Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement