448 infra projects hit by cost overrun in April
ECONOMY & POLICY

448 infra projects hit by cost overrun in April

According to an official report, 448 infrastructure projects, each with an investment of Rs 1.50 billion or more, experienced a cost overrun exceeding Rs 5.55 trillion as of April 2024. The Ministry of Statistics and Programme Implementation (MoSPI), which oversees infrastructure projects costing Rs 1.50 billion and above, reported that out of 1,838 projects, 448 faced cost overruns and 792 were delayed.

The total original cost of the 1,838 projects was Rs 27.64 trillion, and their anticipated completion cost is estimated to be Rs 33.19 trillion, indicating an overall cost overrun of more than Rs 5.55 trillion, according to MoSPI's latest report for April 2024.

The report also highlighted that the expenditure incurred on these projects up to April 2024 amounted to Rs 16.93 trillion, which is 51 % of the anticipated cost. However, the number of delayed projects decreased to 514 when the delay was calculated based on the latest completion schedule.

Of the 792 delayed projects, 220 experienced delays ranging from 1 to 12 months, 192 were delayed by 13 to 24 months, 259 by 25 to 60 months, and 121 by more than 60 months. The average time overrun for these 792 delayed projects is 35.4 months.

The report cited various reasons for the time overruns, including land acquisition issues, environmental clearances, financial problems, contractual and internal issues, manpower shortages, and litigation. (Source: Business Standard )

According to an official report, 448 infrastructure projects, each with an investment of Rs 1.50 billion or more, experienced a cost overrun exceeding Rs 5.55 trillion as of April 2024. The Ministry of Statistics and Programme Implementation (MoSPI), which oversees infrastructure projects costing Rs 1.50 billion and above, reported that out of 1,838 projects, 448 faced cost overruns and 792 were delayed. The total original cost of the 1,838 projects was Rs 27.64 trillion, and their anticipated completion cost is estimated to be Rs 33.19 trillion, indicating an overall cost overrun of more than Rs 5.55 trillion, according to MoSPI's latest report for April 2024. The report also highlighted that the expenditure incurred on these projects up to April 2024 amounted to Rs 16.93 trillion, which is 51 % of the anticipated cost. However, the number of delayed projects decreased to 514 when the delay was calculated based on the latest completion schedule. Of the 792 delayed projects, 220 experienced delays ranging from 1 to 12 months, 192 were delayed by 13 to 24 months, 259 by 25 to 60 months, and 121 by more than 60 months. The average time overrun for these 792 delayed projects is 35.4 months. The report cited various reasons for the time overruns, including land acquisition issues, environmental clearances, financial problems, contractual and internal issues, manpower shortages, and litigation. (Source: Business Standard )

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement