Around 438 infra projects show cost overruns of Rs 4.3 lakh cr
ECONOMY & POLICY

Around 438 infra projects show cost overruns of Rs 4.3 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more.

From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects.

The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost.

The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report.

The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule.

For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed.

From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more.

The average time of cost overrun for delayed projects is 47 months.

According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage.

Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay.

As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation.

Image Source


Also read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

According to a report, about 438 infrastructure projects of over Rs 150 crore have been hit by cost overruns of over Rs 4.3 lakh crore. The Ministry of Statistics and Programme monitors projects worth Rs 150 crore or more. From the total 1,670 infrastructure projects, 438 witnessed cost overruns, and 563 were delayed projects. The Ministry said that the initial cost of implementation of 1,670 projects was Rs 21,66,048.11 crore, and their anticipation completion cost is expected to be Rs 25,96,907.70 crore, which reflects an overall cost overrun of Rs 4,30,859.59 crore, almost 20% of the original cost. The overall expenditure incurred on these infrastructure projects till September is Rs 12,54,512.40 crore, which is 48.31% of the anticipated cost, said the report. The report said that the delayed projects have decreased to 380 if the delay is calculated based on the latest completion schedule. For 808 projects, neither the year of commissioning nor the tentative gestation period has been witnessed. From the total delayed projects, 100 projects were delayed between 1-12 months, 120 for 13-24 months, 216 for 25-60 months, and 127 projects for 61 months or more. The average time of cost overrun for delayed projects is 47 months. According to the agencies, the cost overrun may be due to delayed land acquisition, getting forest and environmental clearances, and lack of infrastructure support and linkage. Delay in project financing, finalisation in detailed engineering works, delay in tendering, change in scope of work, ordering and equipment supply, and other legal issues are other reasons for the delay. As per the report, Covid-19 lockdowns were also a reason for the delay in project implementation. Image SourceAlso read: 470 infra projects show cost overruns worth Rs 4.38 lakh cr

Next Story
Equipment

Schwing Stetter India Unveils New Innovations at Excon 2025

Schwing Stetter India unveiled more than 20 new machines at Excon 2025, marking one of its most significant showcases and introducing several India-first technologies to the construction equipment sector. The company launched the country’s first 56-metre boom pump designed and manufactured in India, the first fully electric truck mixer, the first CNG mixer variant and the first hybrid boom pump. Executives said the launch portfolio was engineered to support India’s move toward faster, greener and more vertically oriented infrastructure through advanced engineering, clean-energy solutions a..

Next Story
Infrastructure Energy

SEPC Resolves Hindustan Copper Dispute, Wins Rs 725 Mn Order

Engineering, procurement and construction firm SEPC Ltd has recently settled a dispute with Hindustan Copper Ltd (HCL) and secured a mining infrastructure order valued at Rs 725 million from the state-owned company. SEPC informed the stock exchanges that it has executed a settlement deed with HCL, bringing closure to all inter-se claims and counterclaims arising from arbitration proceedings. As part of the settlement, SEPC will receive Rs 304.5 million as full and final payment, marking the resolution of all pending disputes between the two entities. The company also stated that Hindustan Co..

Next Story
Infrastructure Energy

20% Ethanol Blending Cuts India’s CO2 Emissions by 73.6 Mn Tonnes

Union Road Transport and Highways Minister Nitin Gadkari recently said that India has reduced carbon dioxide emissions by 73.6 million metric tonnes due to the adoption of 20 per cent ethanol blending in petrol. He made the statement while replying to supplementary questions during the Question Hour in the Lok Sabha. Describing ethanol as a green fuel, the minister said it plays a key role in reducing pollution while also supporting higher incomes for farmers. He underlined that ethanol blending contributes both to environmental sustainability and rural economic growth. Nitin Gadkari also po..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App