NLCIL faces scrutiny over Rs 337.8 million tender hike in Odisha
Real Estate

NLCIL faces scrutiny over Rs 337.8 million tender hike in Odisha

The Neyveli Lignite Corporation of India Limited (NLCIL) has reportedly overridden internal objections to raise the tender value of a major rehabilitation housing project in Jharsuguda, Odisha, by Rs 337.8 million, allegedly in breach of its own contract rules, according to sources.

The cost escalation relates to the construction of 537 houses, along with roads, water supply systems, and community facilities for families displaced by NLCIL’s Talabira Thermal Power Project in Hirma village.

Originally, NLCIL awarded the contract to RSB Projects in December 2022 for Rs 1.38 billion, with a completion deadline of 12 July 2024. However, on 24 April 2025, the General Manager (Civil) of NLCIL issued a letter approving a 24.48 per cent increase in the project value, raising it to Rs 1.72 billion, even though significant portions of the work remained unfinished.

Rate revisions and internal dissent

According to the letter, the escalation covered:

An 18.47 per cent increase for balance works across four housing blocks (A, B, C and K) completed beyond the original deadline.

A 23.47 per cent hike for constructing the remaining 216 houses.

The approval cited clearance from a sub-committee of directors, which had endorsed the rate revisions.

However, internal correspondence reviewed by sources revealed that the Chief General Manager (Civil) at NLCIL’s Central Technical Office had strongly objected to any cost escalation. In an email dated 16 July 2024, addressed to the Executive Director of the Talabira Project, the CGM stated that rate increases were not permissible under the signed contract.

The officer cited three contract clauses that made the quoted rates firm and fixed for the entire duration of the agreement. The same email also referenced an earlier pre-bid meeting where bidders had requested a price variation clause, which NLCIL had expressly declined, confirming that no escalation would be allowed.

Despite these provisions, the tender value was revised upwards by over Rs 330 million, with insiders suggesting that the sub-committee’s approval bypassed standard technical evaluation procedures.

Delays and transparency concerns

The Talabira rehabilitation project, intended to house displaced families, has already faced multiple delays, and the latest cost escalation has raised concerns about procedural integrity and internal accountability within the public sector enterprise.

Industry observers note that such deviations from established contract norms could invite regulatory scrutiny and calls for an internal audit, especially given the project’s public significance and funding.

The Neyveli Lignite Corporation of India Limited (NLCIL) has reportedly overridden internal objections to raise the tender value of a major rehabilitation housing project in Jharsuguda, Odisha, by Rs 337.8 million, allegedly in breach of its own contract rules, according to sources. The cost escalation relates to the construction of 537 houses, along with roads, water supply systems, and community facilities for families displaced by NLCIL’s Talabira Thermal Power Project in Hirma village. Originally, NLCIL awarded the contract to RSB Projects in December 2022 for Rs 1.38 billion, with a completion deadline of 12 July 2024. However, on 24 April 2025, the General Manager (Civil) of NLCIL issued a letter approving a 24.48 per cent increase in the project value, raising it to Rs 1.72 billion, even though significant portions of the work remained unfinished. Rate revisions and internal dissent According to the letter, the escalation covered: An 18.47 per cent increase for balance works across four housing blocks (A, B, C and K) completed beyond the original deadline. A 23.47 per cent hike for constructing the remaining 216 houses. The approval cited clearance from a sub-committee of directors, which had endorsed the rate revisions. However, internal correspondence reviewed by sources revealed that the Chief General Manager (Civil) at NLCIL’s Central Technical Office had strongly objected to any cost escalation. In an email dated 16 July 2024, addressed to the Executive Director of the Talabira Project, the CGM stated that rate increases were not permissible under the signed contract. The officer cited three contract clauses that made the quoted rates firm and fixed for the entire duration of the agreement. The same email also referenced an earlier pre-bid meeting where bidders had requested a price variation clause, which NLCIL had expressly declined, confirming that no escalation would be allowed. Despite these provisions, the tender value was revised upwards by over Rs 330 million, with insiders suggesting that the sub-committee’s approval bypassed standard technical evaluation procedures. Delays and transparency concerns The Talabira rehabilitation project, intended to house displaced families, has already faced multiple delays, and the latest cost escalation has raised concerns about procedural integrity and internal accountability within the public sector enterprise. Industry observers note that such deviations from established contract norms could invite regulatory scrutiny and calls for an internal audit, especially given the project’s public significance and funding.

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement