445 infra projects hits cost overrun of Rs 4.4 lakh crore
ECONOMY & POLICY

445 infra projects hits cost overrun of Rs 4.4 lakh crore

According to a report, 445 infrastructure projects with an investment of Rs 150 crore each have been hit by cost overruns of over Rs 4.4 lakh crore.

The Ministry of Statistics and Programme Implementation looks into the infrastructure projects of Rs 150 crore or more. Of 1,673 projects, 445 faced cost overruns, and 557 projects were delayed.

The Ministry said that the initial implementation cost of these projects was Rs 22,23,791.78 crore, and their anticipated cost is likely to be Rs 26,64,649.18 crore, with Rs 4,40,857.40 crore cost overruns.

As per the report, the expenditure incurred on these infrastructure projects is Rs 13,08,766.65 crore, which is 49.12% of the anticipated cost of the projects.

The number of delayed projects dropped to 420 if the delay is counted based on the latest schedule of completion.

As many as 838 projects have not been given the year of commissioning nor the tentative gestation period.

From the 557 delayed projects, 97 projects have an overall delay between 1-12 months, 127 projects have been delayed for 13-24 months, 217 projects for 25-60 months and 116 projects for 61 months or more. The average time overrun in these projects is 45.69 months.

Time overruns were due to the issue of land acquisition, delay in forest and environment clearances, lack of infrastructure support and linkages. Other reasons include project financing, delay in finalising detailed engineering, change in scope, delay in the tendering process, ordering and equipment supply, law and order problems and Covid-19 restrictions and state-wise lockdowns.

Image Source

Also read: China to rollout infra projects to combat economic slowdown

Also read: BRO develops Project Yojak in Himachal Pradesh to boost road infra

According to a report, 445 infrastructure projects with an investment of Rs 150 crore each have been hit by cost overruns of over Rs 4.4 lakh crore. The Ministry of Statistics and Programme Implementation looks into the infrastructure projects of Rs 150 crore or more. Of 1,673 projects, 445 faced cost overruns, and 557 projects were delayed. The Ministry said that the initial implementation cost of these projects was Rs 22,23,791.78 crore, and their anticipated cost is likely to be Rs 26,64,649.18 crore, with Rs 4,40,857.40 crore cost overruns. As per the report, the expenditure incurred on these infrastructure projects is Rs 13,08,766.65 crore, which is 49.12% of the anticipated cost of the projects. The number of delayed projects dropped to 420 if the delay is counted based on the latest schedule of completion. As many as 838 projects have not been given the year of commissioning nor the tentative gestation period. From the 557 delayed projects, 97 projects have an overall delay between 1-12 months, 127 projects have been delayed for 13-24 months, 217 projects for 25-60 months and 116 projects for 61 months or more. The average time overrun in these projects is 45.69 months. Time overruns were due to the issue of land acquisition, delay in forest and environment clearances, lack of infrastructure support and linkages. Other reasons include project financing, delay in finalising detailed engineering, change in scope, delay in the tendering process, ordering and equipment supply, law and order problems and Covid-19 restrictions and state-wise lockdowns. Image Source Also read: China to rollout infra projects to combat economic slowdown Also read: BRO develops Project Yojak in Himachal Pradesh to boost road infra

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement