TANGEDCO applies for new Environmental Clearance for Udangudi project
ECONOMY & POLICY

TANGEDCO applies for new Environmental Clearance for Udangudi project

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021.

In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project.

Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

TANGEDCO has submitted a request for a renewed Environmental Clearance (EC) for the 2X660 MW Udangudi Supercritical Thermal Power Station, aiming to bypass the necessity of public hearings. As the current EC is set to expire on October 13, 2024, TANGEDCO has urged the Ministry of Environment, Forests, and Climate Change to issue fresh terms of reference. The on-going construction of the Udangudi thermal power plant has seen significant progress, with approximately 82.85% of the main plant work completed and 90% of the coal jetty component finalised. To ensure the timely commissioning of the Udangudi power plant, TANGEDCO has requested permission from the MoEF and CC to continue construction activities beyond the validity period while simultaneously processing a fresh EC with new terms of reference for the main plant. Furthermore, TANGEDCO has sought exemption from public hearings in accordance with a notification from the MoEF and CC dated March 18, 2021. In its communication, TANGEDCO highlighted the renewal of the EC and CRZ clearance obtained for the interlinked project of Captive Coal Jetty and pipe conveyor system in August 2022, following the expiration of the ten-year period stipulated by the Environment Impact Assessment notification 2006. The EC renewal involved conducting Rapid Marine and Terrestrial EIA/EMP studies by an accredited consultant from June to November 2021. As the marine baseline data's validity extends for three years, TANGEDCO proposed the continued use of existing marine baseline data in the EIA/EMP study for the power project. Initially conceptualised as a joint venture between TANGEDCO and BHEL, the Udangudi project later transitioned into a state sector project. Delays arose during the bidding process initiated in July 2013, leading to a legal challenge by one of the bidders, subsequently addressed by the Madras High Court. Ultimately, the Engineering, Procurement, and Construction Contract was awarded to BHEL in December 2017 following the court's ruling. ITD Cementation India Ltd was tasked with establishing a captive coal jetty and pipe conveyor system for the Udangudi project in February 2018, but execution faced setbacks due to cyclones and the Covid-19 pandemic.

Next Story
Infrastructure Transport

Tata, Airbus to Build India’s First Private Helicopter Line

In a landmark development for India’s aerospace sector, Tata Advanced Systems Limited (TASL) and Airbus will establish the country’s first private-sector helicopter assembly line in Vemagal, Karnataka. The facility will manufacture the Airbus H125 and H125M, marking a significant milestone in India’s push for self-reliance in aviation and defence manufacturing. The new Final Assembly Line (FAL) will produce the H125, the world’s best-selling single-engine helicopter, known for its versatility and performance in extreme environments. The first ‘Made in India’ H125 is expected to ro..

Next Story
Infrastructure Urban

NeGD to Support Bharat Taxi in Building Cooperative Ride Platform

In a significant move for India’s digital and mobility transformation, the National e-Governance Division (NeGD) of the Digital India Corporation, under the Ministry of Electronics and Information Technology (MeitY), has entered into an advisory partnership with Sahakar Taxi Cooperative Limited, the company behind Bharat Taxi — a first-of-its-kind, cooperative-led national ride-hailing platform. A Memorandum of Understanding (MoU) has been signed between NeGD and Sahakar Taxi to provide strategic advisory and technical support covering key areas such as platform integration, cybersecurity..

Next Story
Technology

MeitY Hosts Pre-Summit for India–AI Impact Summit 2026

The Ministry of Electronics and Information Technology (MeitY), Government of India, hosted a series of Pre-Summit events for the upcoming India–AI Impact Summit 2026 at the India Mobile Congress (IMC) 2025 in New Delhi. These sessions mark a key milestone ahead of the main summit, scheduled for 19–20 February 2026 at Bharat Mandapam, New Delhi. Delivering the inaugural address, S. Krishnan, Secretary, MeitY, highlighted India’s innovative and frugal approach to AI development. “We have adopted innovative means by learning from others’ experiences to build projects and products that..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?