Fadnavis sets strict deadlines for 10 key infra projects
ECONOMY & POLICY

Fadnavis sets strict deadlines for 10 key infra projects

In a decisive push to fast-track Maharashtra’s major infrastructure works, Chief Minister Devendra Fadnavis has directed authorities to complete 10 key projects within fixed deadlines. Chairing a review meeting at the Sahyadri Guest House, Fadnavis stressed the importance of using advanced technology and efficient planning to ensure timely execution.

Among the metro projects, the Mumbai Metro Line 2B (D.N. Nagar to Mandale, covering 19 stations) has been given a completion target of 31 March 2027, while the Swami Samarth Nagar–Vikhroli Line must be finished by 31 December 2026. The Pune Metro Line 3 (Maan–Hinjewadi–Shivajinagar corridor), being developed by the Pune Metropolitan Region Development Authority (PMRDA), is expected to be ready by 31 March 2026.

The Chief Minister also reviewed the BDD Chawl redevelopment projects, directing that the Naigaon site be completed by June 2029, Worli by May 2029, and N.M. Joshi Marg by June 2031, calling them critical to Mumbai’s urban renewal.

Other major projects under review include the Shivdi–Worli connector, Thane–Borivali twin tunnel, Uttan–Vasai Sea Link, and the Orange Gate–Marine Drive urban tunnel, all of which will operate on 24-hour work schedules to meet deadlines.

The Airoli–Katai Naka Freeway is expected to cut travel time by about 20 minutes, while the Vadpe–Thane Road (23.8 km), a crucial link to the Samruddhi Mahamarg, is slated for completion by March 2026.

Expressing concern over the delays in the Bandra–Versova Sea Link, Fadnavis instructed contractors to deploy advanced construction technologies to speed up progress. Meanwhile, the Versova–Dahisar–Bhayandar Coastal Road has been targeted for completion by 30 December 2028, following recent central approval for coastal land use.

In a decisive push to fast-track Maharashtra’s major infrastructure works, Chief Minister Devendra Fadnavis has directed authorities to complete 10 key projects within fixed deadlines. Chairing a review meeting at the Sahyadri Guest House, Fadnavis stressed the importance of using advanced technology and efficient planning to ensure timely execution. Among the metro projects, the Mumbai Metro Line 2B (D.N. Nagar to Mandale, covering 19 stations) has been given a completion target of 31 March 2027, while the Swami Samarth Nagar–Vikhroli Line must be finished by 31 December 2026. The Pune Metro Line 3 (Maan–Hinjewadi–Shivajinagar corridor), being developed by the Pune Metropolitan Region Development Authority (PMRDA), is expected to be ready by 31 March 2026. The Chief Minister also reviewed the BDD Chawl redevelopment projects, directing that the Naigaon site be completed by June 2029, Worli by May 2029, and N.M. Joshi Marg by June 2031, calling them critical to Mumbai’s urban renewal. Other major projects under review include the Shivdi–Worli connector, Thane–Borivali twin tunnel, Uttan–Vasai Sea Link, and the Orange Gate–Marine Drive urban tunnel, all of which will operate on 24-hour work schedules to meet deadlines. The Airoli–Katai Naka Freeway is expected to cut travel time by about 20 minutes, while the Vadpe–Thane Road (23.8 km), a crucial link to the Samruddhi Mahamarg, is slated for completion by March 2026. Expressing concern over the delays in the Bandra–Versova Sea Link, Fadnavis instructed contractors to deploy advanced construction technologies to speed up progress. Meanwhile, the Versova–Dahisar–Bhayandar Coastal Road has been targeted for completion by 30 December 2028, following recent central approval for coastal land use.

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement