GMDA Drain Construction Along SPR Faces Delays
ECONOMY & POLICY

GMDA Drain Construction Along SPR Faces Delays

The Gurugram Metropolitan Development Authority (GMDA) is experiencing significant delays in its drain construction project along the Southern Peripheral Road (SPR). This project, crucial for preventing waterlogging and improving drainage in the region, has hit several roadblocks, causing concern among residents and officials.

The construction of the drain, which spans 16 kilometres along the SPR, is vital for managing the rainwater runoff and preventing the frequent flooding that plagues the area during monsoons. The project was initially scheduled to be completed within a year, but various challenges have pushed the timeline beyond the expected deadline.

Key issues contributing to the delays include land acquisition problems, shifting of utilities, and contractor performance issues. The GMDA has faced difficulties in acquiring the necessary land for the project, leading to stalled work in several sections. Additionally, the process of relocating utilities such as electricity and water lines has proven to be more complex and time-consuming than anticipated.

Contractor performance has also been a significant concern, with some contractors failing to meet the project milestones. This has prompted the GMDA to consider taking stringent actions, including penalizing underperforming contractors and possibly re-tendering parts of the project to expedite the work.

Residents along the SPR have expressed their frustration over the delays, citing persistent waterlogging issues that disrupt daily life and damage property. The GMDA is under pressure to expedite the project and has been urged to improve coordination with other agencies and stakeholders to resolve the existing bottlenecks.

The successful completion of the drain construction along SPR is critical for enhancing the region's infrastructure and ensuring a more resilient drainage system. The GMDA's efforts to address the delays and streamline the project are crucial in mitigating the waterlogging problems and improving the overall quality of life for Gurgaon's residents.

The Gurugram Metropolitan Development Authority (GMDA) is experiencing significant delays in its drain construction project along the Southern Peripheral Road (SPR). This project, crucial for preventing waterlogging and improving drainage in the region, has hit several roadblocks, causing concern among residents and officials. The construction of the drain, which spans 16 kilometres along the SPR, is vital for managing the rainwater runoff and preventing the frequent flooding that plagues the area during monsoons. The project was initially scheduled to be completed within a year, but various challenges have pushed the timeline beyond the expected deadline. Key issues contributing to the delays include land acquisition problems, shifting of utilities, and contractor performance issues. The GMDA has faced difficulties in acquiring the necessary land for the project, leading to stalled work in several sections. Additionally, the process of relocating utilities such as electricity and water lines has proven to be more complex and time-consuming than anticipated. Contractor performance has also been a significant concern, with some contractors failing to meet the project milestones. This has prompted the GMDA to consider taking stringent actions, including penalizing underperforming contractors and possibly re-tendering parts of the project to expedite the work. Residents along the SPR have expressed their frustration over the delays, citing persistent waterlogging issues that disrupt daily life and damage property. The GMDA is under pressure to expedite the project and has been urged to improve coordination with other agencies and stakeholders to resolve the existing bottlenecks. The successful completion of the drain construction along SPR is critical for enhancing the region's infrastructure and ensuring a more resilient drainage system. The GMDA's efforts to address the delays and streamline the project are crucial in mitigating the waterlogging problems and improving the overall quality of life for Gurgaon's residents.

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement