Infra projects show huge cost overruns
ECONOMY & POLICY

Infra projects show huge cost overruns

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost.

All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost.

However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430.

The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects.

Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months.

Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support.

The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons.

The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

As per recent reports, 437 infrastructure projects, each worth Rs 1.50 billion or more have been adversely affected due to cost overruns, amounting to over Rs 4.37 trillion. Of 1,663 such projects, 531 projects witnessed time escalation, and 437 projects have reported cost overruns. Cost overrun quantum. The incurred expenditure on the projects stood at Rs 11.62 trillion till September, which was 45.60% of the expected cost. All infrastructure projects worth Rs 1.50 billion and above are monitored by the Ministry of Statistics and Programme Implementation (MoSPI). The Ministry's latest report for September 2020 reported that the original cumulative cost for the 1,663 projects was Rs 21.09 trillion. However, the anticipated cost of completion of the projects is probably going to be Rs 25.47 trillion. The overall cost overruns indicated by this is of Rs 4.37 trillion, which is more than 20 per cent of the initially calculated cost. However, the report said that if the delay is assessed based on the latest schedule of completion, the number of delayed projects reduces to 430. The report also mentioned that neither the tentative gestation period nor the year of commissioning was reported for 924 projects. Time overruns quantum. Of the 531 projects that have been delayed, 121 projects reflect a delay of 61 months and more; 160 projects show a delay of any duration between 25 to 60 months; 128 projects reflect a delay in the range of 13-24 months; while 122 projects show an overall delay from anywhere between 1-12 months. The average time overrun in all the 531 projects is 43.89 months. Several project-implementing agencies reported various reasons for the time overruns. The reasons varied from delay in acquiring environment and forest clearances, a delay in acquisition of land or even a lack of linkages and infrastructural support. The report mentioned tendering delays, delay in ordering and supplying of equipment, delay in finalisation of detailed engineering, delays in project financing tie-ups and issues with law and order as some of the other reasons. The report also stated that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported.

Next Story
Resources

IGBC Launches 32nd Chapter in Ranchi to Drive Green Building Growth

The CII Indian Green Building Council (IGBC) has launched its 32nd Chapter in Ranchi to accelerate Jharkhand’s transition towards sustainable and resilient urban infrastructure. The launch event, held on September 6 at Radisson Blu Hotel, brought together government officials, industry leaders, and sustainability experts. Sunil Kumar, IAS, Principal Secretary, Urban Development & Housing Department, Government of Jharkhand, said, “The launch of the IGBC Ranchi Chapter marks a significant step in Jharkhand’s urban development journey. The state is committed to creating a policy e..

Next Story
Real Estate

Mindspace REIT Marks Five Years With 14.8 Per Cent Annualised Returns

Mindspace Business Parks REIT, owner and developer of a Grade-A office portfolio, has completed five years since its listing on the Indian bourses in August 2020. Despite debuting during the global pandemic, the REIT has delivered 14.8 per cent annualised total returns, expanded its portfolio, and reinforced occupier trust. Key achievements over five years include: Portfolio expansion of 30 per cent to 31.0 msf through acquisitions and new developments. Gross leasing of 25.2 msf, with occupancy sustained at 93.7 per cent. Cumulative distribution of Rs 55.9 billion to unitho..

Next Story
Real Estate

Great Value Realty Secures RERA Nod for Ultra-Luxury Ekanam Project

Great Value Realty, one of North India’s most trusted developers, has received RERA approval for its flagship ultra-luxury residential project, Ekanam (RERA No. UPRERAPRJ15109/2019). The announcement was made during the Great Partners Meet at Noida. Built on the only available land parcel in Sector 107, Noida, Ekanam embodies the company’s philosophy, “Great is the New Norm,” promising excellence in design, quality, and sustainable community living. With seamless connectivity to Noida Expressway, DND Flyway, metro stations, and proximity to the upcoming Jewar Airport, the project ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?