Mumbai’s Mogra Pumping Station Work to Begin After 20-Year Wait
ECONOMY & POLICY

Mumbai’s Mogra Pumping Station Work to Begin After 20-Year Wait

Mumbai’s long-delayed Mogra pumping station is set to enter its main construction phase on October 15, nearly two decades after it was first proposed. The Rs. 3.93 bn project received the environmental clearances required for work to proceed and is intended to improve flood management in western Mumbai.

The facility will be developed along the Mogra nullah near Oshiwara and Lokhandwala. Its planned infrastructure includes tidal gates, retaining walls and related works to improve the movement and discharge of stormwater from flood-prone parts of Andheri, Versova and Jogeshwari during the monsoon.

The project was sanctioned in 2021 with an initial 24-month completion schedule, but land acquisition issues and a conflict with Phase 2 of the Versova-Dahisar Coastal Road delayed progress. Preliminary work began in March 2025, after which the site was moved closer to Lokhandwala Creek Road. The change required fresh Coastal Regulation Zone approval and clearance from the Ministry of Environment, Forest and Climate Change.

The revised timeline allows about three years for completion, while the civic administration is targeting operations before 2029. Mogra forms part of Mumbai’s Rs. 130 bn Integrated Flood Control Action Plan, which is supported by central government financial assistance and includes drainage upgrades, higher stormwater capacity, restoration of the Mithi River and nature-based measures.

Residents and local groups have welcomed the progress but have urged faster execution and stronger action against dumping in nullahs. Bulky waste, including furniture, can obstruct waterways and limit their capacity during heavy rain, particularly around Link Road, Veera Desai Road and other low-lying areas.

Pumping stations are especially important when high tide prevents stormwater from flowing naturally into the sea and floodgates must remain closed. Mogra was among eight facilities recommended by the Chitale Committee under the Brihanmumbai Storm Water Disposal System, or BRIMSTOWAD, after the 2005 floods. Its completion would add capacity to Mumbai’s flood-protection network, alongside existing facilities at Irla, Haji Ali, Cleveland, Lovegrove, Reay Road-Britannia and Gajdhar Bandh.

Mumbai’s long-delayed Mogra pumping station is set to enter its main construction phase on October 15, nearly two decades after it was first proposed. The Rs. 3.93 bn project received the environmental clearances required for work to proceed and is intended to improve flood management in western Mumbai. The facility will be developed along the Mogra nullah near Oshiwara and Lokhandwala. Its planned infrastructure includes tidal gates, retaining walls and related works to improve the movement and discharge of stormwater from flood-prone parts of Andheri, Versova and Jogeshwari during the monsoon. The project was sanctioned in 2021 with an initial 24-month completion schedule, but land acquisition issues and a conflict with Phase 2 of the Versova-Dahisar Coastal Road delayed progress. Preliminary work began in March 2025, after which the site was moved closer to Lokhandwala Creek Road. The change required fresh Coastal Regulation Zone approval and clearance from the Ministry of Environment, Forest and Climate Change. The revised timeline allows about three years for completion, while the civic administration is targeting operations before 2029. Mogra forms part of Mumbai’s Rs. 130 bn Integrated Flood Control Action Plan, which is supported by central government financial assistance and includes drainage upgrades, higher stormwater capacity, restoration of the Mithi River and nature-based measures. Residents and local groups have welcomed the progress but have urged faster execution and stronger action against dumping in nullahs. Bulky waste, including furniture, can obstruct waterways and limit their capacity during heavy rain, particularly around Link Road, Veera Desai Road and other low-lying areas. Pumping stations are especially important when high tide prevents stormwater from flowing naturally into the sea and floodgates must remain closed. Mogra was among eight facilities recommended by the Chitale Committee under the Brihanmumbai Storm Water Disposal System, or BRIMSTOWAD, after the 2005 floods. Its completion would add capacity to Mumbai’s flood-protection network, alongside existing facilities at Irla, Haji Ali, Cleveland, Lovegrove, Reay Road-Britannia and Gajdhar Bandh.

Related Stories

Gold Stories

Next Story
Resources

Hettich India And ECO Schulte Form Joint Venture In India

Hettich India and German company ECO Schulte have announced a strategic joint venture to strengthen their presence in India's architectural hardware market. The partnership was announced at ACETECH Mumbai on November 20, 2026, bringing together the two family-owned businesses with a combined engineering heritage of 238 years.The venture combines Hettich's expertise in furniture fittings and interior solutions with ECO Schulte's experience in architectural door hardware and engineered door systems. Its focus will span residential, commercial, institutional and infrastructure projects.Hettich, w..

Next Story
Real Estate

Address Maker sells over 200 Apollo Address plots in six weeks

The Address Maker Group has sold more than two-thirds of the inventory at its Apollo Address villa-plot development in Nelamangala, North-West Bengaluru, within six weeks of its launch. With over 200 plots purchased and approximately 100 remaining, the project has recorded the fastest sales pace in the developer's history.Spread across 23 acres within a larger 90-acre township, Apollo Address offers villa plots ranging from 1,200 to 2,400 sq ft. Inspired by classical Greek architecture, the development features planned infrastructure, landscaped open spaces and residential amenities.Nearly 30 ..

Next Story
Equipment

Zoomlion strengthens equipment partnerships in Australia

Zoomlion Heavy Industry Science & Technology has reaffirmed its commitment to expanding operations in Australia, with Chairman and CEO Zhan Chunxin meeting customers and business partners in Sydney to strengthen long-term partnerships and discuss opportunities for closer collaboration.The meeting, held on 4 November 2026, focused on equipment quality, technical support, spare parts availability, local training and customer service improvements. Representatives from the tower crane, concrete machinery, earthmoving, aerial work platform, agricultural machinery and financial sectors participa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code