Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Building Material

Birla Corporation Plans Cement Expansion and Strategic Diversification

Birla Corporation Limited, the flagship firm of the M P Birla Group, plans to consolidate its cement operations while pursuing meaningful diversification. Speaking at the company’s AGM, Chairman Harsh V Lodha highlighted that Birla Corporation is a key player in central India’s cement sector, with a current production capacity of 20 million tonnes.The company aims to raise capacity to 27.6 million tonnes by 2028–29 through new grinding units and clinkerisation, with an estimated capital expenditure of Rs 43.35 billion. Lodha added that coal block allocations are progressing through vario..

Next Story
Building Material

Ultratech Cement Expands Cuttack Plant with Rs 3.72 Billion Investment

 Odisha Chief Minister Mohan Charan Majhi virtually inaugurated Ultratech Cement’s Rs 3.72 billion expansion project on Monday from Bhubaneswar. The ceremony, held at the state level in Bhubaneswar, saw the participation of Minister of Industries Sampad Chandra Swain, Chief Secretary Manoj Ahuja, Development Commissioner Anu Garg, and Additional Chief Secretary Industries Hemant Sharma.Aditya Birla Group head for Odisha, Ardhendu Mohapatra, and Ultratech Cement Cuttack Plant Head Abhinash Rath were also present. At the project site in Khamar Nuagaon and Kolathpangi villages, Athagarh te..

Next Story
Infrastructure Urban

Muthoot Finance Raises $600 Million via Global Bond Issue

Muthoot Finance has raised $600 million through an External Commercial Borrowing (ECB) issuance in the international bond markets, marking the fifth and final drawdown under its Global Medium-Term Note (GMTN) programme since May 2024 and completing the company’s $2 billion target.The bonds, rated BB+ by S&P and Ba1 by Moody’s, were priced at 6.37 per cent, with a 4.5-year maturity and an average life of four years. This represents Muthoot Finance’s first bond issuance since receiving credit rating upgrades from S&P in March 2025 and Moody’s in April 2025.Proceeds from the issua..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?