449 infra projects sees cost overruns of Rs 5.1 trillion
ECONOMY & POLICY

449 infra projects sees cost overruns of Rs 5.1 trillion

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Asian Energy Services Q1 FY27 PAT Rises 129 Per Cent

Asian Energy Services Limited reported a 129 per cent year-on-year rise in net profit to Rs 128 million for Q1 FY27, compared with the corresponding quarter last year.Revenue increased 135 per cent year-on-year to Rs 2.71 billion, supported by continued momentum across its services business, disciplined execution and contributions from domestic and international operations. EBITDA grew 81 per cent year-on-year during the quarter.As of June 30, 2026, the company’s standalone order book stood at Rs 17.54 billion, with around 60 per cent coming from oil and gas services and 40 per cent from min..

Next Story
Infrastructure Urban

BioBTX to Build First Commercial-Scale Circular Chemicals Plant

Dutch circular chemistry technology developer BioBTX is building what it says will be the world’s first commercial-scale plant to convert mixed plastic waste into high-quality aromatic chemicals using its proprietary Integrated Catalytic Cracking Process (ICCP) technology.The facility will be built at Chemical Park Delfzijl on the northern coast of the Netherlands and is expected to create 35 jobs. Covestro, which has been a shareholder and strategic partner of BioBTX since 2024, holds a mid-single-digit million-euro investment in the company.BioBTX’s ICCP technology uses catalytic pyrolys..

Next Story
Real Estate

Awfis Q1 FY27 PAT Jumps 140% as Revenue Rises 27%

Awfis Space Solutions reported a 140 per cent year-on-year rise in consolidated profit after tax (PAT) to Rs 240 million for Q1 FY27, compared with Rs 100 million in the corresponding quarter last year.Revenue from operations increased 27 per cent to Rs 4.25 billion from Rs 3.35 billion, while EBITDA rose 28 per cent to Rs 1.62 billion. EBITDA margin improved to 38.2 per cent from 37.8 per cent. Profit before tax increased 135 per cent to Rs 240 million.The company's co-working business recorded 27 per cent year-on-year growth, supported by demand from enterprises, Global Capability Centres (G..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement