NLCIL faces scrutiny over Rs 337.8 million tender hike in Odisha
Real Estate

NLCIL faces scrutiny over Rs 337.8 million tender hike in Odisha

The Neyveli Lignite Corporation of India Limited (NLCIL) has reportedly overridden internal objections to raise the tender value of a major rehabilitation housing project in Jharsuguda, Odisha, by Rs 337.8 million, allegedly in breach of its own contract rules, according to sources.

The cost escalation relates to the construction of 537 houses, along with roads, water supply systems, and community facilities for families displaced by NLCIL’s Talabira Thermal Power Project in Hirma village.

Originally, NLCIL awarded the contract to RSB Projects in December 2022 for Rs 1.38 billion, with a completion deadline of 12 July 2024. However, on 24 April 2025, the General Manager (Civil) of NLCIL issued a letter approving a 24.48 per cent increase in the project value, raising it to Rs 1.72 billion, even though significant portions of the work remained unfinished.

Rate revisions and internal dissent

According to the letter, the escalation covered:

An 18.47 per cent increase for balance works across four housing blocks (A, B, C and K) completed beyond the original deadline.

A 23.47 per cent hike for constructing the remaining 216 houses.

The approval cited clearance from a sub-committee of directors, which had endorsed the rate revisions.

However, internal correspondence reviewed by sources revealed that the Chief General Manager (Civil) at NLCIL’s Central Technical Office had strongly objected to any cost escalation. In an email dated 16 July 2024, addressed to the Executive Director of the Talabira Project, the CGM stated that rate increases were not permissible under the signed contract.

The officer cited three contract clauses that made the quoted rates firm and fixed for the entire duration of the agreement. The same email also referenced an earlier pre-bid meeting where bidders had requested a price variation clause, which NLCIL had expressly declined, confirming that no escalation would be allowed.

Despite these provisions, the tender value was revised upwards by over Rs 330 million, with insiders suggesting that the sub-committee’s approval bypassed standard technical evaluation procedures.

Delays and transparency concerns

The Talabira rehabilitation project, intended to house displaced families, has already faced multiple delays, and the latest cost escalation has raised concerns about procedural integrity and internal accountability within the public sector enterprise.

Industry observers note that such deviations from established contract norms could invite regulatory scrutiny and calls for an internal audit, especially given the project’s public significance and funding.

The Neyveli Lignite Corporation of India Limited (NLCIL) has reportedly overridden internal objections to raise the tender value of a major rehabilitation housing project in Jharsuguda, Odisha, by Rs 337.8 million, allegedly in breach of its own contract rules, according to sources. The cost escalation relates to the construction of 537 houses, along with roads, water supply systems, and community facilities for families displaced by NLCIL’s Talabira Thermal Power Project in Hirma village. Originally, NLCIL awarded the contract to RSB Projects in December 2022 for Rs 1.38 billion, with a completion deadline of 12 July 2024. However, on 24 April 2025, the General Manager (Civil) of NLCIL issued a letter approving a 24.48 per cent increase in the project value, raising it to Rs 1.72 billion, even though significant portions of the work remained unfinished. Rate revisions and internal dissent According to the letter, the escalation covered: An 18.47 per cent increase for balance works across four housing blocks (A, B, C and K) completed beyond the original deadline. A 23.47 per cent hike for constructing the remaining 216 houses. The approval cited clearance from a sub-committee of directors, which had endorsed the rate revisions. However, internal correspondence reviewed by sources revealed that the Chief General Manager (Civil) at NLCIL’s Central Technical Office had strongly objected to any cost escalation. In an email dated 16 July 2024, addressed to the Executive Director of the Talabira Project, the CGM stated that rate increases were not permissible under the signed contract. The officer cited three contract clauses that made the quoted rates firm and fixed for the entire duration of the agreement. The same email also referenced an earlier pre-bid meeting where bidders had requested a price variation clause, which NLCIL had expressly declined, confirming that no escalation would be allowed. Despite these provisions, the tender value was revised upwards by over Rs 330 million, with insiders suggesting that the sub-committee’s approval bypassed standard technical evaluation procedures. Delays and transparency concerns The Talabira rehabilitation project, intended to house displaced families, has already faced multiple delays, and the latest cost escalation has raised concerns about procedural integrity and internal accountability within the public sector enterprise. Industry observers note that such deviations from established contract norms could invite regulatory scrutiny and calls for an internal audit, especially given the project’s public significance and funding.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement