Around 438 infra projects show cost overruns of Rs 4.3 lakh cr
ECONOMY & POLICY

Around 438 infra projects show cost overruns of Rs 4.3 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more.

From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects.

The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost.

The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report.

The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule.

For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed.

From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more.

The average time of cost overrun for delayed projects is 47 months.

According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage.

Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay.

As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more. From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects. The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost. The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report. The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule. For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed. From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more. The average time of cost overrun for delayed projects is 47 months. According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage. Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay. As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation. Image SourceAlso read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement