load handling and safety.

Construction involved building a side-position bridge adjacent to the old structure to maintain traffic flow. Once the old bridge was demolished, the new bridge was constructed in its final position. In spring 2025, the deck built in the side position was laterally shifted onto the newly built piers using hydraulics and sliding tracks.

Habau has relied on Wolffkran cranes since 2008. For the Aurach Valley project, the WOLFF 7534.16 Clear’s combination of high load capacity and large freestanding hook height proved decisive.

After over three years of construction, the new Aurach Bridge near the Regau junction opened to traffic in early September. Three WOLFF 7534.16 Clear cranes were deployed on behalf of the Habau/Porr joint venture to support the demolition and reconstruction of the A1 West Motorway bridge. Long-standing Wolffkran customer Habau supplied the flat-top cranes, each with a maximum load capacity of 16.5 tons. The cranes, installed in 2022, were mounted on two 77.6-meter towers and one 64.1-meter tower.The cranes handled demolition of the old bridge and the transport of reinforcing steel, formwork elements, precast concrete components, construction vehicles, and concrete for the new superstructures and piers. Freestanding loads of up to 13 tons were lifted safely. After approximately three years on site, the cranes were dismantled in March 2025.Precise logistics were essential due to restricted space between highway traffic, railway tracks, and a stream. Numerous safety and water protection regulations were observed. The Wolffkran team supported site planning and equipped the cranes with slew limiters and cameras to enhance load handling and safety.Construction involved building a side-position bridge adjacent to the old structure to maintain traffic flow. Once the old bridge was demolished, the new bridge was constructed in its final position. In spring 2025, the deck built in the side position was laterally shifted onto the newly built piers using hydraulics and sliding tracks.Habau has relied on Wolffkran cranes since 2008. For the Aurach Valley project, the WOLFF 7534.16 Clear’s combination of high load capacity and large freestanding hook height proved decisive.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement