443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report
ECONOMY & POLICY

443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore.

The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above.

As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost.

From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns.

However, the number of delayed projects reduces to 381, based on the latest completion schedule.

Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared.

Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months.

Overall estimated time overrun in these 514 delayed projects is 46.23 months.

Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support.

Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons.

According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay.

It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported.

Image Source

Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore. The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above. As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost. From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns. However, the number of delayed projects reduces to 381, based on the latest completion schedule. Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared. Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months. Overall estimated time overrun in these 514 delayed projects is 46.23 months. Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support. Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons. According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay. It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported. Image Source Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

Next Story
Infrastructure Transport

Beyond the Overlay

Every year, as the monsoon retreats, India’s highways hum with activity. Asphalt plants roar back to life, contractors rush to meet deadlines, and the clock starts ticking on another paving season. Yet the same questions persist: why do many Indian roads demand overlays within seven years when global peers last twice as long? And what will it take to make roads endure India’s climate, traffic, and pace of growth?“In developed countries, highways are designed for 25 to 30 years; in India, it’s 15 to 20,” observes Muthu Annamalai, Vice-President – Projects, Vertis Infrastructure Trus..

Next Story
Real Estate

Sonu Sood Inspires Fitness at Signature Global’s DXP WellFest

Signature Global, one of India’s leading real estate developers, hosted another edition of its DXP Wellness Fest at DXP Estate, Sector 37D, Dwarka Expressway, bringing together residents, fitness enthusiasts, and wellness brands for a day dedicated to health, mindfulness, and community living.The highlight of the event was an engaging session with actor and philanthropist Sonu Sood, who inspired participants to embrace fitness, resilience, and collective well-being. The festival also featured energetic performances by Tagra Raho, the fitness brand by M.S. Dhoni, and interactive experiences b..

Next Story
Equipment

BICES 2025 Draws 1,300 Global Exhibitors to Showcase Next-Gen Machinery

The 17th China (Beijing) International Construction Machinery, Building Material Machines and Mining Machines Exhibition (BICES 2025) concluded successfully at the China International Exhibition Center, Shunyi.Held from September 23–26 under the theme “High-end, Green, Smart and Future,” the world-class event brought together nearly 1,300 leading domestic and international enterprises across a sprawling 150,000 sq. m exhibition area. The show attracted over 148,000 professional visitors and users from 73 countries and regions, reinforcing its position as one of the most influential gathe..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement