Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Infrastructure Urban

Shivraj Singh Chouhan inaugurates ICAR-IIMR admin block in Ludhiana

Union Agriculture Minister Shri Shivraj Singh Chouhan recently inaugurated the administrative building at the Indian Council of Agricultural Research – Indian Institute of Maize Research (ICAR-IIMR) in Ludhiana, Punjab. During the visit, he interacted with maize stakeholders, farmers, rural development scheme beneficiaries, and women self-help group (SHG) members. He said that under the leadership of Prime Minister Narendra Modi, the government’s key goals include boosting foodgrain production, reducing input costs, and improving farmers’ incomes. He highlighted the importance of div..

Next Story
Technology

Google to Build Rs 10,000 Cr Data Centre in Visakhapatnam

In a major boost to India’s digital infrastructure, Google will establish a 1-GW hyperscale data centre and Artificial Intelligence (AI) hub in Visakhapatnam, Andhra Pradesh. The project, valued at Rs 100 billion, is expected to significantly contribute to the state’s economy and create more than 20,000 direct and indirect employment opportunities. Union Minister of State for External Affairs and Education, Dr Pemmasani Chandrasekhar, highlighted that this landmark investment by Google will help position Andhra Pradesh as a prominent digital hub under the “Swarandhra Pradesh” vision. ..

Next Story
Infrastructure Urban

TCIL honoured with HR Excellence Award 2025

Telecommunications Consultants India Limited (TCIL), a Miniratna Schedule ‘A’ PSU under the Department of Telecommunications, has been honoured with the HR Excellence Award at the Fortune Leadership Awards 2025, held at Radisson Blu Plaza, Delhi. The accolade acknowledges TCIL’s outstanding HR practices promoting employee development, innovation, and inclusivity. The award was presented by Dr. Dinesh Upadhyay, Former Member, Ministry of AYUSH, and Shri M. S. Nethrapal, IRS, and received by Shri P. Suresh Babu, CGM (HR), in the presence of distinguished leaders from various sectors. Bet..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?