Current Time taken for Building Affordable Homes
Real Estate

Current Time taken for Building Affordable Homes

“Currently, we are developing 6-7 lakh sq ft in 18 months at one location or project at competitive costs of development (which includes construction of buildings with all the infrastructure – beginning with the road, boundary wall, STP, UGT, landscape and hardscape, as well as all electrical and plumbing works),” shares Amit Pal, Vice President-Operations, Mahindra Happinest. At its Happinest Avadi project in Chennai, the company has completed and handed over 4.35 lakh sq ft of the total 7.35 lakh sq ft in about 18 months. “If, in future, we are required to complete 1 million sq ft in 18 months, we are geared up for it,” he adds. “We have a 1-million-sq-ft project coming up in Kalyan, which we are aiming to complete in 24 months.”

VBHC Value Homes currently has close to 0.5 million sq ft under construction across various projects. The cost of development per sq ft would clearly vary depending on the type of construction and location, says Rahul Sabharwal, CEO, VBHC Value Homes. While the time for development again is dependent on the construction, he adds, “Ideally, for a G+4 construction, we would take between 18 and 20 months for completion, while for a high-rise of 20+ floors it would be between 24 and 30 months. The component to look at to reduce time would be finishing activities, tiling and painting being the foremost.”

NCC has 45 million sq ft of affordable housing projects under development under the EPC mode. “In the past year, we have constructed at the speed of almost 125 flats per day,” says PNVS Murthy, Vice-President (Tech), NCC. “With one set of aluminium formwork, we can complete one floor (on an average, two flats a day with one set of aluminium formwork).” 

Brick Eagle, a company that runs an incubator to support entrepreneurs (developers or service providers) operating in the affordable housing sector, currently has 500 acre under management, at various stages of development. When asked about the time and cost to build, Rajesh Krishnan, Founder & CEO, Brick Eagle, responds, “It is a function of the product specification. G+2 structures can be done quite quickly, at even Rs 1,000 a sq ft; G+22 would be about Rs 2,000 per sq ft.”

- SERAPHINA D’SOUZA

“Currently, we are developing 6-7 lakh sq ft in 18 months at one location or project at competitive costs of development (which includes construction of buildings with all the infrastructure – beginning with the road, boundary wall, STP, UGT, landscape and hardscape, as well as all electrical and plumbing works),” shares Amit Pal, Vice President-Operations, Mahindra Happinest. At its Happinest Avadi project in Chennai, the company has completed and handed over 4.35 lakh sq ft of the total 7.35 lakh sq ft in about 18 months. “If, in future, we are required to complete 1 million sq ft in 18 months, we are geared up for it,” he adds. “We have a 1-million-sq-ft project coming up in Kalyan, which we are aiming to complete in 24 months.”VBHC Value Homes currently has close to 0.5 million sq ft under construction across various projects. The cost of development per sq ft would clearly vary depending on the type of construction and location, says Rahul Sabharwal, CEO, VBHC Value Homes. While the time for development again is dependent on the construction, he adds, “Ideally, for a G+4 construction, we would take between 18 and 20 months for completion, while for a high-rise of 20+ floors it would be between 24 and 30 months. The component to look at to reduce time would be finishing activities, tiling and painting being the foremost.”NCC has 45 million sq ft of affordable housing projects under development under the EPC mode. “In the past year, we have constructed at the speed of almost 125 flats per day,” says PNVS Murthy, Vice-President (Tech), NCC. “With one set of aluminium formwork, we can complete one floor (on an average, two flats a day with one set of aluminium formwork).” Brick Eagle, a company that runs an incubator to support entrepreneurs (developers or service providers) operating in the affordable housing sector, currently has 500 acre under management, at various stages of development. When asked about the time and cost to build, Rajesh Krishnan, Founder & CEO, Brick Eagle, responds, “It is a function of the product specification. G+2 structures can be done quite quickly, at even Rs 1,000 a sq ft; G+22 would be about Rs 2,000 per sq ft.”- SERAPHINA D’SOUZA

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement