449 infra projects sees cost overruns of Rs 5.1 trillion
ECONOMY & POLICY

449 infra projects sees cost overruns of Rs 5.1 trillion

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

Next Story
Infrastructure Urban

Aadhaar Authentications Cross 27 Billion in FY25

Aadhaar authentication transactions surged past 27.07 billion in FY 2024–25, including 2.47 billion in March alone, reflecting its growing adoption across sectors such as banking, finance, telecom, and public service delivery. Since its inception, the cumulative number of Aadhaar authentication transactions has exceeded 148 billion.The Unique Identification Authority of India’s (UIDAI) AI/ML-based face authentication technology is also witnessing a sharp rise in usage. In March 2025 alone, over 150 million face authentication transactions were recorded. This biometric modality is now used ..

Next Story
Infrastructure Urban

IEPFA Holds Preparatory Meet for 'Niveshak Shivir' Initiative

The Investor Education and Protection Fund Authority (IEPFA), under the Ministry of Corporate Affairs, Government of India, hosted a preparatory meeting on April 28, 2025, with Nodal Officers from stakeholder companies via video conference. The session, chaired by IEPFA CEO Smt. Anita Shah Akella, focused on finalising operational plans for the upcoming ""Niveshak Shivir"" initiative—a joint effort between IEPFA and the Securities and Exchange Board of India (SEBI).""Niveshak Shivir"" aims to improve investor services and streamline the claims process by reaching out to cities with a high nu..

Next Story
Infrastructure Urban

India, France Sign Deal for 26 Rafale-Marine Jets for Navy

India and France have signed an Inter-Governmental Agreement (IGA) for the acquisition of 26 Rafale-Marine aircraft for the Indian Navy, comprising 22 single-seater and four twin-seater jets. The deal also includes training systems, simulators, associated equipment, weapons, and performance-based logistics, along with additional equipment for the Indian Air Force’s existing Rafale fleet.The IGA was signed by India’s Defence Minister Rajnath Singh and French Minister of Armed Forces Sébastien Lecornu. The agreement, along with supply protocols for aircraft and weapons, was exchanged in the..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?