Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement