Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Infrastructure Urban

India Flex Workspace Stock Crosses 100 Mn Sq Ft

India's flexible workspace sector has crossed the 100 million square feet (mn sq ft) milestone and is on course for a ten billion dollar valuation by 2028. The shift reflects a move to profitability-led expansion among operators. Market observers noted growing enterprise mandates and improving financial metrics. Demand has been fuelled by robust enterprise leasing, with Global Capability Centres (GCCs) accounting for nearly 40 per cent of new seats in recent quarters. Average deal sizes have more than doubled, rising from 25 seats in 2023 to 53 seats in 2025. The banking, financial services an..

Next Story
Infrastructure Urban

Bhive Workspace Plans One Million Sq Ft Expansion

Bhive Workspace has announced plans to add one million square feet (mn sq ft) of workspace in 2026 and to invest Rs three billion (bn) to support the expansion. The company stated that the fresh capacity will be targeted at key urban markets where demand for flexible workspace remains strong. The investment is intended to cover leasing, fit outs and technology upgrades for new centres. The expansion follows a period of measured growth and is aligned with the company strategy to increase market coverage. Management indicated that the expansion will enhance the firm portfolio and allow it to sca..

Next Story
Infrastructure Energy

Adani Green Adds Over Five Gigawatt Renewable Capacity In FY26

Adani Green Energy added over five gigawatt (GW) of renewable energy capacity in fiscal year 2026, taking its total operational portfolio to 19.3 GW and marking the highest greenfield annual capacity expansion globally outside China. The new capacity comprised three point four gigawatt of solar, zero point seven gigawatt of wind (686 megawatt (MW)) and one gigawatt of wind-solar hybrid capacity, reflecting a diversified clean energy build-out strategy. The additions underline a focus on scale and diversified site deployment across technologies.\n\nMost of the incremental capacity was commissio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement