Around 438 infra projects show cost overruns of Rs 4.3 lakh cr
ECONOMY & POLICY

Around 438 infra projects show cost overruns of Rs 4.3 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more.

From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects.

The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost.

The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report.

The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule.

For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed.

From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more.

The average time of cost overrun for delayed projects is 47 months.

According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage.

Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay.

As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more. From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects. The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost. The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report. The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule. For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed. From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more. The average time of cost overrun for delayed projects is 47 months. According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage. Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay. As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation. Image SourceAlso read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Equipment

Better Concrete Handling

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select WellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Dharavi Rising!

Dharavi, Asia’s largest informal settlement, stands on the cusp of a historic transformation. With an ambitious urban renewal project finally taking shape, millions of residents are looking ahead with hope. But delivering a project of this scale brings immense challenges – from land acquisition to rehabilitate ineligible residents outside Dharavi and rehabilitation to infrastructure development. It also requires balancing commercial goals with deep-rooted social impact. At the helm is SVR Srinivas, IAS, CEO & Officer on Special Duty, Dharavi Redevelopment Project (DRP), Government..

Next Story
Infrastructure Urban

Patel Engineering Secures Two Projects Worth Rs 20.37 Billion

Patel Engineering Ltd has secured two important infrastructure projects valued at Rs 20.37 billion. The company received an order from the City and Industrial Development Corporation of Maharashtra Ltd (CIDCO) for dam construction and associated works in Maharashtra. The project will be executed over a period of 42 months. Another project, awarded by the North Eastern Electric Power Corporation Ltd (NEEPCO), involves the development of a 240 MW hydropower project in Arunachal Pradesh. The project scope includes civil construction, testing, commissioning, and installation of hydro-mechanical e..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?