Current Time taken for Building Affordable Homes
Real Estate

Current Time taken for Building Affordable Homes

“Currently, we are developing 6-7 lakh sq ft in 18 months at one location or project at competitive costs of development (which includes construction of buildings with all the infrastructure – beginning with the road, boundary wall, STP, UGT, landscape and hardscape, as well as all electrical and plumbing works),” shares Amit Pal, Vice President-Operations, Mahindra Happinest. At its Happinest Avadi project in Chennai, the company has completed and handed over 4.35 lakh sq ft of the total 7.35 lakh sq ft in about 18 months. “If, in future, we are required to complete 1 million sq ft in 18 months, we are geared up for it,” he adds. “We have a 1-million-sq-ft project coming up in Kalyan, which we are aiming to complete in 24 months.”

VBHC Value Homes currently has close to 0.5 million sq ft under construction across various projects. The cost of development per sq ft would clearly vary depending on the type of construction and location, says Rahul Sabharwal, CEO, VBHC Value Homes. While the time for development again is dependent on the construction, he adds, “Ideally, for a G+4 construction, we would take between 18 and 20 months for completion, while for a high-rise of 20+ floors it would be between 24 and 30 months. The component to look at to reduce time would be finishing activities, tiling and painting being the foremost.”

NCC has 45 million sq ft of affordable housing projects under development under the EPC mode. “In the past year, we have constructed at the speed of almost 125 flats per day,” says PNVS Murthy, Vice-President (Tech), NCC. “With one set of aluminium formwork, we can complete one floor (on an average, two flats a day with one set of aluminium formwork).” 

Brick Eagle, a company that runs an incubator to support entrepreneurs (developers or service providers) operating in the affordable housing sector, currently has 500 acre under management, at various stages of development. When asked about the time and cost to build, Rajesh Krishnan, Founder & CEO, Brick Eagle, responds, “It is a function of the product specification. G+2 structures can be done quite quickly, at even Rs 1,000 a sq ft; G+22 would be about Rs 2,000 per sq ft.”

- SERAPHINA D’SOUZA

“Currently, we are developing 6-7 lakh sq ft in 18 months at one location or project at competitive costs of development (which includes construction of buildings with all the infrastructure – beginning with the road, boundary wall, STP, UGT, landscape and hardscape, as well as all electrical and plumbing works),” shares Amit Pal, Vice President-Operations, Mahindra Happinest. At its Happinest Avadi project in Chennai, the company has completed and handed over 4.35 lakh sq ft of the total 7.35 lakh sq ft in about 18 months. “If, in future, we are required to complete 1 million sq ft in 18 months, we are geared up for it,” he adds. “We have a 1-million-sq-ft project coming up in Kalyan, which we are aiming to complete in 24 months.”VBHC Value Homes currently has close to 0.5 million sq ft under construction across various projects. The cost of development per sq ft would clearly vary depending on the type of construction and location, says Rahul Sabharwal, CEO, VBHC Value Homes. While the time for development again is dependent on the construction, he adds, “Ideally, for a G+4 construction, we would take between 18 and 20 months for completion, while for a high-rise of 20+ floors it would be between 24 and 30 months. The component to look at to reduce time would be finishing activities, tiling and painting being the foremost.”NCC has 45 million sq ft of affordable housing projects under development under the EPC mode. “In the past year, we have constructed at the speed of almost 125 flats per day,” says PNVS Murthy, Vice-President (Tech), NCC. “With one set of aluminium formwork, we can complete one floor (on an average, two flats a day with one set of aluminium formwork).” Brick Eagle, a company that runs an incubator to support entrepreneurs (developers or service providers) operating in the affordable housing sector, currently has 500 acre under management, at various stages of development. When asked about the time and cost to build, Rajesh Krishnan, Founder & CEO, Brick Eagle, responds, “It is a function of the product specification. G+2 structures can be done quite quickly, at even Rs 1,000 a sq ft; G+22 would be about Rs 2,000 per sq ft.”- SERAPHINA D’SOUZA

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code