449 infra projects sees cost overruns of Rs 5.1 trillion
ECONOMY & POLICY

449 infra projects sees cost overruns of Rs 5.1 trillion

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

According to the Ministry of Statistics and Programme Implementation (MoSPI) report, nearly 449 infrastructure projects out of 1,873 projects, each with an investment of Rs 1.5 billion and above, were hit by a cost overrun of more than Rs 5.01 trillion in March 2024. It also indicated that 779 projects were delayed. The expense on these projects until March 2024 is Rs 17.11 trillion., which is 53.68% of the anticipated cost of the projects. However, the number of delayed projects decreased to 567 if the delay was calculated on the basis of the latest schedule of completion. It further said that 393 projects have neither the tentative gestation duration nor the year of commissioning disclosed. Of the 779 projects that have been postponed, 202 have been delayed for a total of 1 to 12 months, 181 for 13 to 24 months, 277 for 25 to 60 months, and 119 for longer than 60 months. 36.04 months is the average time overrun for these 779 delayed projects. Various project implementing agencies have indicated that delays in land acquisition, gaining approvals related to the environment and forests, and a lack of infrastructural support and connectivity are among the reasons for schedule overruns. Among other things, delays in securing project funding, completion of technical engineering, scope changes, tendering, ordering, and equipment delivery, and issues with law and order The 1,873 projects' total estimated completion cost is expected to be Rs 31.88 trillion, reflecting an overall cost overrun of Rs 5.01 trillion (18% of the original cost). The 1,873 projects' total initial cost of execution was Rs 26.87 trillion. The study also attributed the delay in these projects' completion to state-level lockdowns brought on by COVID-19, which were implemented in 2020 and 2021. Additionally, it has been noted that many project execution agencies are failing to provide updated cost estimates and commissioning timelines, which raises the possibility that time and cost overrun statistics are being underreported.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement