Suraksha to Complete 20,000 Unfinished Jaypee Infratech Homes
Real Estate

Suraksha to Complete 20,000 Unfinished Jaypee Infratech Homes

Suraksha Group has committed Rs 55 Bn to complete around 20,000 stalled homes under Jaypee Infratech, with full delivery targeted by 2027. The group has secured a Rs 30 Bn credit line and infused Rs 1.25 Bn in equity to resolve the long-standing homebuyer crisis.

Construction is underway across 159 residential towers. Occupancy certificates have been issued for 22 towers, applications filed for 12 more, and an additional 18 expected by early June. Jaypee Infratech aims to deliver 62 towers by the end of 2025, while the remaining 97 will be handed over within the next 40 months.

Despite prior delays caused by GRAP orders, most construction work has been awarded to former contractors of Jaypee Associates Limited. Real Estate Regulatory Authority (RERA) approvals are in place for most sites, and the sale of 1,100 unsold units is expected to begin shortly.

The National Company Law Appellate Tribunal approved Suraksha’s resolution plan in 2024. Under the agreement, Suraksha is required to pay Rs 13.35 Bn to the Yamuna Expressway Industrial Development Authority over four years.

Suraksha Group has committed Rs 55 Bn to complete around 20,000 stalled homes under Jaypee Infratech, with full delivery targeted by 2027. The group has secured a Rs 30 Bn credit line and infused Rs 1.25 Bn in equity to resolve the long-standing homebuyer crisis.Construction is underway across 159 residential towers. Occupancy certificates have been issued for 22 towers, applications filed for 12 more, and an additional 18 expected by early June. Jaypee Infratech aims to deliver 62 towers by the end of 2025, while the remaining 97 will be handed over within the next 40 months.Despite prior delays caused by GRAP orders, most construction work has been awarded to former contractors of Jaypee Associates Limited. Real Estate Regulatory Authority (RERA) approvals are in place for most sites, and the sale of 1,100 unsold units is expected to begin shortly.The National Company Law Appellate Tribunal approved Suraksha’s resolution plan in 2024. Under the agreement, Suraksha is required to pay Rs 13.35 Bn to the Yamuna Expressway Industrial Development Authority over four years.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App