+
448 infra projects hit by cost overrun in April
ECONOMY & POLICY

448 infra projects hit by cost overrun in April

According to an official report, 448 infrastructure projects, each with an investment of Rs 1.50 billion or more, experienced a cost overrun exceeding Rs 5.55 trillion as of April 2024. The Ministry of Statistics and Programme Implementation (MoSPI), which oversees infrastructure projects costing Rs 1.50 billion and above, reported that out of 1,838 projects, 448 faced cost overruns and 792 were delayed.

The total original cost of the 1,838 projects was Rs 27.64 trillion, and their anticipated completion cost is estimated to be Rs 33.19 trillion, indicating an overall cost overrun of more than Rs 5.55 trillion, according to MoSPI's latest report for April 2024.

The report also highlighted that the expenditure incurred on these projects up to April 2024 amounted to Rs 16.93 trillion, which is 51 % of the anticipated cost. However, the number of delayed projects decreased to 514 when the delay was calculated based on the latest completion schedule.

Of the 792 delayed projects, 220 experienced delays ranging from 1 to 12 months, 192 were delayed by 13 to 24 months, 259 by 25 to 60 months, and 121 by more than 60 months. The average time overrun for these 792 delayed projects is 35.4 months.

The report cited various reasons for the time overruns, including land acquisition issues, environmental clearances, financial problems, contractual and internal issues, manpower shortages, and litigation. (Source: Business Standard )

According to an official report, 448 infrastructure projects, each with an investment of Rs 1.50 billion or more, experienced a cost overrun exceeding Rs 5.55 trillion as of April 2024. The Ministry of Statistics and Programme Implementation (MoSPI), which oversees infrastructure projects costing Rs 1.50 billion and above, reported that out of 1,838 projects, 448 faced cost overruns and 792 were delayed. The total original cost of the 1,838 projects was Rs 27.64 trillion, and their anticipated completion cost is estimated to be Rs 33.19 trillion, indicating an overall cost overrun of more than Rs 5.55 trillion, according to MoSPI's latest report for April 2024. The report also highlighted that the expenditure incurred on these projects up to April 2024 amounted to Rs 16.93 trillion, which is 51 % of the anticipated cost. However, the number of delayed projects decreased to 514 when the delay was calculated based on the latest completion schedule. Of the 792 delayed projects, 220 experienced delays ranging from 1 to 12 months, 192 were delayed by 13 to 24 months, 259 by 25 to 60 months, and 121 by more than 60 months. The average time overrun for these 792 delayed projects is 35.4 months. The report cited various reasons for the time overruns, including land acquisition issues, environmental clearances, financial problems, contractual and internal issues, manpower shortages, and litigation. (Source: Business Standard )

Next Story
Infrastructure Transport

Audit Begins on Srisailam Bridge Amid Structural Safety Concerns

An audit of the Srisailam road bridge—an over 50-year-old structure spanning the Krishna River between Andhra Pradesh and Telangana—has commenced amid growing concerns over its structural integrity.Authorities from the Roads & Buildings (R&B) Department and the National Highways Authority of India (NHAI) conducted a detailed inspection over the weekend following reports of significant vibrations when heavy vehicles traverse the bridge. Engineering teams carried out load tests, including the movement of a tipper truck across the span with varying weights, to monitor the bridge’s r..

Next Story
Infrastructure Urban

SC permits felling of 95 trees for road project near Aarey

The Supreme Court has permitted the felling of 95 trees for the Goregaon-Mulund Link Road (GMLR) project in Mumbai’s Film City area, located near the Aarey forest belt. However, the Court clarified that no trees may be cut without its explicit permission.A bench headed by Chief Justice of India D Y Chandrachud and Justice K Vinod Chandran heard the Bombay Municipal Corporation’s (BMC) plea seeking approval to proceed with the initial phase of tree removal. The request followed a previous Supreme Court order dated January 10, which barred the BMC’s Tree Authority from cutting trees in Aar..

Next Story
Infrastructure Transport

Bengaluru Tunnel Road DPR Reduces Tunnelling Timeline to 24 Months

Officials from Bengaluru Smart Infrastructure (B-SMILE) claim the reduced timeline is achievable through the deployment of advanced TBMs, each capable of boring a minimum of 200 metres per month—more than double the previous estimate. The overall project duration has also been reduced from 61 months to 50 months in the final DPR.“We initially considered six TBMs with a cutting speed of 90 metres per month, but that made the process too lengthy,” said B S Prahallad, Director, B-SMILE. “Switching to eight high-speed machines allows us to complete 32 km of tunnelling in two years under op..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?