379 Infrastructure Projects Hit by Cost Overruns
ECONOMY & POLICY

379 Infrastructure Projects Hit by Cost Overruns

An official analysis stated that as many as 379 infrastructure projects, each requiring an expenditure of at least Rs 1.5 billion, have been affected by cost overruns of more than Rs 4.64 lakh crore as of April 2023.

Out of 1,605 projects, 379 reported cost overruns and up to 800 projects were delayed, according to the Ministry of Statistics and Programme Implementation, which oversees infrastructure projects worth Rs 1.5 billion and above.

"Total original cost of implementation of the 1,605 projects was Rs 22,85,674.25 crore and their anticipated completion cost is likely to be Rs 27,50,591.38 crore, which reflects overall cost overruns of Rs 4,64,917.13 crore (20.34 per cent of original cost)," the ministry's latest report for April 2023 said.

The study states that the amount spent on these projects up till April 2023 was 51.39 percent of the projects' estimated cost. On the basis of the most recent completion schedule, it was announced that the number of projects with delays drops to 598. Additionally, it noted that neither the tentative gestation length nor the commissioning year for 413 projects had been published.

Out of the 800 projects that have been postponed, 194 have total delays between one and twelve months, 175 have delays between three and four years, 306 have delays between five and sixty years, and 125 have delays of more than sixty years.

Further evidence that time/cost overrun figures are underreported comes from the fact that many project executing agencies fail to publish revised cost estimates and commissioning schedules.

See also:
Project cost for Versova-Bandra Sealink jumps by 60% to Rs 113.33 bn
Mumbai Metro 3 project cost rises by Rs 10,269.82 crore


An official analysis stated that as many as 379 infrastructure projects, each requiring an expenditure of at least Rs 1.5 billion, have been affected by cost overruns of more than Rs 4.64 lakh crore as of April 2023. Out of 1,605 projects, 379 reported cost overruns and up to 800 projects were delayed, according to the Ministry of Statistics and Programme Implementation, which oversees infrastructure projects worth Rs 1.5 billion and above. Total original cost of implementation of the 1,605 projects was Rs 22,85,674.25 crore and their anticipated completion cost is likely to be Rs 27,50,591.38 crore, which reflects overall cost overruns of Rs 4,64,917.13 crore (20.34 per cent of original cost), the ministry's latest report for April 2023 said. The study states that the amount spent on these projects up till April 2023 was 51.39 percent of the projects' estimated cost. On the basis of the most recent completion schedule, it was announced that the number of projects with delays drops to 598. Additionally, it noted that neither the tentative gestation length nor the commissioning year for 413 projects had been published. Out of the 800 projects that have been postponed, 194 have total delays between one and twelve months, 175 have delays between three and four years, 306 have delays between five and sixty years, and 125 have delays of more than sixty years. Further evidence that time/cost overrun figures are underreported comes from the fact that many project executing agencies fail to publish revised cost estimates and commissioning schedules. See also: Project cost for Versova-Bandra Sealink jumps by 60% to Rs 113.33 bnMumbai Metro 3 project cost rises by Rs 10,269.82 crore

Next Story
Infrastructure Transport

Lack of Bidders Stalls VOC Port’s Rs 70.56 Bn Harbour Project Again

The VOC Port Authority’s Rs 70.56 billion outer harbour project has once again faced a setback, with the latest tender process cancelled due to the absence of qualified bidders. This marks the second failed attempt to secure participation for the mega infrastructure initiative.The tender has reportedly been withdrawn from the active list of bids, and the authority is now expected to re-evaluate and possibly restructure the project to enhance its appeal to potential developers.The port authority had initially floated the Request for Proposal (RFP) in December 2024, following the cancellation ..

Next Story
Infrastructure Transport

Sea Lord Containers Opens Cryogenic LPG Terminal in Mangalore

Sea Lord Containers (SCL), a wholly-owned subsidiary of Aegis Logistics, has commissioned a new cryogenic Liquified Petroleum Gas (LPG) terminal in Mangalore. The facility, which became operational on 12 June 2025, offers a static storage capacity of 82,000 metric tons (MT), significantly strengthening the region’s LPG logistics infrastructure.The terminal was developed by SCL on behalf of Aegis Vopak Terminals, an associate company of Aegis Logistics. The asset is expected to be transferred to Aegis Vopak Terminals Limited at a later date, with formal updates to be shared separately with st..

Next Story
Infrastructure Urban

Cochin Port and Oil India Partner for Offshore Exploration Support

The Cochin Port Authority (CoPA) has signed a Memorandum of Understanding (MoU) with Oil India (OIL) to establish a shore base facility supporting offshore oil exploration in the Kerala-Konkan Basin. The agreement was formalised at a ceremony held at CoPA, Willingdon Island, on 12 June 2025, in the presence of senior officials from both organisations.Under the partnership, Cochin Port will provide critical logistics infrastructure for OIL’s offshore drilling operations, expected to begin later in 2025. The planned shore base will include a dedicated warehouse, dry bulk handling plant, and an..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?