379 Infrastructure Projects Hit by Cost Overruns
ECONOMY & POLICY

379 Infrastructure Projects Hit by Cost Overruns

An official analysis stated that as many as 379 infrastructure projects, each requiring an expenditure of at least Rs 1.5 billion, have been affected by cost overruns of more than Rs 4.64 lakh crore as of April 2023.

Out of 1,605 projects, 379 reported cost overruns and up to 800 projects were delayed, according to the Ministry of Statistics and Programme Implementation, which oversees infrastructure projects worth Rs 1.5 billion and above.

"Total original cost of implementation of the 1,605 projects was Rs 22,85,674.25 crore and their anticipated completion cost is likely to be Rs 27,50,591.38 crore, which reflects overall cost overruns of Rs 4,64,917.13 crore (20.34 per cent of original cost)," the ministry's latest report for April 2023 said.

The study states that the amount spent on these projects up till April 2023 was 51.39 percent of the projects' estimated cost. On the basis of the most recent completion schedule, it was announced that the number of projects with delays drops to 598. Additionally, it noted that neither the tentative gestation length nor the commissioning year for 413 projects had been published.

Out of the 800 projects that have been postponed, 194 have total delays between one and twelve months, 175 have delays between three and four years, 306 have delays between five and sixty years, and 125 have delays of more than sixty years.

Further evidence that time/cost overrun figures are underreported comes from the fact that many project executing agencies fail to publish revised cost estimates and commissioning schedules.

See also:
Project cost for Versova-Bandra Sealink jumps by 60% to Rs 113.33 bn
Mumbai Metro 3 project cost rises by Rs 10,269.82 crore


An official analysis stated that as many as 379 infrastructure projects, each requiring an expenditure of at least Rs 1.5 billion, have been affected by cost overruns of more than Rs 4.64 lakh crore as of April 2023. Out of 1,605 projects, 379 reported cost overruns and up to 800 projects were delayed, according to the Ministry of Statistics and Programme Implementation, which oversees infrastructure projects worth Rs 1.5 billion and above. Total original cost of implementation of the 1,605 projects was Rs 22,85,674.25 crore and their anticipated completion cost is likely to be Rs 27,50,591.38 crore, which reflects overall cost overruns of Rs 4,64,917.13 crore (20.34 per cent of original cost), the ministry's latest report for April 2023 said. The study states that the amount spent on these projects up till April 2023 was 51.39 percent of the projects' estimated cost. On the basis of the most recent completion schedule, it was announced that the number of projects with delays drops to 598. Additionally, it noted that neither the tentative gestation length nor the commissioning year for 413 projects had been published. Out of the 800 projects that have been postponed, 194 have total delays between one and twelve months, 175 have delays between three and four years, 306 have delays between five and sixty years, and 125 have delays of more than sixty years. Further evidence that time/cost overrun figures are underreported comes from the fact that many project executing agencies fail to publish revised cost estimates and commissioning schedules. See also: Project cost for Versova-Bandra Sealink jumps by 60% to Rs 113.33 bnMumbai Metro 3 project cost rises by Rs 10,269.82 crore

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement