379 Infrastructure Projects Hit by Cost Overruns
ECONOMY & POLICY

379 Infrastructure Projects Hit by Cost Overruns

An official analysis stated that as many as 379 infrastructure projects, each requiring an expenditure of at least Rs 1.5 billion, have been affected by cost overruns of more than Rs 4.64 lakh crore as of April 2023.

Out of 1,605 projects, 379 reported cost overruns and up to 800 projects were delayed, according to the Ministry of Statistics and Programme Implementation, which oversees infrastructure projects worth Rs 1.5 billion and above.

"Total original cost of implementation of the 1,605 projects was Rs 22,85,674.25 crore and their anticipated completion cost is likely to be Rs 27,50,591.38 crore, which reflects overall cost overruns of Rs 4,64,917.13 crore (20.34 per cent of original cost)," the ministry's latest report for April 2023 said.

The study states that the amount spent on these projects up till April 2023 was 51.39 percent of the projects' estimated cost. On the basis of the most recent completion schedule, it was announced that the number of projects with delays drops to 598. Additionally, it noted that neither the tentative gestation length nor the commissioning year for 413 projects had been published.

Out of the 800 projects that have been postponed, 194 have total delays between one and twelve months, 175 have delays between three and four years, 306 have delays between five and sixty years, and 125 have delays of more than sixty years.

Further evidence that time/cost overrun figures are underreported comes from the fact that many project executing agencies fail to publish revised cost estimates and commissioning schedules.

See also:
Project cost for Versova-Bandra Sealink jumps by 60% to Rs 113.33 bn
Mumbai Metro 3 project cost rises by Rs 10,269.82 crore


An official analysis stated that as many as 379 infrastructure projects, each requiring an expenditure of at least Rs 1.5 billion, have been affected by cost overruns of more than Rs 4.64 lakh crore as of April 2023. Out of 1,605 projects, 379 reported cost overruns and up to 800 projects were delayed, according to the Ministry of Statistics and Programme Implementation, which oversees infrastructure projects worth Rs 1.5 billion and above. Total original cost of implementation of the 1,605 projects was Rs 22,85,674.25 crore and their anticipated completion cost is likely to be Rs 27,50,591.38 crore, which reflects overall cost overruns of Rs 4,64,917.13 crore (20.34 per cent of original cost), the ministry's latest report for April 2023 said. The study states that the amount spent on these projects up till April 2023 was 51.39 percent of the projects' estimated cost. On the basis of the most recent completion schedule, it was announced that the number of projects with delays drops to 598. Additionally, it noted that neither the tentative gestation length nor the commissioning year for 413 projects had been published. Out of the 800 projects that have been postponed, 194 have total delays between one and twelve months, 175 have delays between three and four years, 306 have delays between five and sixty years, and 125 have delays of more than sixty years. Further evidence that time/cost overrun figures are underreported comes from the fact that many project executing agencies fail to publish revised cost estimates and commissioning schedules. See also: Project cost for Versova-Bandra Sealink jumps by 60% to Rs 113.33 bnMumbai Metro 3 project cost rises by Rs 10,269.82 crore

Next Story
Equipment

Schwing Stetter India Unveils New Innovations at Excon 2025

Schwing Stetter India unveiled more than 20 new machines at Excon 2025, marking one of its most significant showcases and introducing several India-first technologies to the construction equipment sector. The company launched the country’s first 56-metre boom pump designed and manufactured in India, the first fully electric truck mixer, the first CNG mixer variant and the first hybrid boom pump. Executives said the launch portfolio was engineered to support India’s move toward faster, greener and more vertically oriented infrastructure through advanced engineering, clean-energy solutions a..

Next Story
Infrastructure Energy

SEPC Resolves Hindustan Copper Dispute, Wins Rs 725 Mn Order

Engineering, procurement and construction firm SEPC Ltd has recently settled a dispute with Hindustan Copper Ltd (HCL) and secured a mining infrastructure order valued at Rs 725 million from the state-owned company. SEPC informed the stock exchanges that it has executed a settlement deed with HCL, bringing closure to all inter-se claims and counterclaims arising from arbitration proceedings. As part of the settlement, SEPC will receive Rs 304.5 million as full and final payment, marking the resolution of all pending disputes between the two entities. The company also stated that Hindustan Co..

Next Story
Infrastructure Energy

20% Ethanol Blending Cuts India’s CO2 Emissions by 73.6 Mn Tonnes

Union Road Transport and Highways Minister Nitin Gadkari recently said that India has reduced carbon dioxide emissions by 73.6 million metric tonnes due to the adoption of 20 per cent ethanol blending in petrol. He made the statement while replying to supplementary questions during the Question Hour in the Lok Sabha. Describing ethanol as a green fuel, the minister said it plays a key role in reducing pollution while also supporting higher incomes for farmers. He underlined that ethanol blending contributes both to environmental sustainability and rural economic growth. Nitin Gadkari also po..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App