Covid-19 curbs hit infra works, takeover of DLF areas in Gurugram
ECONOMY & POLICY

Covid-19 curbs hit infra works, takeover of DLF areas in Gurugram

The Municipal Corporation of Gurugram (MCG) has decided to extend the deadlines for DLF to complete the pending civic infrastructure work in DLF Phase 1, 2, and 3 for their handover to the corporation, citing delays caused by Covid-19 restrictions.

In February this year, MCG had decided to provide civic amenities to DLF Phases 1, 2, and 3 from March, ahead of an impending total takeover. The services included cleaning of roads and drains, pruning of trees, installing of sewage treatment plant (STP), open-air gyms and compost plants, and laying pavement tiles.

DLF submitted a tentative timeline to finish the pending work between July and December in the meeting held in February. However, the timeline has been found too long by the MCG officials, and June 30 has been set as the deadline.

A senior MCG official told the media that around 70% to 80% of the work related to roads had been finished in the DLF-1 and 2. It was the status before the lockdown was implemented. However, most of the work is still pending in the DLF-3, and they have not yet been able to hold a meeting and discuss the takeover.

Chief Minister of Haryana, Manohar Lal Khattar had announced the takeover of DLF Phase 1, 2, and 3 in 2016.

The MCG, in 2017, had carried out a civic infrastructure survey of the three colonies to determine the estimated cost of repairs and new infrastructure in the three DLF phases.

The survey done as per the building plans for the three colonies approved by the directorate of town and country planning (DTCP) in the 1980s set the cost at Rs 192.91 crore in the three colonies. This was revised to Rs 35.44 crore after the developer raised issues regarding the estimate.

It is only after completion of works by DLF, such as road repairs, water supply, sewerage, parks, open spaces, and streetlight, the colonies can be taken over by the MCG.

Image Source


Also read: Home sales in tier-2, tier-3 cities decline in April amid Covid-19

Also read: Delhi govt allows construction work for one week starting May 31

The Municipal Corporation of Gurugram (MCG) has decided to extend the deadlines for DLF to complete the pending civic infrastructure work in DLF Phase 1, 2, and 3 for their handover to the corporation, citing delays caused by Covid-19 restrictions. In February this year, MCG had decided to provide civic amenities to DLF Phases 1, 2, and 3 from March, ahead of an impending total takeover. The services included cleaning of roads and drains, pruning of trees, installing of sewage treatment plant (STP), open-air gyms and compost plants, and laying pavement tiles. DLF submitted a tentative timeline to finish the pending work between July and December in the meeting held in February. However, the timeline has been found too long by the MCG officials, and June 30 has been set as the deadline. A senior MCG official told the media that around 70% to 80% of the work related to roads had been finished in the DLF-1 and 2. It was the status before the lockdown was implemented. However, most of the work is still pending in the DLF-3, and they have not yet been able to hold a meeting and discuss the takeover. Chief Minister of Haryana, Manohar Lal Khattar had announced the takeover of DLF Phase 1, 2, and 3 in 2016. The MCG, in 2017, had carried out a civic infrastructure survey of the three colonies to determine the estimated cost of repairs and new infrastructure in the three DLF phases. The survey done as per the building plans for the three colonies approved by the directorate of town and country planning (DTCP) in the 1980s set the cost at Rs 192.91 crore in the three colonies. This was revised to Rs 35.44 crore after the developer raised issues regarding the estimate. It is only after completion of works by DLF, such as road repairs, water supply, sewerage, parks, open spaces, and streetlight, the colonies can be taken over by the MCG. Image SourceAlso read: Home sales in tier-2, tier-3 cities decline in April amid Covid-19 Also read: Delhi govt allows construction work for one week starting May 31

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement