Mumbai’s Mogra Pumping Station Work to Begin After 20-Year Wait
ECONOMY & POLICY

Mumbai’s Mogra Pumping Station Work to Begin After 20-Year Wait

Mumbai’s long-delayed Mogra pumping station is set to enter its main construction phase on October 15, nearly two decades after it was first proposed. The Rs. 3.93 bn project received the environmental clearances required for work to proceed and is intended to improve flood management in western Mumbai.

The facility will be developed along the Mogra nullah near Oshiwara and Lokhandwala. Its planned infrastructure includes tidal gates, retaining walls and related works to improve the movement and discharge of stormwater from flood-prone parts of Andheri, Versova and Jogeshwari during the monsoon.

The project was sanctioned in 2021 with an initial 24-month completion schedule, but land acquisition issues and a conflict with Phase 2 of the Versova-Dahisar Coastal Road delayed progress. Preliminary work began in March 2025, after which the site was moved closer to Lokhandwala Creek Road. The change required fresh Coastal Regulation Zone approval and clearance from the Ministry of Environment, Forest and Climate Change.

The revised timeline allows about three years for completion, while the civic administration is targeting operations before 2029. Mogra forms part of Mumbai’s Rs. 130 bn Integrated Flood Control Action Plan, which is supported by central government financial assistance and includes drainage upgrades, higher stormwater capacity, restoration of the Mithi River and nature-based measures.

Residents and local groups have welcomed the progress but have urged faster execution and stronger action against dumping in nullahs. Bulky waste, including furniture, can obstruct waterways and limit their capacity during heavy rain, particularly around Link Road, Veera Desai Road and other low-lying areas.

Pumping stations are especially important when high tide prevents stormwater from flowing naturally into the sea and floodgates must remain closed. Mogra was among eight facilities recommended by the Chitale Committee under the Brihanmumbai Storm Water Disposal System, or BRIMSTOWAD, after the 2005 floods. Its completion would add capacity to Mumbai’s flood-protection network, alongside existing facilities at Irla, Haji Ali, Cleveland, Lovegrove, Reay Road-Britannia and Gajdhar Bandh.

Mumbai’s long-delayed Mogra pumping station is set to enter its main construction phase on October 15, nearly two decades after it was first proposed. The Rs. 3.93 bn project received the environmental clearances required for work to proceed and is intended to improve flood management in western Mumbai. The facility will be developed along the Mogra nullah near Oshiwara and Lokhandwala. Its planned infrastructure includes tidal gates, retaining walls and related works to improve the movement and discharge of stormwater from flood-prone parts of Andheri, Versova and Jogeshwari during the monsoon. The project was sanctioned in 2021 with an initial 24-month completion schedule, but land acquisition issues and a conflict with Phase 2 of the Versova-Dahisar Coastal Road delayed progress. Preliminary work began in March 2025, after which the site was moved closer to Lokhandwala Creek Road. The change required fresh Coastal Regulation Zone approval and clearance from the Ministry of Environment, Forest and Climate Change. The revised timeline allows about three years for completion, while the civic administration is targeting operations before 2029. Mogra forms part of Mumbai’s Rs. 130 bn Integrated Flood Control Action Plan, which is supported by central government financial assistance and includes drainage upgrades, higher stormwater capacity, restoration of the Mithi River and nature-based measures. Residents and local groups have welcomed the progress but have urged faster execution and stronger action against dumping in nullahs. Bulky waste, including furniture, can obstruct waterways and limit their capacity during heavy rain, particularly around Link Road, Veera Desai Road and other low-lying areas. Pumping stations are especially important when high tide prevents stormwater from flowing naturally into the sea and floodgates must remain closed. Mogra was among eight facilities recommended by the Chitale Committee under the Brihanmumbai Storm Water Disposal System, or BRIMSTOWAD, after the 2005 floods. Its completion would add capacity to Mumbai’s flood-protection network, alongside existing facilities at Irla, Haji Ali, Cleveland, Lovegrove, Reay Road-Britannia and Gajdhar Bandh.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Madhya Pradesh Plans Airport Every 150 Km, Airstrip Every 75 Km

The Madhya Pradesh government plans to establish an airport every 150 km, an airstrip every 75 km and a helipad every 45 km, according to the state aviation department. Airports being developed in Ujjain and Shivpuri are expected to take the state’s airport count to 10. The government stated that Madhya Pradesh currently has eight airports in eight cities. The locations named by the department include Indore, Bhopal, Jabalpur, Gwalior, Khajuraho, Rewa and Satna. The state also has more than 20 airstrips and 220 helipads, while permanent helipads are planned in all 230 Assembly constituencies..

Next Story
Infrastructure Transport

West Bengal Plans Four Airports for 2028 Completion Under UDAN

West Bengal will develop four new airports under an agreement signed between the Union Civil Aviation Ministry and the state government, with all facilities targeted for completion by 2028. Union Civil Aviation Minister K Rammohan Naidu said the airports would be located at Charra in Purulia, Kalaikunda in Paschim Medinipur, Balurghat in Dakshin Dinajpur and Hasimara in Alipurduar. The project is part of the Centre’s regional connectivity UDAN programme. The Union government has committed Rs. 290 bn for West Bengal’s aviation sector over the next decade, while the state government will pro..

Next Story
Infrastructure Transport

Mumbai Airport Bars Russian Airlines as Agent Seeks Ministry Intervention

Mumbai airport has stopped accepting cargo booked on Russian flag carrier Aeroflot, disrupting shipments and prompting the airline’s cargo sales agent, Delmos Aviation, to seek intervention from the Ministry of Civil Aviation. The restrictions also affect cargo booked on Volga-Dnepr Airlines, according to a letter submitted by Delmos Aviation to the ministry on September 30. Aeroflot operates daily flights between Moscow and Delhi and runs a winter seasonal service to Goa. Bonded cargo from Mumbai and other cities is transported by road to Delhi before being flown to Russia. The agent said t..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code