RERA Orders Builder to Refund Buyers for Project Delay in Telangana
Real Estate

RERA Orders Builder to Refund Buyers for Project Delay in Telangana

The Telangana Real Estate Regulatory Authority (TGRERA) has ordered R Homes Realtors Global LLP to refund six buyers for delays in completing a residential project at Beeramguda. The buyers had booked flats in Jai Vasavi’s ORR Heights in 2021, paying over Rs eight million.

The builder promised construction would start by January 2022 and flats would be handed over within thirty months of approvals. However, even after more than two years, only initial digging work was done. The builder changed building plans from five floors to nine without informing buyers or obtaining consent.

RERA found that the builder collected money and signed agreements before registering the project or obtaining approvals from the Hyderabad Metropolitan Development Authority, violating Section three of the Real Estate (Regulation and Development) Act. Despite repeated notices, the builder did not respond.

RERA ruled that buyers can cancel bookings and receive a refund but are not eligible for interest as final approval was granted in September 2022, and the builder has time until September 2025 to complete the project. The builder was also directed to pay a penalty of Rs 60,600 thousands to the RERA fund within thirty days and refund buyers within ninety days.

Source:Deccan Chronicle

The Telangana Real Estate Regulatory Authority (TGRERA) has ordered R Homes Realtors Global LLP to refund six buyers for delays in completing a residential project at Beeramguda. The buyers had booked flats in Jai Vasavi’s ORR Heights in 2021, paying over Rs eight million.The builder promised construction would start by January 2022 and flats would be handed over within thirty months of approvals. However, even after more than two years, only initial digging work was done. The builder changed building plans from five floors to nine without informing buyers or obtaining consent.RERA found that the builder collected money and signed agreements before registering the project or obtaining approvals from the Hyderabad Metropolitan Development Authority, violating Section three of the Real Estate (Regulation and Development) Act. Despite repeated notices, the builder did not respond.RERA ruled that buyers can cancel bookings and receive a refund but are not eligible for interest as final approval was granted in September 2022, and the builder has time until September 2025 to complete the project. The builder was also directed to pay a penalty of Rs 60,600 thousands to the RERA fund within thirty days and refund buyers within ninety days.Source:Deccan Chronicle

Next Story
Infrastructure Urban

Concord Control Systems Limited Reports ~85% YoY Growth in H1 FY26

Concord Control Systems Limited (BSE: CNCRD | 543619), India’s leading manufacturer of embedded electronic systems and critical electronic solutions, announced its unaudited financial results for the half year ended September 30, 2025.Financial Highlights – H1 FY26 (YoY Comparison)Revenue from Operations rose to ₹815.45 million, up from ₹497.53 million in H1 FY25, marking a 63.90% year-on-year growth.EBITDA increased to ₹217.34 million, compared to ₹142 million in the same period last year.EBITDA Margin stood at 26.65%, compared to 28.54% in H1 FY25, with the decline attributed to ..

Next Story
Infrastructure Urban

Gateway Distriparks Announces Q2 FY25 Results

Gateway Distriparks Limited (GDL), one of India’s leading multimodal logistics providers, announced its financial results for the quarter ended 30 September 2025.For Q2, the company reported total revenue of INR 154.8 crore (H1: INR 316.9 crore), EBITDA of INR 20.56 crore (H1: INR 45.65 crore), PBT of INR –4.23 crore (H1: INR –0.28 crore), and PAT of INR –2.91 crore (H1: INR –0.37 crore). The company stated that these numbers reflect the consolidation of accounts following Snowman Logistics transitioning from an associate company to a subsidiary in December 2024.Commenting on the per..

Next Story
Infrastructure Transport

Last-Mile Connectivity a Prime Focus, Says Ms. Ashwini Bhide,

The IMC Chamber of Commerce and Industry (IMC) hosted a high-impact Managing Committee session today on the theme “Mumbai Metro: Transforming Connectivity and Commuting.” The session featured an insightful address by Ms. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation Ltd. (MMRCL), who shared updates on key transport infrastructure developments across Mumbai and the MMR region.Emphasising the city’s critical economic role, Ms. Bhide noted, “Mumbai is the economic powerhouse of Maharashtra, with more than 95% of the region’s population living in urban areas. As Maharas..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement