443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report
ECONOMY & POLICY

443 infra projects hits cost overruns of Rs 4.45 lakh crore: Report

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore.

The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above.

As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost.

From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns.

However, the number of delayed projects reduces to 381, based on the latest completion schedule.

Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared.

Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months.

Overall estimated time overrun in these 514 delayed projects is 46.23 months.

Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support.

Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons.

According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay.

It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported.

Image Source

Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

A government report revealed that 443 infrastructure projects, with the cost of investment of over Rs 150 crore, have been hit by cost overruns totalling over Rs 4.45 lakh crore. The Ministry of Statistics and Programme Implementation (MOSPI) monitors infrastructure projects of Rs 150 crore and above. As per the report, till January 2022, expenditure incurred on these projects stood at Rs 13,16,293.63 crore or 48.76% of the estimated project cost. From 1,671 such projects, 514 projects were delayed, and 443 reported cost overruns. However, the number of delayed projects reduces to 381, based on the latest completion schedule. Moreover, for 881 projects, neither the year of commissioning nor the tentative gestation period has been declared. Out of the 514 delayed projects, 89 have a total delay of one to two months, 113 are delayed for 13-24 months, 204 for 25-60 months, and 108 projects have been delayed for over 61 months. Overall estimated time overrun in these 514 delayed projects is 46.23 months. Various agencies executing these projects notified reasons for time overrun, such as delay in land acquisition, delay in getting environment approvals, and shortage of infrastructure linkages and support. Additional reasons include finalisation detail engineering delay, change in scope, law and order issues, and many other reasons. According to the report, the state-wise lockdown due to the Covid-19 pandemic was one of the reasons for the delay. It also mentioned that project agencies are not reporting revised cost estimates and schedule commissioning for various projects, which shows that time/cost overrun figures are under-reported. Image Source Also read: 445 infra projects hits cost overrun of Rs 4.4 lakh crore

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement