Mumbai’s Mogra Pumping Station Work to Begin After 20-Year Wait
ECONOMY & POLICY

Mumbai’s Mogra Pumping Station Work to Begin After 20-Year Wait

Mumbai’s long-delayed Mogra pumping station is set to enter its main construction phase on October 15, nearly two decades after it was first proposed. The Rs. 3.93 bn project received the environmental clearances required for work to proceed and is intended to improve flood management in western Mumbai.

The facility will be developed along the Mogra nullah near Oshiwara and Lokhandwala. Its planned infrastructure includes tidal gates, retaining walls and related works to improve the movement and discharge of stormwater from flood-prone parts of Andheri, Versova and Jogeshwari during the monsoon.

The project was sanctioned in 2021 with an initial 24-month completion schedule, but land acquisition issues and a conflict with Phase 2 of the Versova-Dahisar Coastal Road delayed progress. Preliminary work began in March 2025, after which the site was moved closer to Lokhandwala Creek Road. The change required fresh Coastal Regulation Zone approval and clearance from the Ministry of Environment, Forest and Climate Change.

The revised timeline allows about three years for completion, while the civic administration is targeting operations before 2029. Mogra forms part of Mumbai’s Rs. 130 bn Integrated Flood Control Action Plan, which is supported by central government financial assistance and includes drainage upgrades, higher stormwater capacity, restoration of the Mithi River and nature-based measures.

Residents and local groups have welcomed the progress but have urged faster execution and stronger action against dumping in nullahs. Bulky waste, including furniture, can obstruct waterways and limit their capacity during heavy rain, particularly around Link Road, Veera Desai Road and other low-lying areas.

Pumping stations are especially important when high tide prevents stormwater from flowing naturally into the sea and floodgates must remain closed. Mogra was among eight facilities recommended by the Chitale Committee under the Brihanmumbai Storm Water Disposal System, or BRIMSTOWAD, after the 2005 floods. Its completion would add capacity to Mumbai’s flood-protection network, alongside existing facilities at Irla, Haji Ali, Cleveland, Lovegrove, Reay Road-Britannia and Gajdhar Bandh.

Mumbai’s long-delayed Mogra pumping station is set to enter its main construction phase on October 15, nearly two decades after it was first proposed. The Rs. 3.93 bn project received the environmental clearances required for work to proceed and is intended to improve flood management in western Mumbai. The facility will be developed along the Mogra nullah near Oshiwara and Lokhandwala. Its planned infrastructure includes tidal gates, retaining walls and related works to improve the movement and discharge of stormwater from flood-prone parts of Andheri, Versova and Jogeshwari during the monsoon. The project was sanctioned in 2021 with an initial 24-month completion schedule, but land acquisition issues and a conflict with Phase 2 of the Versova-Dahisar Coastal Road delayed progress. Preliminary work began in March 2025, after which the site was moved closer to Lokhandwala Creek Road. The change required fresh Coastal Regulation Zone approval and clearance from the Ministry of Environment, Forest and Climate Change. The revised timeline allows about three years for completion, while the civic administration is targeting operations before 2029. Mogra forms part of Mumbai’s Rs. 130 bn Integrated Flood Control Action Plan, which is supported by central government financial assistance and includes drainage upgrades, higher stormwater capacity, restoration of the Mithi River and nature-based measures. Residents and local groups have welcomed the progress but have urged faster execution and stronger action against dumping in nullahs. Bulky waste, including furniture, can obstruct waterways and limit their capacity during heavy rain, particularly around Link Road, Veera Desai Road and other low-lying areas. Pumping stations are especially important when high tide prevents stormwater from flowing naturally into the sea and floodgates must remain closed. Mogra was among eight facilities recommended by the Chitale Committee under the Brihanmumbai Storm Water Disposal System, or BRIMSTOWAD, after the 2005 floods. Its completion would add capacity to Mumbai’s flood-protection network, alongside existing facilities at Irla, Haji Ali, Cleveland, Lovegrove, Reay Road-Britannia and Gajdhar Bandh.

Related Stories

Gold Stories

Next Story
Technology

Where Infrastructure Meets Intelligence: Inside Bentley's Year inc

Oct 28, 2026  @Tanveer PadodeA first-hand account of Bentley’s 2026 awards, where AI, digital twins and engineering innovation are reshaping infrastructure delivery.- By Tanveer Padode, CEO, IMPACCT: A first-hand account of Bentley’s 2026 awards, where AI, digital twins and engineering innovation are reshaping infrastructure delivery.Two days in SingaporeConstruction is won or lost in two places: how a project is designed and how it is delivered. Technology has promised to improve both for years, and the question I carried into Bentley's Year in Infrastructure, held at the Fairmont Si..

Next Story
Infrastructure Transport

Vaishnaw Inaugurates Two Rail Sections in Madhya Pradesh

Railway Minister Ashwini Vaishnaw on October 24 inaugurated the Satna-Devendranagar and Rewa-Churhat rail sections under the Lalitpur-Singrauli Railway Project in Madhya Pradesh. He also flagged off the new Devendranagar-Churhat passenger train service through video conferencing. Chief Minister Dr Mohan Yadav attended the event. The new Rewa-Churhat railway line, which extends approximately 65 km, was built at a cost of over Rs. 10 bn. The 53 km Satna-Devendranagar line was constructed at a cost of over Rs. 8 bn. The passenger service is expected to provide improved rail access to residents in..

Next Story
Infrastructure Transport

Railways Minister to Inaugurate New Rail Sections Covering 118 km

Railways Minister Ashwini Vaishnaw will inaugurate the Satna-Devendra Nagar and Rewa-Churhat rail sections in Madhya Pradesh on October 24. The two sections have a combined length of 118 km and are intended to improve passenger and freight connectivity across the region. Vaishnaw will also flag off a new train service between Devendra Nagar and Churhat. Madhya Pradesh Chief Minister Mohan Yadav will attend the inauguration programme, according to information released by the Ministry of Railways. The 53-km Satna-Devendra Nagar section is expected to improve rail access to Satna, Nagod, Devendra..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code