+
TANGEDCO applies for new Environmental Clearance for Udangudi project
ECONOMY & POLICY

TANGEDCO applies for new Environmental Clearance for Udangudi project

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021.

In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project.

Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021. In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project. Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code