Amit Shah Likely to Inaugurate Delhi’s Barapullah Phase 3 Projects
ROADS & HIGHWAYS

Amit Shah Likely to Inaugurate Delhi’s Barapullah Phase 3 Projects

Four major road infrastructure projects in Delhi are scheduled to feature at an event on 29 September. Union Home Minister Amit Shah is likely to inaugurate the completed Barapullah Phase 3 elevated corridor and the Mukarba Chowk underpass, besides laying the foundation stones for two new flyovers.

The Barapullah corridor is the largest of the four projects and will provide a signal-free connection between Mayur Vihar Phase 1 and South Delhi. It will link with the existing Barapullah corridor at Sarai Kale Khan, creating a continuous route of around 9 km towards AIIMS and other parts of South Delhi.

The project was approved in 2014, and construction began in 2015. Although completion was initially planned for 2017, delays increased the revised project estimate to around Rs. 16.35 bn. The corridor is now among the key road links intended to improve movement between eastern and southern parts of the capital.

The foundation stones for the Modi Mill-Kalkaji flyover and the Savitri Cinema half-flyover will also be laid at the event. The Modi Mill project forms part of a plan for a 7.2 km signal-free corridor towards IIT Gate, with three lanes in each direction. The Savitri Cinema project involves a 435-metre, three-lane single carriageway, which the Public Works Department plans to expand into a dual carriageway.

The two flyovers have an estimated combined cost of Rs. 3.72 bn and are intended to improve traffic movement towards Nehru Place, Okhla and nearby areas. The Mukarba Chowk underpass has been completed near Gate 3 of Haiderpur Badli Mor Metro station in North Delhi. Work on the Outer Ring Road project had stopped in 2022 during the COVID-19 period before resuming and reaching completion.

Four major road infrastructure projects in Delhi are scheduled to feature at an event on 29 September. Union Home Minister Amit Shah is likely to inaugurate the completed Barapullah Phase 3 elevated corridor and the Mukarba Chowk underpass, besides laying the foundation stones for two new flyovers. The Barapullah corridor is the largest of the four projects and will provide a signal-free connection between Mayur Vihar Phase 1 and South Delhi. It will link with the existing Barapullah corridor at Sarai Kale Khan, creating a continuous route of around 9 km towards AIIMS and other parts of South Delhi. The project was approved in 2014, and construction began in 2015. Although completion was initially planned for 2017, delays increased the revised project estimate to around Rs. 16.35 bn. The corridor is now among the key road links intended to improve movement between eastern and southern parts of the capital. The foundation stones for the Modi Mill-Kalkaji flyover and the Savitri Cinema half-flyover will also be laid at the event. The Modi Mill project forms part of a plan for a 7.2 km signal-free corridor towards IIT Gate, with three lanes in each direction. The Savitri Cinema project involves a 435-metre, three-lane single carriageway, which the Public Works Department plans to expand into a dual carriageway. The two flyovers have an estimated combined cost of Rs. 3.72 bn and are intended to improve traffic movement towards Nehru Place, Okhla and nearby areas. The Mukarba Chowk underpass has been completed near Gate 3 of Haiderpur Badli Mor Metro station in North Delhi. Work on the Outer Ring Road project had stopped in 2022 during the COVID-19 period before resuming and reaching completion.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NDMC Approves Five Prakriti Cafés in Three Delhi Parks

The New Delhi Municipal Council (NDMC) approved the setting up of five Prakriti Cafés across three prominent parks in the capital during its council meeting on Tuesday. The locations include Lodhi Garden, Nehru Park and BRICS Garden on Shanti Path. Two cafés will be developed in Lodhi Garden, while two others will come up in Nehru Park. The remaining café is planned for BRICS Garden. The council granted in-principle approval to explore the project under the Build-Operate-Transfer (BOT) model. Under the proposed arrangement, the selected agency will develop the cafés at its own cost and man..

Next Story
Infrastructure Transport

Air India and Airbus to Build India's First Corporate SAF Programme

Air India and Airbus have partnered to develop a framework for India’s first voluntary corporate Sustainable Aviation Fuel (SAF) programme. The feasibility study will examine how businesses can reduce lifecycle emissions associated with air travel by voluntarily supporting the procurement and use of SAF. Jürgen Westermeier, President and Managing Director of Airbus India and South Asia, and P Balaji, Group Head of Governance, Risk and Compliance and Corporate Affairs at Air India, signed the Feasibility Study Agreement. The signing took place in the presence of Rammohan Naidu Kinjarapu, Min..

Next Story
Infrastructure Energy

Indian Companies to Buy US LPG from Four Firms in 2027

Indian state-run oil companies have awarded a joint tender to Saudi Aramco, Chevron, TotalEnergies Trading SA (Totsa) and Vitol for the import of about 2.75 mn t of US liquefied petroleum gas (LPG) in 2027. The contracts are intended to diversify supplies and reduce India’s reliance on the Middle East. Indian Oil, Bharat Petroleum and Hindustan Petroleum floated the tender in September. They sought four very large gas carrier (VLGC) cargoes each month on a delivered basis and one cargo each month on a free-on-board basis from the US. A VLGC typically carries about 46,000 t of LPG, which cons..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code