TANGEDCO applies for new Environmental Clearance for Udangudi project
ECONOMY & POLICY

TANGEDCO applies for new Environmental Clearance for Udangudi project

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021.

In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project.

Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021. In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project. Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Jammu Division Records Highest Punctuality of 94.12%

The Jammu Division of Northern Railway (Jammu Division) set a new benchmark in operational efficiency when it achieved a single-day punctuality rate of 94.12 per cent for Mail and Express trains on July 31. This performance is the highest recorded in the division's history and surpasses the previous best of 92.59 per cent achieved on February 20, 2025. The official communique indicated that the figure represents a significant improvement in on-time arrivals and departures across the network. Railway officials attributed the outcome to meticulous planning and effective coordination between grou..

Next Story
Infrastructure Transport

Tinaighat-Kulem Rail Doubling Threatens Forest Biodiversity

A peer-reviewed study by 20 scientists has challenged the cumulative environmental impact assessment prepared by the Wildlife Institute of India for the proposed doubling of the Tinaighat-Kulem railway line in Karnataka and Goa. The study says the assessment overlooks biodiversity and ecological impacts across one of the region's most sensitive forest landscapes. The authors describe the matter as urgent given the scale of planned infrastructure. The review was published in the Journal of Threatened Taxa and was carried out by a multidisciplinary team of ecologists, social scientists, conserva..

Next Story
Infrastructure Transport

CONCOR Launches Ennore to Hyderabad Rail Freight Service

Container Corporation of India (CONCOR) has commenced a new rail freight service that links Ennore Port, part of the Kamarajar Port cluster in Chennai, with ICD Sanathnagar in Hyderabad. The new corridor provides containerised cargo movement directly between the eastern gateway port and a major inland logistics hub in the Deccan plateau. CONCOR positioned the launch as an expansion of its multi-modal offerings to trade and industry in Telangana and neighbouring regions. The service connects the port cluster through intermediate logistics nodes and establishes a dedicated rail corridor for expo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement