Supertech opposes NBCC’s takeover plan to complete 14,000 flats
Real Estate

Supertech opposes NBCC’s takeover plan to complete 14,000 flats

Supertech raised concerns regarding a proposal submitted by National Buildings Construction Corporation Ltd (NBCC) to finalise the construction of 14,000 flats across 17 projects, arguing that the state-backed firm’s approach would prolong the process, leaving homebuyers waiting indefinitely. The developer also criticised NBCC’s cost projections, claiming they were nearly double those of Supertech. They suggested that completing one project at a time, as done with Doon Square, would be more beneficial for stakeholders.

NBCC became involved in Supertech’s projects in May after a group of homebuyers petitioned the National Company Law Appellate Tribunal (NCLAT), seeking a resolution to their delayed flats. Following this, the tribunal directed the interim resolution professional (IRP) to consider NBCC's involvement in completing the flats, similar to their involvement with Amrapali. NBCC agreed and proposed a plan to complete 17 projects within three years. On 19th September, the tribunal requested stakeholders, including homebuyers and lenders, to provide feedback on NBCC's proposal before the next hearing on 21st October. On Sunday, Supertech’s managing director, RK Arora, publicly opposed the plan.

Arora reportedly stated that NBCC’s approach would extend the project timelines by at least six months, noting that despite reputable firms like AECOM, EY, and CBRE already conducting due diligence, NBCC had opted to carry out its own. He criticised NBCC’s plan for lacking specific timelines and a clear repayment scheme, asserting that it left the state-backed company unaccountable to homebuyers, banks, or land authorities. According to Arora, NBCC’s process mirrored that of Amrapali, which had failed, resulting in delivery delays and conflicts over possession and maintenance. Furthermore, Arora dismissed NBCC’s claims of technical issues stalling the projects, attributing delays solely to funding shortages. He highlighted Supertech's successful track record of delivering over 80,000 flats without complaints about construction quality and questioned the disparity between NBCC’s cost estimate and that of Supertech.

Supertech raised concerns regarding a proposal submitted by National Buildings Construction Corporation Ltd (NBCC) to finalise the construction of 14,000 flats across 17 projects, arguing that the state-backed firm’s approach would prolong the process, leaving homebuyers waiting indefinitely. The developer also criticised NBCC’s cost projections, claiming they were nearly double those of Supertech. They suggested that completing one project at a time, as done with Doon Square, would be more beneficial for stakeholders. NBCC became involved in Supertech’s projects in May after a group of homebuyers petitioned the National Company Law Appellate Tribunal (NCLAT), seeking a resolution to their delayed flats. Following this, the tribunal directed the interim resolution professional (IRP) to consider NBCC's involvement in completing the flats, similar to their involvement with Amrapali. NBCC agreed and proposed a plan to complete 17 projects within three years. On 19th September, the tribunal requested stakeholders, including homebuyers and lenders, to provide feedback on NBCC's proposal before the next hearing on 21st October. On Sunday, Supertech’s managing director, RK Arora, publicly opposed the plan. Arora reportedly stated that NBCC’s approach would extend the project timelines by at least six months, noting that despite reputable firms like AECOM, EY, and CBRE already conducting due diligence, NBCC had opted to carry out its own. He criticised NBCC’s plan for lacking specific timelines and a clear repayment scheme, asserting that it left the state-backed company unaccountable to homebuyers, banks, or land authorities. According to Arora, NBCC’s process mirrored that of Amrapali, which had failed, resulting in delivery delays and conflicts over possession and maintenance. Furthermore, Arora dismissed NBCC’s claims of technical issues stalling the projects, attributing delays solely to funding shortages. He highlighted Supertech's successful track record of delivering over 80,000 flats without complaints about construction quality and questioned the disparity between NBCC’s cost estimate and that of Supertech.

Next Story
Infrastructure Energy

Arunachal’s Hydro Corp Earns Carbon Credits Milestone

The Hydro Power Development Corporation of Arunachal Pradesh (HPDCAPL) has received verified carbon credits for its 3 MW Zemithang hydro project in Tawang, making it the Northeast’s first in the voluntary carbon market.The Universal Carbon Registry issued credits for FY 2022–23, with the project having generated 16,326 tonne so far and targeting 97,783 tonne by 2028.The plant uses 1.5 MW pelton turbines and remains HPDCAPL’s only commissioned project. The initiative supports India’s net-zero goal by 2070.CMD Toko Onuj is steering HPDCAPL towards becoming a green energy and carbon tradi..

Next Story
Infrastructure Energy

Chandigarh Power Infra to Be Upgraded

Chandigarh Power Distribution Limited (CPDL) has announced plans to invest Rs 9.56 billion over five years to modernise the city’s ageing electricity network.Over 50 per cent of existing infrastructure is outdated, leading to frequent breakdowns. CPDL proposes tariff revisions to fund upgrades including new transformers, underground cabling, smart meters, and customer care centres.The Capital Expenditure (CAPEX) plan has been submitted to the Joint Electricity Regulatory Commission for approval.To improve communication, CPDL has also launched a KYC update drive for consumers. ..

Next Story
Infrastructure Energy

Jayakwadi Hydro Plant Shut Since Dec 2023 for Repairs

The 12 MW hydroelectric plant at Jayakwadi dam, Chhatrapati Sambhajinagar, has been offline since December 2023 due to turbine vibration issues.Officials say continued use could damage machinery. Three firms have submitted maintenance bids, which are under review by MAHAGENCO.The plant’s fast response—ready in 5 minutes—and low cost (50.56 paisa per unit) make it valuable for peak demand. Water used in the process is also pumped back into the reservoir...

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?