443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report
ECONOMY & POLICY

443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore.

The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above.

As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost.

From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns.

However, the number of delayed projects reduces to 381, based on the latest completion schedule.

Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared.

Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months.

Overall estimated time overrun in these 514 delayed projects is 46.23 months.

Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support.

Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons.

According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay.

It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported.

Image Source

Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore. The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above. As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost. From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns. However, the number of delayed projects reduces to 381, based on the latest completion schedule. Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared. Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months. Overall estimated time overrun in these 514 delayed projects is 46.23 months. Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support. Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons. According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay. It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported. Image Source Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement