448 infra projects hit by cost overrun in April
ECONOMY & POLICY

448 infra projects hit by cost overrun in April

According to an official report, 448 infrastructure projects, each with an investment of Rs 1.50 billion or more, experienced a cost overrun exceeding Rs 5.55 trillion as of April 2024. The Ministry of Statistics and Programme Implementation (MoSPI), which oversees infrastructure projects costing Rs 1.50 billion and above, reported that out of 1,838 projects, 448 faced cost overruns and 792 were delayed.

The total original cost of the 1,838 projects was Rs 27.64 trillion, and their anticipated completion cost is estimated to be Rs 33.19 trillion, indicating an overall cost overrun of more than Rs 5.55 trillion, according to MoSPI's latest report for April 2024.

The report also highlighted that the expenditure incurred on these projects up to April 2024 amounted to Rs 16.93 trillion, which is 51 % of the anticipated cost. However, the number of delayed projects decreased to 514 when the delay was calculated based on the latest completion schedule.

Of the 792 delayed projects, 220 experienced delays ranging from 1 to 12 months, 192 were delayed by 13 to 24 months, 259 by 25 to 60 months, and 121 by more than 60 months. The average time overrun for these 792 delayed projects is 35.4 months.

The report cited various reasons for the time overruns, including land acquisition issues, environmental clearances, financial problems, contractual and internal issues, manpower shortages, and litigation. (Source: Business Standard )

According to an official report, 448 infrastructure projects, each with an investment of Rs 1.50 billion or more, experienced a cost overrun exceeding Rs 5.55 trillion as of April 2024. The Ministry of Statistics and Programme Implementation (MoSPI), which oversees infrastructure projects costing Rs 1.50 billion and above, reported that out of 1,838 projects, 448 faced cost overruns and 792 were delayed. The total original cost of the 1,838 projects was Rs 27.64 trillion, and their anticipated completion cost is estimated to be Rs 33.19 trillion, indicating an overall cost overrun of more than Rs 5.55 trillion, according to MoSPI's latest report for April 2024. The report also highlighted that the expenditure incurred on these projects up to April 2024 amounted to Rs 16.93 trillion, which is 51 % of the anticipated cost. However, the number of delayed projects decreased to 514 when the delay was calculated based on the latest completion schedule. Of the 792 delayed projects, 220 experienced delays ranging from 1 to 12 months, 192 were delayed by 13 to 24 months, 259 by 25 to 60 months, and 121 by more than 60 months. The average time overrun for these 792 delayed projects is 35.4 months. The report cited various reasons for the time overruns, including land acquisition issues, environmental clearances, financial problems, contractual and internal issues, manpower shortages, and litigation. (Source: Business Standard )

Next Story
Infrastructure Transport

CPCL crosses $10 million revenue milestone

Chaitanya Projects Consultancy (CPCL), a leading infrastructure and engineering consultancy, has surpassed $10 million in annual revenue for FY 2024–25, marking a five-year compound annual growth rate of 28.2 per cent—well above the industry average. Established in 2004, CPCL has delivered over 300 projects across highways, bridges, urban infrastructure, water, transport, and environmental sectors. Its achievements include over 600 km of six-lane highways, 2,000 km of national highways, and 100 major bridges. “Our goal has always been to improve India’s infrastructure,” sai..

Next Story
Resources

KPIL secures new orders worth Rs 37.89 billion

Kalpataru Projects International Ltd (KPIL), a major EPC player in power transmission and civil infrastructure, has secured new orders worth approximately Rs 37.89 billion along with its international subsidiaries. The orders include a significant contract in the Buildings and Factories (B&F) segment in India, marking KPIL’s largest B&F order to date. The project involves the development of over 12 million sq ft of residential space with supporting infrastructure, awarded on a design-build basis. Additionally, the company has won new transmission and distribution (T&D) order..

Next Story
Real Estate

Apartment loading rises to 40 per cent in top cities

Driven by rising demand for premium amenities, the average apartment loading across India’s top seven cities has reached 40 per cent in Q1 2025, up from 31 per cent in 2019, according to ANAROCK Research. The loading factor, or the area paid for beyond the usable carpet area, covers common spaces such as lobbies, staircases, and clubhouses. Mumbai Metropolitan Region (MMR) continues to lead with the highest loading at 43 per cent. Bengaluru saw the sharpest jump, from 30 per cent in 2019 to 41 per cent in Q1 2025. Chennai recorded the lowest average loading at 36 per cent. “Sixty..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?