All about the world’s tallest modular building!
Real Estate

All about the world’s tallest modular building!

Construction company Bouygues Bâtiment International has built the Clement Canopy, a pair of 140-m-high towers made of prefabricated concrete modules. The company claims that the development in Singapore has set a new record for the tallest modular buildings. Previously the title had been held by 101 George Street, a 135-m tower built in Croydon, England, by Tide Construction. Notably, the first high-rise modular tower was built in New York in 2016 by SHoP Architects. 

Recently, CONSTRUCTION WORLD conducted a webinar on how ‘Precast & Prefab Technology – The Answer to Fast Track Construction Industry Growth.’ Our esteemed panelists deliberated upon critical need to adopt latest construction technologies and standards. The webinar discussed various advantages of precast technology, including in areas of timely delivery and accurate project execution. 

The specs 

Clement Canopy is a residential condominium located along Clementi Avenue. The development has a gross floor area of 50,200 sq m, consisting of 505 dwelling units spread over two 40-storey blocks and a multi storey car park with one basement floor. The basement floor, multi-storey car park and first floor of the blocks are of conventional construction, while the typical floors from level 2 to 40 have adopted prefabricated prefinished volumetric construction (PPVC). The PPVC modules were designed as six-sided concrete PPVC modules. The weight of the modules range from 26 tonne to 31 tonne and have been installed using two 48-tonne capacity tower cranes. 

Clement Canopy's 1,899 prefabricated and pre-finished modules were built off-site whose weight ranged from 37,000 to 64,000 lbs. Each module is around 85 per cent finished off-site, before then being assembled onsite. The main contractor was able to install 10 to 12 modules per day with a floor cycle time of 7 days. The entire project was completed in 30 months, six months ahead of the scheduled date.

The architecture has been designed by ADDP Architects LLP, structural engineering by TW-Asia Consultants Pte Ltd and main contractor being Dragages Singapore Pte Ltd. The construction of the skyscraper started in 2016 and was completed in 2019.



Fast, reliable, flexible

The pioneer technique developed by MCT Italy to cast 3D modules in a fast, reliable, and flexible way thanks to the joint action of high-speed flying bucket and automatic casting machines increase the benefits of modular and prefabrication processes whereby:

Construction time can be reduced up to 50 per cent
On site labour can be reduced by 30 per cent
Reduction of jobsite noise, pollution and neighbourhood disruption
Improvements in jobsite safety and the quality of the finished product.

The module's structures are cast from concrete in a yard in Senai, Malaysia; then a factory in Tuas, West Singapore, carries out the fit-out in 15-days to a nearly finished stage. This includes, the painting, windows frame and glazing, doors, wardrobes, and MEP (mechanical, electrical and plumbing) including water and sanitary pipes, electrical conduits and ducting, which are all totally finished before the modules arrive on site. Clement Canopy's concrete core was built at the same time as the modules were stacked and installed, in a carefully choreographed sequence. This method helped reduce the time of construction and was more eco-friendly as the modules were built off-site in an eco-friendly environment. By industrialising and building 50 per cent of the project offsite, loss of time due to poor on-site weather conditions was mitigated. 

PPVC benefits

The adoption of PPVC at The Clement Canopy brought about many learning points in design, production and site works. While quality of workmanship was improved as the bulk of architectural works were carried out in a factory-controlled environment, strict site control and discipline had to be maintained to ensure minimal damages to the finishes. Early confirmation of drawings and materials represented one of the major hurdles towards ensuring a smooth production cycle. Another important decision to be made was the location of the heavy-duty tower crane to determine the crane’s foundation and its tie-back to the main tower. This affected the overall structural design of the residential towers and modules had to be strengthened to cater for this additional loading. The adoption of PPVC has helped all stakeholders of the project in achieving shorter construction duration, higher quality workmanship, safer construction site and lesser disruptions to the surroundings schools.

Construction company Bouygues Bâtiment International has built the Clement Canopy, a pair of 140-m-high towers made of prefabricated concrete modules. The company claims that the development in Singapore has set a new record for the tallest modular buildings. Previously the title had been held by 101 George Street, a 135-m tower built in Croydon, England, by Tide Construction. Notably, the first high-rise modular tower was built in New York in 2016 by SHoP Architects. Recently, CONSTRUCTION WORLD conducted a webinar on how ‘Precast & Prefab Technology – The Answer to Fast Track Construction Industry Growth.’ Our esteemed panelists deliberated upon critical need to adopt latest construction technologies and standards. The webinar discussed various advantages of precast technology, including in areas of timely delivery and accurate project execution. The specs Clement Canopy is a residential condominium located along Clementi Avenue. The development has a gross floor area of 50,200 sq m, consisting of 505 dwelling units spread over two 40-storey blocks and a multi storey car park with one basement floor. The basement floor, multi-storey car park and first floor of the blocks are of conventional construction, while the typical floors from level 2 to 40 have adopted prefabricated prefinished volumetric construction (PPVC). The PPVC modules were designed as six-sided concrete PPVC modules. The weight of the modules range from 26 tonne to 31 tonne and have been installed using two 48-tonne capacity tower cranes. Clement Canopy's 1,899 prefabricated and pre-finished modules were built off-site whose weight ranged from 37,000 to 64,000 lbs. Each module is around 85 per cent finished off-site, before then being assembled onsite. The main contractor was able to install 10 to 12 modules per day with a floor cycle time of 7 days. The entire project was completed in 30 months, six months ahead of the scheduled date.The architecture has been designed by ADDP Architects LLP, structural engineering by TW-Asia Consultants Pte Ltd and main contractor being Dragages Singapore Pte Ltd. The construction of the skyscraper started in 2016 and was completed in 2019.Fast, reliable, flexibleThe pioneer technique developed by MCT Italy to cast 3D modules in a fast, reliable, and flexible way thanks to the joint action of high-speed flying bucket and automatic casting machines increase the benefits of modular and prefabrication processes whereby:● Construction time can be reduced up to 50 per cent● On site labour can be reduced by 30 per cent● Reduction of jobsite noise, pollution and neighbourhood disruption● Improvements in jobsite safety and the quality of the finished product.The module's structures are cast from concrete in a yard in Senai, Malaysia; then a factory in Tuas, West Singapore, carries out the fit-out in 15-days to a nearly finished stage. This includes, the painting, windows frame and glazing, doors, wardrobes, and MEP (mechanical, electrical and plumbing) including water and sanitary pipes, electrical conduits and ducting, which are all totally finished before the modules arrive on site. Clement Canopy's concrete core was built at the same time as the modules were stacked and installed, in a carefully choreographed sequence. This method helped reduce the time of construction and was more eco-friendly as the modules were built off-site in an eco-friendly environment. By industrialising and building 50 per cent of the project offsite, loss of time due to poor on-site weather conditions was mitigated. PPVC benefitsThe adoption of PPVC at The Clement Canopy brought about many learning points in design, production and site works. While quality of workmanship was improved as the bulk of architectural works were carried out in a factory-controlled environment, strict site control and discipline had to be maintained to ensure minimal damages to the finishes. Early confirmation of drawings and materials represented one of the major hurdles towards ensuring a smooth production cycle. Another important decision to be made was the location of the heavy-duty tower crane to determine the crane’s foundation and its tie-back to the main tower. This affected the overall structural design of the residential towers and modules had to be strengthened to cater for this additional loading. The adoption of PPVC has helped all stakeholders of the project in achieving shorter construction duration, higher quality workmanship, safer construction site and lesser disruptions to the surroundings schools.

Next Story
Infrastructure Energy

NARCL Sells Rs 37.63 Billion of Wind World Debt to Omkara ARC

The National Asset Reconstruction Company Limited (NARCL) has successfully sold Rs 37.63 billion of Wind World’s outstanding debt, marking a significant step in managing stressed assets within India’s renewable energy sector. The transaction forms part of wider efforts to resolve non-performing loans and bolster financial stability in the industry.Omkara ARC emerged as the anchor bidder in the deal, demonstrating strong investor interest in renewable energy debt. Anchor bidders play a vital role in ensuring successful debt resolution and attracting participation from other investors in suc..

Next Story
Infrastructure Energy

Madhya Pradesh Targets 50 Per Cent Power From Renewable Sources

Madhya Pradesh is ramping up its green energy generation, aiming for renewable sources to account for 50 per cent of the state’s total power consumption, a senior official has announced.“Renewable energy cannot be ignored. Solar power is now a viable option, and we are committed to significantly enhancing green energy generation in Madhya Pradesh, targeting 50 per cent of total power consumption from renewable sources,” said Manu Srivastava, Additional Chief Secretary of Madhya Pradesh Urja Vikas Nigam, on Friday.Speaking at the inaugural session of the 8th GRIHA Regional Conclave in Bho..

Next Story
Infrastructure Transport

High-Speed Expressway to Cut Ayodhya–Varanasi Travel to Two Hours

Travel between Ayodhya and Varanasi is set to become faster and more convenient, as the National Highways Authority of India (NHAI) begins planning a nearly 200-km high-speed access-controlled expressway connecting the two cities. The tender process has been initiated to prepare the Detailed Project Report (DPR) for the project.Former MP Lallu Singh stated, “Upon completion, the distance from Ayodhya to Kashi can be covered in just two hours.” He added, “The expressway will connect to the Purvanchal Expressway, further enhancing connectivity from Ayodhya to Delhi.”The Ministry of Road ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?