Shirdi airport: Re-carpeting of runway begins
AVIATION & AIRPORTS

Shirdi airport: Re-carpeting of runway begins

Re-carpeting work at the airport, managed and operated by Maharashtra Airport Development Company Limited (MADC), is expected to continue until next February. Shirdi airport director Gaurav Upshyam mentioned that initial work related to re-carpeting has already commenced, with the hot cement mixing plant set up and the contractor working on other areas, such as taxiways. He added that the main work on the runway is scheduled to begin in early October, once the monsoon subsides.

The airport, which was inaugurated by former President Ram Nath Kovind in October 2017, received its license from the DGCA to operate after sunset last February. However, after-sunset flights have not yet commenced.

An MADC official stated that, since the airport operates only between 11 am and 6 pm, re-carpeting work has been planned for after sunset, starting around 6:30 pm and continuing until 10:30 am. While proper re-carpeting of the main runway area is planned, the official noted that any decisions regarding potential disruptions to flight movements would be made based on the situation at the time.

Once the re-carpeting work is completed, the airport is expected to become operational 24 hours a day, with ongoing discussions with airlines, Upshyam said. He further explained that the airport's runway, which has a total length of 3,200 meters, currently uses 2,500 meters. Upon completion of the re-carpeting, the entire stretch will be available for use by airlines.

The director also noted that approximately 2,000 passengers use the airport for arrivals and departures daily and mentioned plans to work towards a new terminal building, which will require additional CISF personnel and other infrastructure.

Re-carpeting work at the airport, managed and operated by Maharashtra Airport Development Company Limited (MADC), is expected to continue until next February. Shirdi airport director Gaurav Upshyam mentioned that initial work related to re-carpeting has already commenced, with the hot cement mixing plant set up and the contractor working on other areas, such as taxiways. He added that the main work on the runway is scheduled to begin in early October, once the monsoon subsides. The airport, which was inaugurated by former President Ram Nath Kovind in October 2017, received its license from the DGCA to operate after sunset last February. However, after-sunset flights have not yet commenced. An MADC official stated that, since the airport operates only between 11 am and 6 pm, re-carpeting work has been planned for after sunset, starting around 6:30 pm and continuing until 10:30 am. While proper re-carpeting of the main runway area is planned, the official noted that any decisions regarding potential disruptions to flight movements would be made based on the situation at the time. Once the re-carpeting work is completed, the airport is expected to become operational 24 hours a day, with ongoing discussions with airlines, Upshyam said. He further explained that the airport's runway, which has a total length of 3,200 meters, currently uses 2,500 meters. Upon completion of the re-carpeting, the entire stretch will be available for use by airlines. The director also noted that approximately 2,000 passengers use the airport for arrivals and departures daily and mentioned plans to work towards a new terminal building, which will require additional CISF personnel and other infrastructure.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code