+
445 infra projects hits cost overrun of Rs 4.4 lakh crore
ECONOMY & POLICY

445 infra projects hits cost overrun of Rs 4.4 lakh crore

According to a report, 445 infrastructure projects with an investment of Rs 150 crore each have been hit by cost overruns of over Rs 4.4 lakh crore.

The Ministry of Statistics and Programme Implementation looks into the infrastructure projects of Rs 150 crore or more. Of 1,673 projects, 445 faced cost overruns, and 557 projects were delayed.

The Ministry said that the initial implementation cost of these projects was Rs 22,23,791.78 crore, and their anticipated cost is likely to be Rs 26,64,649.18 crore, with Rs 4,40,857.40 crore cost overruns.

As per the report, the expenditure incurred on these infrastructure projects is Rs 13,08,766.65 crore, which is 49.12% of the anticipated cost of the projects.

The number of delayed projects dropped to 420 if the delay is counted based on the latest schedule of completion.

As many as 838 projects have not been given the year of commissioning nor the tentative gestation period.

From the 557 delayed projects, 97 projects have an overall delay between 1-12 months, 127 projects have been delayed for 13-24 months, 217 projects for 25-60 months and 116 projects for 61 months or more. The average time overrun in these projects is 45.69 months.

Time overruns were due to the issue of land acquisition, delay in forest and environment clearances, lack of infrastructure support and linkages. Other reasons include project financing, delay in finalising detailed engineering, change in scope, delay in the tendering process, ordering and equipment supply, law and order problems and Covid-19 restrictions and state-wise lockdowns.

Image Source

Also read: China to rollout infra projects to combat economic slowdown

Also read: BRO develops Project Yojak in Himachal Pradesh to boost road infra

According to a report, 445 infrastructure projects with an investment of Rs 150 crore each have been hit by cost overruns of over Rs 4.4 lakh crore. The Ministry of Statistics and Programme Implementation looks into the infrastructure projects of Rs 150 crore or more. Of 1,673 projects, 445 faced cost overruns, and 557 projects were delayed. The Ministry said that the initial implementation cost of these projects was Rs 22,23,791.78 crore, and their anticipated cost is likely to be Rs 26,64,649.18 crore, with Rs 4,40,857.40 crore cost overruns. As per the report, the expenditure incurred on these infrastructure projects is Rs 13,08,766.65 crore, which is 49.12% of the anticipated cost of the projects. The number of delayed projects dropped to 420 if the delay is counted based on the latest schedule of completion. As many as 838 projects have not been given the year of commissioning nor the tentative gestation period. From the 557 delayed projects, 97 projects have an overall delay between 1-12 months, 127 projects have been delayed for 13-24 months, 217 projects for 25-60 months and 116 projects for 61 months or more. The average time overrun in these projects is 45.69 months. Time overruns were due to the issue of land acquisition, delay in forest and environment clearances, lack of infrastructure support and linkages. Other reasons include project financing, delay in finalising detailed engineering, change in scope, delay in the tendering process, ordering and equipment supply, law and order problems and Covid-19 restrictions and state-wise lockdowns. Image Source Also read: China to rollout infra projects to combat economic slowdown Also read: BRO develops Project Yojak in Himachal Pradesh to boost road infra

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement