+
Reactor Containment Successfully Tested at Rooppur NPP Unit 1
ECONOMY & POLICY

Reactor Containment Successfully Tested at Rooppur NPP Unit 1

At power unit No.1 of the Rooppur NPP, which is being built in the People's Republic of Bangladesh by the Rosatom State Corporation Engineering Division, tightness and strength tests have been successfully conducted at the containment of the reactor compartment. The tests confirmed full compliance with the design requirements and the highest safety standards of the reactor containment.

During the tests, a compressor was used to increase the pressure inside the containment to the design value of 4.6 kgf/cm² (which corresponds to approximately 0.45 MPa) and a series of tests were conducted to confirm the structure’s tightness and ability to withstand internal loads that occur in abnormal conditions.

The tests were successful to confirm that the containment complies in full scope with the design requirements. This is especially important at the stage of preparation for nuclear fuel loading, since the containment acts as the last protective barrier in the event of a hypothetical accident.

The containment is a physical barrier made of pre-stressed reinforced concrete with an internal sealing steel lining. It is designed to prevent the release of radioactive substances into the environment in the event of an emergency and to localize them inside the containment, as well as to protect against possible external impacts.

“A number of operations are unique and carried out once during these tests, only after the construction and erection works have been completed in the reactor building. The tests results confirm that the containment system fully complies with all design and regulatory requirements. This is an important step towards commissioning of power unit 1 which testifies to high quality of work at all stages of construction,” said Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh.

As soon as these tests are completed, the NPP will proceed to a series of hot media tests, namely, the primary coolant circuit heated to rated values and the generated steam.

Various safety modes of the NPP operation will be tested, including the operation mode of the devices providing steam discharge into the atmosphere. The tests are accompanied at the NPP by noise which is planned and absolutely safe for the public.

Rosatom's most important priority is safety, therefore the project focuses on meeting all mandatory standards and requirements.

The Rooppur NPP equipped with two VVER-1200 reactors of the total 2400 MW capacity is being constructed under the Russian design 160 km from Dhaka, the capital of Bangladesh, in accordance with General Contract dated December 25, 2015.

At power unit No.1 of the Rooppur NPP, which is being built in the People's Republic of Bangladesh by the Rosatom State Corporation Engineering Division, tightness and strength tests have been successfully conducted at the containment of the reactor compartment. The tests confirmed full compliance with the design requirements and the highest safety standards of the reactor containment.During the tests, a compressor was used to increase the pressure inside the containment to the design value of 4.6 kgf/cm² (which corresponds to approximately 0.45 MPa) and a series of tests were conducted to confirm the structure’s tightness and ability to withstand internal loads that occur in abnormal conditions.The tests were successful to confirm that the containment complies in full scope with the design requirements. This is especially important at the stage of preparation for nuclear fuel loading, since the containment acts as the last protective barrier in the event of a hypothetical accident.The containment is a physical barrier made of pre-stressed reinforced concrete with an internal sealing steel lining. It is designed to prevent the release of radioactive substances into the environment in the event of an emergency and to localize them inside the containment, as well as to protect against possible external impacts.“A number of operations are unique and carried out once during these tests, only after the construction and erection works have been completed in the reactor building. The tests results confirm that the containment system fully complies with all design and regulatory requirements. This is an important step towards commissioning of power unit 1 which testifies to high quality of work at all stages of construction,” said Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh.As soon as these tests are completed, the NPP will proceed to a series of hot media tests, namely, the primary coolant circuit heated to rated values and the generated steam.Various safety modes of the NPP operation will be tested, including the operation mode of the devices providing steam discharge into the atmosphere. The tests are accompanied at the NPP by noise which is planned and absolutely safe for the public.Rosatom's most important priority is safety, therefore the project focuses on meeting all mandatory standards and requirements.The Rooppur NPP equipped with two VVER-1200 reactors of the total 2400 MW capacity is being constructed under the Russian design 160 km from Dhaka, the capital of Bangladesh, in accordance with General Contract dated December 25, 2015.

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement