TANGEDCO applies for new Environmental Clearance for Udangudi project
ECONOMY & POLICY

TANGEDCO applies for new Environmental Clearance for Udangudi project

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021.

In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project.

Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021. In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project. Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement